13019-11-001A NOT SENSITIVE
ANZY9100563
SPEC NO. 13019-11-001A
30 May 2014
CONSTRUCTION SPECIFICATION
FOR
VKF REVITALIZATION (HVAC-MT&L)
ARNOLD ENGINEERING DEVELOPMENT COMPLEX
ARNOLD AIR FORCE BASE, TENNESSEE 37389-9998
NOT SENSITIVE
IRA-1241
ANZY9100563 Index-1
INDEX
DIVISION 01 GENERAL REQUIREMENTS
01 10 00 Summary 01 33 00 Submittal Procedures 01 45 00 Regulatory Requirements 01 73 29 Cutting and Patching 01 74 19 Construction Waste Management and Disposal
DIVISION 02 EXISTING CONDITIONS
02 08 00 Asbestos Removal 02 08 50 Lead and Heavy Metal Removal 02 08 60 Mold Remediation 02 41 19 Selective Structural/Mechanical Demolition
DIVISION 03 NOT USED
DIVISION 04 MASONRY
04 05 03 Masonry Mortaring and Grouting 04 20 00 Unit Masonry 04 20 19 Veneer Unit Masonry
DIVISIONS 05 - 06 NOT USED
DIVISION 07 THERMAL AND MOISTURE PROTECTION
07 84 00 Firestopping 07 90 00 Joint Protection
DIVISION 08 NOT USED
DIVISION 09 FINISHES
09 21 16 Gypsum Board Assemblies 09 51 23 Acoustical Tile Ceilings 09 65 00 Resilient Flooring 09 68 13 Tile Carpeting 09 72 00 Wall Coverings 09 77 13 Stretched Fabric Wall System 09 90 00 Painting and Coating
DIVISION 10 SPECIALTIES
10 14 00 Plastic Signs
DIVISIONS 10-11 NOT USED
DIVISION 12 FURNISHINGS
12 21 13 Horizontal Louver Blinds
ANZY9100563 Index-2
DIVISIONS 13-20 NOT USED
DIVISION 21 FIRE SUPPRESSION
21 13 13 Wet Pipe Sprinkler Systems
DIVISION 22 NOT USED
DIVISION 23 HEATING, VENTILATING, AND AIR-CONDITIONING
(HVAC)
23 05 29 Hangers and Supports for HVAC Piping and Equipment
23 05 53 Identification for HVAC Piping and Equipment 23 05 93 Testing, Adjusting, and Balancing for HVAC 23 07 00 HVAC Insulation 23 07 50 Piping Insulation 23 09 23 Direct-Digital Control System for HVAC 23 21 13 Hydronic Piping 23 21 16 Hydronic Piping Special Ties 23 21 23 Hydronic Pumps 23 22 13 Steam Condensate Heating Piping 23 22 16 Steam and Condensate Piping specialties 23 22 23 Steam Condensate Pumps 23 31 00 HVAC Ducts and Casings 23 33 00 Air Duct Accessories 23 37 00 Indoor Central-Station Air-Handling Units
DIVISIONS 24 - 25 NOT USED
DIVISION 26 ELECTRICAL
26 05 03 Equipment Wiring Connections 26 05 19 Low-Voltage Electrical Power Conductors and
Cables 26 05 26 Grounding and Bonding for Electrical Systems 26 05 29 Hangers and Supports for Electrical Equipment 26 05 33 Raceways and Boxes for Electrical Equipment 26 05 53 Identification for Electrical Systems 26 09 23 Lighting Control Devices 26 24 16 Panelboards 26 27 26 Wire Devices 26 28 19 Enclosed Switches 26 51 00 Interior Lighting
DIVISION 27 COMMUNICATIONS
27 05 36 Cable Trays for Communications Systems 27 13 43 Communications Services Cabling
ANZY9100563 Index-3
DIVISION 28 ELECTRONIC SAFETY AND SECURITY
28 31 76 Interior Fire Alarm and Mass Notification System
DIVISIONS 29 – 49 NOT USED
ANZY9100563 01 10 00-1
SECTION 01 10 00
SUMMARY
PART 1 GENERAL
1.1 The work consists of all materials, equipment, and labor to demolish and replace the HVAC system and associated piping, ceiling, interior finishes, and provide a fire suppression system for a portion of MT&L Building 676. Work will also include interior furnishes and installation of a mass notification system for the building. All work is to be done at Arnold Engineering Development Center, Arnold Air Force Base, Tennessee. The extent of the work is contained in the drawings and specifications. Major items of work include, but are not limited to, the following:
A. Demolition of existing equipment, interior finishes, ceiling tile/grid, lighting fixtures, HVAC units, ductwork, piping and other miscellaneous items.
B. Asbestos and lead removal: Existing materials to be demolished are assumed to contain asbestos including piping and HVAC flexible connections, duct work in mechanical room, asbestos base, floor tile, and mastics under carpet, and all paint is assumed to contain lead paint. Treat and dispose of in accordance with Sections 02 80 00 and 02 08 50.
C. Mold Remediation: Mold is located in Rooms 116, 116A, and can be located under wallpaper or any interior finishes. Treat and dispose of in accordance with Section 02 08 60.
D. Installation of four air handling units, ductwork, diffusers, HVAC hot water system including pump and heat exchanger, steam condensate pump, direct digital controls (DDC), piping, supports, and accessories.
