A1_AFRL-14087-Project_Manual.pdf
PDF 2 MB Posted
- Attached to
- Enclose Hangar Door Federal contract opportunity
- Solicitation number
- FA8751-15-R-0006
About this file
Atch 1 - Project Manual
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA8751-15-R-0006-0001.pdf | ||
| 15R0006_Solicitation_Q A_17Sep.docx | DOCX document | |
| 15R0006_Solicitation_Q A_16Sep.docx | DOCX document | |
| A5_Wage_Determination.pdf | ||
| A2_Drawings.pdf | ||
| FA8751-15-R-0006_SOLICITATION.pdf | ||
| A3__PPQ.doc | DOC document | |
| A4_RRS_Form_31.pdf | ||
| AFRL-14087-Final-Submission-Specifications-2014-09-12-.pdf | ||
| AFRL-14087-Final-Submission-Drawings-2014-09-12.pdf | ||
| 15r06_a08_acq_plan_PPQ.doc | DOC document | |
| 15r06_a08_acq_plan_LM.doc | DOC document |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ENCLOSE HANGAR DOOR, BUILDING 101
Located at
AIR FORCE RESEARCH LABORATORY
ROME RESEARCH SITE
ROME, NEW YORK 13441
PROJECT NR: ULDF 140003 DATED: 4 June 2015
ADDENDUM 1
1. The Following changes/additional work are required for this project:
- Section 07 42 14, Part 1.6A
Change: Correct defective Work warranty from “five year period” to “one year period”.
- Section 07 90 05, Part 2.1A.2 Add: d. Joints between insulated metal panels and other insulated metal panels per manufacture specifications.
- Section 08 36 13, Part 1.5A
- Section 08 43 13, Part 1.7A
BDA #14087
64 South Street
Auburn, New York 13021 Telephone: (315) 253-7301
Fax: (315) 253-7306 Email: bda@beardsley.com
PROJECT MANUAL
for
AIR FORCE RESEARCH LABORATORY
Rome, New York
Enclosed Hangar Door, Building 101
Project NR: ULDF #140003AE
September 12, 2014
Air Force Research Laboratory ULDF #140003AE