E. Lighting and power.
F. Suspended acoustical ceiling.
G. Painting, acoustical wall panels, floor covering, signage, wall covering, and blinds.
H. Fire alarm system design and installation.
I. Mass notification system design and installation.
J. Communications.
K. Sprinkler system design and installation by a licensed Fire Protection Engineer.
L. Provide temporary cooling to Room 221.
ANZY9100563 01 10 00-2
M. Perform communication work on the north wing at night or weekends.
N. Allow jobsite access to a systems furniture Contractor to install new furniture prior to power and communication installation.
O. Relocate furniture and personnel boxes to perform work. Furnish a waterproof exterior storage container. Return boxes and furnishings as needed at job completion.
P. Attend weekly construction update meetings to ensure no disruption to control room, user rooms, or high bay during testing.
Q. Other incidental tasks and repairs necessary to complete the work as required.
1.2 DEFINITIONS
A. Certain terms used in the contract documents are defined below.
Definitions and explanations contained in this section are not complete, but are general for the work to the extent that they are not stated more explicitly in another element of the contract documents.
1. Furnish. The term "furnish" means to supply and deliver to the project site, ready for unloading, unpacking, assembly, installation, and similar operations.
2. Install. The term "install" describes operations at the project site, including the actual unloading, unpacking, assembly, erection, placing, anchoring, applying, working to dimensions, finishing, curing, protecting, cleaning, and similar operations.
3. Provide. The term "provide" means "provide complete in place";
that is, "furnish and install.”
4. Indicated. Where "as indicated" or words of similar import are used, it shall be understood that the reference is made to the drawings accompanying this contract unless stated otherwise.
5. Postconsumer material (from FAR clause 52.223-9): a material or finished product that has served its intended use and has been discarded for disposal or recover, having completed its life as a consumer item. Postconsumer material is a part of the broader category of “recovered materials”.
6. Recovered material (from FAR clause 52.223-9): waste materials and by-products recovered or diverted from solid waste. The term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.
7. Biobased product (FAR 2.101): a product determined by the U.S.
Department of Agriculture (USDA) to be a commercial or industrial product (other than food or feed) that is composed, in whole or in significant part, of biological products, including renewable domestic agricultural materials (including plant, animal, and marine materials) or forestry materials.
ANZY9100563 01 10 00-3
8. USDA-designated item (FAR 233.401): a generic grouping of products that are or can be made with Biobased materials (1) that is listed by USDA in a procurement guideline (7 CFR 2902, Subpart B); and (2) for which USDA has provided purchasing recommendations.
1.3 CODES AND STANDARDS
A. AEDC Safety, Health, and Environmental (SHE) Standards latest version, available at http://www.aerospacetestingalliance.com/en/vendors/-site-work/safety-standards/
1. A6 with Supplement User and Subcontractor Safety
(Mandatory Documents/Submittals).
2. A9 Hazard Communications.
3. A10 Job Safety Analysis.
4. B1 Master Work Permit.
5. B2 Lockout/Tagout (LOTO).
6. B3 Control of Hazardous Areas Using
Safety Signs, Tags, and Barricades.
7. B5 Confined Spaces.
8. B6 Low Voltage Electrical Safety Related
Work Practices.
9. D3 Identification of Piping Systems.
10. D6 Aerial Work Platforms.
11. D8 Portable Power Tools.
12. D9 Fixed and Portable Ladders.
13. D10 Scaffolds.
14. E7 Asbestos.
15. E17 Oil and Hazardous Substances Spill
Response.
16. E18 Managing Wastes Containing Chemical or Petroleum Products.
17. E19 Lead and Heavy Metals.
18. F2 Personal Protection Equipment (PPE).
19. F6 Fall Protection.
B. Air Force Federal Acquisition Regulation:
1. AFFARS 2.101 Definitions of Words and Terms.
2. AFFARS 23.401 Use of Recovered Materials Definition.
3. AFFARS 52.223-9 Estimate of Percentage of Recovered
Material Content for EPA-Designated Items.
4. AFFARS 5352.223-9000 Elimination of Use of Class I Ozone Depleting Substances (ODS).
ANZY9100563 01 10 00-4
C. Code of Federal Regulations (CFR):
1. 7 CFR 2902 Subpart B Guidelines for Designating Biobased
Products for Federal Procurement, Designated Items, 2014.
2. 29 CFR 1926.1101 Asbestos, 2014.
3. 40 CFR 261 Identification and Listing of Hazardous
Waste, 2014.
4. 40 CFR 370 EPA Hazardous Chemical Reporting and Community Right to Know Requirement, 2014.
D. US Army Corp of Engineers:
1. USACE EM 385-1-1 Safety and Health Requirements
Manual, 2008.
1.4 JOB CONDITIONS
A. Plan and execute this project in a manner to minimize downtime.
Schedule all work in advance with the Government Representative.
B. Work may require coordination with test schedule. Coordinate with Government Representative.
C. Furnish new components and devices, complete, with all necessary materials for installation to meet this objective.
D. Do not interrupt existing utilities or commence power outages without signed authorization from the Government Representative. Submit each utility outage request for Government approval at least two weeks prior to each requested outage date. Outages may be granted depending upon the Government’s schedule for facility use, and may occur on weekends and/or holidays.
E. Keep work area clean and free from waste and debris. Dispose of waste as directed by the Government Representative.
F. Do not close or obstruct egress width to any building or site exit without written permission from the Government Representative.
G. Do not disable or disrupt building fire or life safety systems without written permission from the Government Representative.
H. Conform to applicable procedures when any hazardous or contaminated materials are discovered.
I. Cease operations immediately for any unsafe conditions and notify the Government Representative. Do not resume operations until authorized by the Government Representative.
ANZY9100563 01 10 00-5
J. Provide temporary barricades and other forms of protection as required to protect Government personnel and the general public from injury due to the work. Provide temporary signage as needed or directed in accordance with AEDC SHE Standard B3.
K. Remove protections at the completion of work.
L. Do not close, block, or otherwise obstruct streets, walks, or other occupied or used facilities without written permission from the Contracting officer.
M. Submit sketches of proposed scaffolding, if utilized. All scaffolding shall be in accordance with AEDC SHE Standard D10 and shall be inspected, approved, and tagged by the Contractor’s scaffold competent person after it has been erected and prior to use.
N. Verify lighting circuits are as indicated on the drawings. Mark up the drawings to show any changes.
O. Submit record as-built drawings.
1.5 PROTECTION OF EXISTING IMPROVEMENTS:
A. Protection of the grounds, walkways and structures from deterioration due to excessive vehicular traffic, equipment disturbance, and material staging is critical to maintaining the quality appearance of AEDC. The Contractor shall protect against damage incurred by service vehicles, construction activities, maintenance and repair, and all other work that detracts from the overall appearance of the grounds and increases the costs of grounds maintenance.
B. Prior to commencement of work, inspect areas in which work will be performed. Submit a report with the Contracting Officer listing existing conditions which could be construed as damage resulting from the work.
The Government Representative may also photograph or video tape areas or improvements susceptible to damage to document conditions prior to the start of work.
C. The activity of vehicles and equipment on the grounds shall be limited to only that which is essential and required for completing the work. The Government Representative will approve all access and haul routes required for the work prior to any on site operations to preclude damage to sensitive utilities or improvements which may not be readily apparent.
D. Minimize travel paths and staging areas to limit the impact and damage to work areas. Lay out the work site, material and equipment staging, and vehicle and equipment activity to minimize visibility and aesthetic impact of activities to surrounding areas.
ANZY9100563 01 10 00-6
E. Protect above and below grade utilities, plant life, lawns, and other features or improvements to remain.
F. Protect benchmarks, existing structures, sidewalks, curbs, and pavements from excavation equipment and vehicular traffic.
G. Use protective materials, such as sheeting, steel plating, rigger pads, to protect grounds and pavement from heavy equipment activity and damage.
H. Protect existing facilities from falling debris during construction such as roof materials, ductwork scraps, or other materials, by use of protective materials such as sheeting, steel plates, netting, or other materials.
I. Provide temporary weather protection during any interval between demolition and removal of existing construction on exterior surfaces and installation of new construction to ensure no water leakage or damage occurs to the structure, interior areas, or contents of the existing facility.
J. Implement a daily procedure for area clean up and organized parking of vehicles and equipment.
K. Provide temporary barricades, shoring, bracing, supports or other forms of protection as required to protect all existing improvements not scheduled to be demolished for both above and below ground improvements and to prevent movement, settlement, collapse or damage of any kind.
L. Maintain personnel and vehicular access and existing utilities to all buildings and other structures during the course of the work. Any changes or interruptions shall be coordinated and approved by the Government Representative well in advance. Temporary protections or services may be required as a condition of approval of any such change or interruption.
M. The Contractor shall be responsible for damage caused by the work and shall repair or replace same to the satisfaction of the Government. Obtain Government Representative’s approval of methods, materials, equipment or products for repair or replacement prior to use. All such repair or replacement shall be performed promptly at no additional cost to the Government. The Government will place special emphasis and requirements for repair or replacement of damage to underground utilities, lawns, grassed areas, existing structures, sidewalks, curbing, railings and pavements.
N. Remove all temporary barricades, shoring, bracing, supports or other forms of protection at completion of work. Restore all adjacent structures and surfaces to conditions existing prior to construction. Clean up all stockpiles and spoil areas, and restore all surrounding areas to conditions existing prior to construction.
ANZY9100563 01 10 00-7
1.6 SAFETY REQUIREMENTS:
A. All work shall be accomplished in compliance with AEDC SHE Standards A6 with supplement, A9, A10, B1, B2, B3, B5, B6, D3, D6, D8, D9, D10, E7, E17, E18, E19, F2, and F6. Submit a safety and health plan in accordance with AEDC SHE Standard A6 and USACE EM 385-1-1.
1.7 DISPOSAL OF CONTAMINATED EQUIPMENT
A. The Contractor shall clean equipment or material of contaminants prior to disposal at the AEDC Salvage Yard (with the exception of lead paint, unless the paint is flaking in which case the flaking paint shall be removed prior to transport to prevent contamination during transport). If cleaned, equipment is to be turned-in to the Government for storage or excessing, a GC-1785, Special Material Turn-in Certification, shall be completed and submitted to the Government with the equipment or material prior to disposal. The Government Representative will assist the Contractor in filling out the form and in coordinating with Industrial Hygiene and Environmental Quality.
1.8 CONNECTIONS TO POTABLE WATER
A. Contractor shall not make any connections to an AEDC potable water system without specific approval from the Government Representative.
B. Notify Government Representative if connections to hose bibs are needed. Do not connect to any hose bibs without Government-supplied backflow preventer and specific approval from Government Representative.
1.9 DELIVERY, STORAGE, AND HANDLING
A. Deliver all equipment properly packaged in factory containers and/or mounted on shipping skids.
B. Provide and store all equipment in a clean, dry space, and protect from dirt, fumes, moisture, construction debris, and traffic. Ensure that all equipment is prepared for anticipated storage conditions.
C. Where equipment is stored outdoors, ensure electrical components are stored above grade and enclosed with watertight wrapping. Provide 120V temporary power to space heaters or provide temporary heat if required to protect equipment.
D. Notify Government Representative a minimum of two weeks prior to delivery of large equipment being stored on-site. Contractor shall offload equipment at a location designated by the Government Representative.
ANZY9100563 01 10 00-8
E. All handling, loading, and offloading of all equipment shall be done by the Contractor.
F. Handle and store all equipment in accordance with manufacturer’s instructions.
1.10 TOOL CONTROL: Coordinate tool control with the Government Representative.
1.11 EPA-DESIGNATED ITEMS
A. The Contractor, on completion of this contract in accordance with AFFARS 52.223-9, shall:
1. Estimate the percentage of the total recovered material content for
EPA-designated item(s) delivered and/or used in contract performance, including, if applicable, the percentage of post-consumer material content; and
2. Submit this estimate to the Contracting Officer.
1.12 ELIMINATION OF ODS CHEMICALS
A. The use of Class I ozone depleting substances (ODS) is prohibited.
Reference text of AFFARS clause 5352.223-9000 (April 2003).
1.13 DISALLOWED PRODUCTS
A. Do not use products or materials that contain lead, chromium, mercury, cadmium, silver, barium, selenium, beryllium, or arsenic on this project except as expressly authorized by the Contracting Officer. If no substitutes for products containing the listed materials are available, and the Contracting Officer approves the use of products containing the listed materials, highlight and detail their exact location on the drawings.
1.14 ASBESTOS PRODUCTS
A. Do not use products or materials that contain asbestos on this project except as expressly authorized by the Contracting Officer. If no substitutes for asbestos products are available, and the Contracting Officer approves the use of asbestos products, highlight and detail their exact location on the drawings and identify their location in the field following 29 CFR
1926.1101 guidelines.
1.15 HAZARDOUS WASTE
A. Where hazardous waste (as identified in 40 CFR 261) is generated, follow the procedures in AEDC SHE Standard E18, Chemical and Petroleum Products Waste Management, for storing and turning in hazardous waste.
These procedures include the requirement to complete Forms GC-565 and GC-1337, which will be furnished by the Government Representative.
ANZY9100563 01 10 00-9
1.16 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA
A. The following procedures shall be followed to meet 40 CFR 370, EPA Hazardous Chemical Reporting and Community Right to Know Requirement.
1. Procedures:
a. The Contractor shall furnish information on the hazardous materials he brings on AEDC property prior to beginning on-site work. Hazardous materials may include solvents, paints, adhesives, acids, or any other substance which could be included within the definitions in paragraph 2.
b. The information required is:
1) Company name, point of contact, and phone number.
2) Brief statement indicating how the hazardous material will be used within the scope of the contract.
3) List of all hazardous materials to be used (product name, manufacturer’s name, and address).
4) Amount of each material to be stored on site and where it will be stored.
5) Where the product Safety Data Sheet (SDS) will be maintained.
c. All unused product is the responsibility of the Contractor and shall be removed from AEDC property at the completion of the project.
d. The Contractor shall coordinate with the Government Representative and the Hazardous Waste Operations Group (454-3628) if any hazardous waste is to be generated.
2. Definitions
a. Hazard communication standard. A chemical right-to-know law under OSHA that requires chemical manufacturers and importers to assess the hazards of chemicals they make or import and to distribute this information to inform workers of the hazards associated with these chemicals. This written information is a Safety Data Sheet (SDS).
b. Hazard classes. Hazardous materials that have been grouped into classes by the Department of Transportation (DOT). These classes include explosives, flammables, oxidizers and organic peroxides, compressed gases, corrosives, and poisons.
c. Hazardous material. Any substance that may be harmful when used. Specific substances have been designated as hazardous under the Clean Water Act, the Resource and Conservation and Recovery Act, and the hazardous air pollutants under the Clean Air Act.
d. Hazardous waste. Any waste that may cause or significantly contribute to serious illness or death or that may pose a substantial threat to human health or the environment, if not
ANZY9100563 01 10 00-10
properly managed. Hazardous wastes may be solids, liquids, semi-solids, or compressed gases.
1.17 PROPRIETARY AND BRAND NAMES: Proprietary and brand names used in this document are meant to describe physical, performance, and quality characteristics of items and materials, and are not meant to limit competition or exclude Contractors, Vendors, or Manufacturers from submitting like products to the Contracting Officer for approval.
END OF SECTION
ANZY9100563 01 33 00-1
SECTION 01 33 00
SUBMITTAL PROCEDURE
PART 1 GENERAL
1.1 DESCRIPTION OF REQUIREMENTS. This section specifies procedural requirements for non-administrative submittals, including but not limited to shop drawings, product data, manufacturer’s certificate, design data, calculations, and verifications, manufacturer’s instructions, manufacturer’s field service reports, samples, operation and maintenance manuals, and other miscellaneous work-related submittals. These submittals are required to amplify, expand, and coordinate other information contained in the contract. This section describes the type and content of submittals that may be required for this work. The required submittals are included in the Statement of Work or Specification.
Non-work-related submittals are addressed elsewhere in the contract rather than in the specification and may include items such as: contract progress schedule, permits, payment applications, performance and payment bonds, insurance certificates, and progress reports.
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections of the specification or statement of work.
1.2 SUBMITTAL PROCEDURE
A. Definition: For the purposes of this section, the term “Contractor” denotes the prime Contractor.
B. Listing: At the end of this section is a summarized listing of item submittals requiring approval for the work. The listing is included for the convenience of users of the contract documents. The listing may not be all inclusive and additional item submittals may be required. Within 14 calendar days after receiving contract award, Contractor shall submit a copy of the summarized submittal listing with calendar dates assigned to each item submittal indicating when submittal will be received by the Government. If contract requires a pre-construction conference, Contractor may submit completed submittal listing at the conference.
C. Risk: Do not proceed with the part of the work covered by an item submittal including purchasing, fabricating, and delivering until approval is received. Machinery, equipment, material, and articles that do not have the required approval shall be installed or used at the risk of subsequent rejection. Any fabrication or other work performed in advance of the receipt of accepted item submittals and approvals shall be entirely at the Contractor’s risk and expense.
D. Transmittal Timing: Coordinate the preparation and processing of item submittals with the performance of the work. Prepare and transmit each
ANZY9100563 01 33 00-2
item submittal to the Contracting Officer sufficiently in advance of the performance of related work and other applicable activities. Transmit related item submittals for the same unit of work so that processing will not be delayed by the Government's need to review submittals concurrently for coordination. No delay damages or time extensions will be allowed for time lost in late submittals.
E. Content: Each submittal shall be complete and in sufficient detail to allow ready determination of compliance with contract requirements. All submittals which are generic and list more information than is specifically required shall be marked to identify required information. Complete AF Form 3000 and attach as cover sheet for each submittal. Contractor may include multiple item numbers on an AF Form 3000.
F. Language: All item submittals shall be written in English, including documents, notes on drawings, sketches, and/or samples, calculations, manuals, and all other instances of written text and communication.
G. Units: All item submittals shall be marked or show dimensions and values in the same units as specified in the contract documents.
H. Review Time: Allow sufficient time so that contract performance will not be delayed as a result of the time required to properly process submittals, including time for re-submittals, if necessary. Allow 14 calendar days for initial Government processing of each submittal. No extension of time will be authorized because of the Contractor's failure to transmit submittals to the Government sufficiently in advance of the work.
I. Contractor Certification: All submittals shall be carefully reviewed by an authorized representative of the Contractor prior to submission to the Government. Each submittal shall be dated, signed, and certified by the Contractor as being correct and in strict conformance with the contract documents. No consideration for review by the Government of any Contractor’s submittal will be made for any items which have not been so certified by the Contractor. All noncertified submittals will be returned to the Contractor without action taken by the Government, and any delays caused thereby shall be the total responsibility of the Contractor.
J. Deviations: Should any item submittals required by the contract documents show deviations from the contract requirement, the Contractor shall make specific mention of such deviations in the letter of transmittal, including stating cost effects, and product and system limitations which may adversely affect the work, in order that if acceptable, suitable action may be taken for proper adjustment of the contract; otherwise the Contractor will not be relieved of the responsibility for executing the work in accordance with the contract documents and the approved submittals.
Contractor shall clearly mark the proposed variation in all documentation and specifically point out deviations from contract requirements in transmittal letters. Failure to point out deviations may result in the
ANZY9100563 01 33 00-3
Government requiring rejection and removal of such work at no additional cost to the Government. Deviations from contract requirements require Government approval and will only be considered when advantageous to the Government. When proposing deviations, deliver written request to the Contracting Officer, with documentation of the nature and features of the deviation and why the deviation is desirable and beneficial to the Government. If lower cost is a benefit, include an estimate of the cost savings. In addition to documentation required for deviation, include the submittal information required for the item. Allow an additional 14 calendar days beyond normal submittal review period for consideration by the Government of submittals with deviations.
K. Approved Submittals: The part of the work covered by the approved item submittal may proceed provided it complies with the requirements of the contract documents. Final acceptance will depend upon that compliance.
The term “Approved” shall only indicate that there is no exception taken to the submittal. Approval of the item submittal shall not be construed as a complete check, and indicates only that the general method or other information appears to meet the contract requirements. Approval does not relieve the Contractor of the responsibility for any error which may exist.
After item submittals have been approved by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment, or changes to any other information will be considered unless accompanied by an explanation of why a substitution or change is necessary.
L. Disapproved Submittals: Contractor shall correct disapproved item submittals and resubmit for approval within timeframe noted. If no date is given, Contractor shall submit corrected submittal within 14 calendar days.
If the Contractor considers any correction or notation on the returned submittal to constitute a change to the contract drawings, specification, or statement of work the Contractor shall notify the Contracting Officer.
M. Responsibility: The Government’s review of Contractor submittals shall not relieve the Contractor of the entire responsibility for the correctness of details and dimensions and conformance to the specifications. The Contractor shall assume all responsibility and risk for any mistakes and/or costs due to any errors in submittals.
N. Inconsistencies: If a conflict or inconsistency arises between an approved item submittal and the contract documents, the contract documents shall govern.
1.3 SPECIFIC SUBMITTAL DESCRIPTIONS AND REQUIREMENTS: Submittal requirements for individual units of work are specified in the applicable specification section or Statement of Work (SOW). Except as otherwise indicated in the individual specification sections or SOW, comply with the following requirements for each type of submittal.
ANZY9100563 01 33 00-4
A. Shop Drawings: These are technical drawings and data specially prepared for this contract including fabrication and installation drawings, setting and seaming diagrams, and coordination drawings (for use on-site). Shop drawings include drawings, diagrams and schedules specifically prepared to illustrate some portion of the work, diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project, or drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated. Information required on shop drawings includes dimensions, identification of specific products and materials which are included in the work, compliance with specified standards, and notations of coordination requirements with other work.
Provide special notations of dimensions that have been established by field measurements. Highlight, encircle, or otherwise indicate deviations from the contract documents on the shop drawings. Furnish one hard copy and one electronic copy in AutoCAD 2005 through 2010 drawing file format (.dwg). The only permissible text font is ROMANS. Custom fonts and shapes are prohibited. The minimum allowable font size shall be 0.125-inch. The maximum allowable font size shall be 0.25-inch.
B. Product Data: This data includes standard printed information on manufactured products that has not been specially prepared for this contract, including manufacturers' product specifications illustrating size, physical appearance and other characteristics of materials, installation instructions, standard color charts, catalog cuts, illustrations, schedules, standard wiring diagrams, standard product operating and maintenance manuals, and samples of warranty language when the contract requires extended product warranties. General information required specifically as product data includes manufacturers' standard printed recommendations for application and use, compliance with recognized standards of trade associations and testing agencies, the application of their labels and seals (if any), special notation of dimensions which have been verified by way of field measurement, and special coordination requirements for interfacing the material, product, or system with other work. Furnish three hard copies and one electronic copy.
C. Samples: These are physical examples of work, including, swatches showing color, texture, and pattern, color-range sets, and units of work to be used for independent inspection and testing. Samples include fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged, color samples from the manufacturer’s standard line (or custom color samples if specified) to be used in selecting or approving colors for the project, and field samples and mock-ups constructed on the project site to establish standards by which the ensuring work can be judged. This includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at
ANZY9100563 01 33 00-5
conclusion of the work. Submit samples for the Contracting Officer's visual review of general kind, color, pattern, and texture for a final check of the coordination of these characteristics with other related elements of the work and for quality control comparison of these characteristics between the final sample submittal and the actual work as it is delivered and installed. Submit one each.
D. Design Data: Design data includes design calculations, mix designs, analyses or other data pertaining to a part of work. Refer to individual sections of the specification or statement of work for required quantities, formats, and signatures or certifications required. Furnish three hard copies and one electronic copy.
E. Test Plans and Reports: Test plans shall include planned testing, including a description of the test, equipment and supplies needed, and step-by-step notation of test activities and tasks. Test reports include reports signed by an authorized official of a testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accordance with the specified requirements.
Testing shall have been within three years of date of contract award for the project. Reports also include findings of tests required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to the job site, findings of tests made at the job site or on a sample taken from the job site, investigation reports, daily logs and checklists, and final acceptance test and operational test procedures. Furnish three hard copies and one electronic copy of each such report required.
F. Certificates: These include statements printed on the manufacturer’s letterhead and signed by the responsible officials of the manufacturer of a product, system or material attesting that the product, system or material meets specification requirements. Certificates include documentation required of the Contractor, or of a manufacturer, supplier, installer or subcontractor through the Contractor, to further demonstrate the quality of orderly progressions of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications. Examples include confined space entry permits, and text of posted operating instructions.
Certificates shall be dated after award of the project contract and clearly name the project. Furnish three hard copies and one electronic copy of each certificate required.
G. Manufacturer’s Instructions: Preprinted material describing installation of a product, system or material, including special notices and Material Safety Data sheets concerning impedances, hazards and safety precautions.
Furnish three hard copies and one electronic copy.
H. Manufacturer’s Field Reports: Documentation of the testing and verification actions taken by a manufacturer’s representative at the job site, in the vicinity of the job site, or on a sample taken from the job site, ANZY9100563 01 33 00-6 on a portion of the work, during or after installation, to confirm compliance with the manufacturer’s standards or instructions. The documentation shall be signed by an authorized official of a testing laboratory or agency and shall state the test results, and indicate whether the material, product, or system has passed or failed the test. Furnish three hard copies and one electronic copy.
I. Operation and Maintenance Data: Data furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer’s help and product line documentation necessary to maintain and install the equipment, and needed by operating and maintenance personnel for the safe and efficient operation, maintenance, and repair of the item. The data is intended to be incorporated in an operations and maintenance manual or control system.
Furnish two hard copies and one electronic copy.
J. Final Design Drawings and Documentation: Final design documentation including drawings, specifications, estimates, and other required deliverables. Electronic documentation submitted shall include every associated component file of drawings and other documentation, including raster images, jpeg, tiff, Excel, and any related items required to view, modify, or manipulate the electronic files. Furnish a CD-ROM of all final design documentation, and drawings in AutoCAD 2005 through 2010 drawing file format (.dwg), to the Contracting Officer for approval prior to applying for final payment. The drawings shall be fully editable using AutoCAD software. In addition, drawings shall be delivered to clearly show the location and arrangement of all materials and equipment. The only permissible text font is ROMANS. Custom fonts are shape files are prohibited. The minimum allowable font size shall be 0.125-inch. The maximum allowable font size shall be 0.25-inch.
K. Record (As-Built) Drawings: Record drawings showing final configuration of work accomplished. Show all changes, additions, and deviations from the original contract drawings and documentation. If no changes occur, furnish certification to that effect. Drawings shall be redlined electronic drawings, unless waived by the Government, and shall accurately show as-built conditions during the progress of the job. Furnish drawings on a CD-ROM, in AutoCAD 2005 through 2010 format, including every associated component file of the drawings, including raster images, jpeg, tiff, Excel, and any related items required to view, modify, or manipulate the electronic files. Submit to the Contracting Officer for approval prior to applying for final payment.
L. Miscellaneous Submittals: These are work-related, non-administrative submittals that do not fit in the previous categories, including the following:
1. Maintenance agreements. Furnish one hard copy and one electronic copy.
2. Survey data and reports. Furnish one hard copy and one electronic copy.
ANZY9100563 01 33 00-7
3. Project photographs. Furnish both hard copies and digital files.
4. Keys and other security protection devices.
5. Maintenance tools, spare parts, and overrun or maintenance stock.
Refer to individual sections of the specification for required quantities of spare parts, extra and overrun stock, maintenance tools and devices, keys, and similar physical units to be submitted.
6. Qualification certificates. Furnish one hard copy and one electronic copy.
7. Employee training certificates and documentation showing successful completion of training.
8. Documentation of percentage of recovered material content used during contract.
9. Contractor safety and work plans and schedules.
10. Warranties.
1.4 REQUIRED SUBMITTALS
No. Section Reference Description Due 1 01 10 00 para 1.4D Outage Request 2 weeks prior to outage 2 01 10 00 para 1.4M Proposed Scaffolding Before assembly and use 3 01 10 00 para 1.4O Record As-Built Drawings Before final inspection 4 01 10 00 para 1.5B Existing Conditions Report Which could be Construed as Damage Resulting from Work
Before beginning work
5 01 10 00 para 1.6A Safety and Health Plan 10 days after contract award
6 01 10 00 para 1.7A Form GC-1785 Prior to disposal 7 01 10 00 para 1.11.A.2 Percentage of Recovered Material
Content Before final inspection
8 01 10 00 para 1.13A Disallowed Products Locations Before final inspection 9 01 10 00 para 1.14A Asbestos Locations Before final inspection 10 01 10 00 para 1.15A Forms GC-565 and GC-1337 Before final inspection 11 01 10 00 para 1.16.A.1.a Hazardous Material Info Before beginning on-site work 12 01 33 00 para 1.2B Summarized submittal listing with delivery dates 14 days after contract award 13 01 73 29 para 1.2A Proposed Procedures for Cutting and
Patching 2 weeks prior to the procedure 14 01 73 29 para 1.2B Proof of Duro-Last Roof Installer Before beginning on-site work 15 01 73 29 para 1.2C Warranty Before pre-final inspection 16 01 74 19 para 1.4A Construction Waste Management
Plan Before beginning on-site work
Table I. Required submittal list - Continued
ANZY9100563 01 33 00-8
No. Section Reference Description Due 17 02 08 00 para 1.3A Employee Certification Before beginning on-site work 18 02 08 00 para 1.3B Training and Medical Certifications Before beginning on-site work 19 02 08 00 para 1.3C Training and Hazard
Communications Certification Before beginning on-site work 20 02 08 00 para 1.3D Product List Before beginning on-site work 21 02 08 00 para 1.3E Equipment List Before beginning on-site work 22 02 08 00 para 1.3F Notice of Violation Before beginning on-site work 23 02 08 00 para 1.3G Environmental, Health, and Safety
Plan Before beginning on-site work 24 02 08 00 para 1.3H Asbestos Removal Plan Before beginning on-site work 25 02 08 00 para 1.3I Air Sampling Reports Before beginning on-site work 26 02 08 00 para 1.3J Testing Certifications Before beginning on-site work 27 02 08 00 para 1.3K CPR Certification Before beginning on-site work 28 02 08 00 para 1.3L Insurance Coverage Certification Before beginning on-site work 29 02 08 00 para 1.3M Sampling List Before beginning on-site work 30 02 08 00 para 1.3N Operator’s Log and Shipper’s Log Before beginning on-site work 31 02 08 00 para 1.3O Daily Logs: Sign-In and Field Notes Before beginning on-site work 32 02 08 50 para 1.4A Employee Certification Before beginning on-site work 33 02 08 50 para 1.4B Training and Medical Certification Before beginning on-site work 34 02 08 50 para 1.4C Notice of Violation Before beginning on-site work 35 02 08 50 para 1.4D Environmental, Health, and Safety
Plan Before beginning on-site work 36 02 08 50 para 1.4E Training and Hazard
Communications Certification Before beginning on-site work 37 02 08 50 para 1.4F Product List Before beginning on-site work 38 02 08 50 para 1.4G Lead Abatement Plan Before beginning on-site
ANZY9100563 01 33 00-9
No. Section Reference Description Due 39 02 08 50 para 1.4H Air & Substrate Sampling Reports Before beginning on-site work 40 02 08 50 para 1.4I Testing Laboratory Qualifications Before beginning on-site work 42 02 08 50 para 1.4J Air Monitoring Results Before beginning on-site work 43 02 08 50 para 1.4K Equipment List Before beginning on-site work 44 02 08 50 para 1.4L Rental Equipment List Before beginning on-site work 45 02 08 50 para 1.4M Shower Water Test Results Before beginning on-site work 46 02 08 60 para 1.4A Employee Certification Before beginning on-site work 48 02 08 60 para 1.4B Training and Medical Certification Before beginning on-site work 49 02 08 60 para 1.4C Notice of Violation Before beginning on-site work 50 02 08 60 para 1.4D Environmental, Health, and Safety
Plan Before beginning on-site work 51 02 08 60 para 1.4E Training and Hazard
Communications Certification Before beginning on-site work 52 02 08 60 para 1.4F Product List Before beginning on-site work 53 02 08 60 para 1.4G Mold Remediation/Abatement Plan Before beginning on-site work 54 02 08 60 para 1.4H Daily Logs: Sign-In and Field Notes Before beginning on-site work 55 02 08 60 para 1.4I Air Monitoring Results Before beginning on-site work 56 02 08 60 para 1.4J Testing Laboratory Qualifications Before beginning on-site work 57 02 08 60 para 1.4K Air Monitoring Before beginning on-site work 58 02 08 60 para 1.4L Equipment List Before beginning on-site work 59 02 08 60 para 1.4M Equipment Rental Notifications Before beginning on-site work 60 02 08 60 para 1.4N Shower Water Test Results Before beginning on-site work 61 02 41 19 para 1.2A Demolition Plan and Schedule Before beginning on-site work 62 04 20 19 para 1.3A Product Data Before beginning on-site
ANZY9100563 01 33 00-10
No. Section Reference Description Due 63 04 20 19 para 1.3B Samples Before beginning on-site work 64 04 20 19 para 1.3C Manufacturer’s Certificate Before installation 65 07 84 00 para 1.3A Manufacturer’s Installation
Instructions Before beginning on-site work 66 07 84 00 para 1.3B Product Data Prior to purchasing 67 07 90 00 para 1.3A Product Data Prior to purchasing 68 09 51 23 para 1.3A Product Data Prior to purchasing 69 09 51 23 para 1.4B Samples Prior to purchasing 70 09 65 00 para 1.5A Product Data Prior to purchasing 71 09 65 00 para 1.5B Substituted Materials Brand Name and Samples Prior to purchasing
72 09 68 13 para 1.3A Samples Prior to purchasing 73 09 68 13 para 1.3B Warranty Prior to pre-final inspection 74 09 72 00 para 1.3A Samples Prior to purchasing 75 09 72 00 para 1.3B Test Reports Prior to purchasing 76 09 77 13 para 1.4A Samples Prior to Purchasing 77 09 77 13 para 1.4B Manufacturer’s Installation
Instructions Prior to Purchasing
78 09 90 00 para 1.4A Product Data Prior to purchasing 79 09 90 00 para 1.4B Samples Prior to purchasing 80 10 14 00 para 1.2.A Shop Drawings Prior to purchasing 81 10 14 00 para 1.2.B Samples Prior to purchasing 82 10 14 00 para 1.2.C Manufacturer’s Installation
Instructions Prior to installation
83 21 13 13 para 1.4A Design Drawings, Calculations, and Flow Test
Prior to installation
84 12 21 13 para 1.3A Product Data Prior to Purchasing 85 12 21 13 para 1.3B Samples Prior to Purchasing 86 21 13 13 para 1.4B Product Data Prior to purchasing 87 21 13 13 para 1.4C Maintenance Data Prior to pre-final inspection 88 21 13 13 para 1.4D Certification 14 days after contract award 89 21 13 13 para 1.4E Test Date 2 weeks prior to test 90 21 13 13 para 1.4F Test Reports 2 weeks after test 91 21 13 13 para 1.4G Backflow Test Report 2 weeks after test 92 23 05 29 para 1.3A Hanger and Supports Product Data Before beginning on-site work 93 23 05 29 para 1.3B Manufacturer’s Installation
Instructions Before beginning on-site
ANZY9100563 01 33 00-11
No. Section Reference Description Due 94 23 05 53 para 1.3A Nameplate and Pipe Marker Sample Before beginning on-site work 95 23 05 93 para 1.4A Testing, Adjusting, and Balancing
Reports Before final inspection
96 23 05 93 para 1.4B Adjusting And Balancing Agency 14 days after contract award
97 23 05 93 para 1.4C Project Record Documents Before final inspection 98 23 07 00 para 1.3A Product Data Before beginning on-site work 99 23 07 00 para 1.3B Manufacturer’s Installation
Instructions Before beginning on-site work 100 23 07 50 para 1.3A Product Data Before beginning on-site work 101 23 07 50 para 1.3B Manufacturer’s Instructions Before beginning on-site work 102 23 09 23 para 1.2A Manufacturer’s Literature Before beginning on-site work 103 23 09 23 para 1.2B Shop Drawings Before beginning on-site work 104 23 09 23 para 1.2C Test Data Before final inspection 105 23 09 23 para 1.2D Graphics Page Files Before final inspection 106 23 09 23 para 1.2E Warranty Before final inspection 107 23 21 13 para 1.4A Test Reports Before final inspection 108 23 21 13 para 1.4B Product Data Before beginning on-site work 109 23 21 16 para 1.3A Product Data Before beginning on-site work
110 23 21 16 para 1.3B Installer Certification Before beginning on-site work
111 23 21 16 para 1.3C Manufacturer’s Installation Instructions
Before beginning on-site work
112 23 21 16 para 1.3D Operation and Maintenance Data Prior to pre-final inspection
113 23 21 23 para 1.3A Product Data Before beginning on-site work
114 23 21 23 para 1.3B Test and Inspection Reports 2 weeks after test 115 23 21 23 para 1.3C Operation and Maintenance Data Prior to pre-final inspection 116 23 21 23 para 1.3D Warranty Prior to pre-final inspection 117 23 22 13 para 1.3A Product Data Before beginning on-site
ANZY9100563 01 33 00-12
No. Section Reference Description Due 118 23 22 13 para 1.3B Manufacturers Catalog Information Before beginning on-site work 119 23 22 13 para 1.3.C Hydrostatic Pressure Test Reports Prior to final inspection 120 23 22 13 para 1.3D Welding Procedures Before beginning on site work 121 23 22 13 para 1.3E Welder Qualifications and
Certifications 14…
This is the start of the file's text. The full file is on GovTribe.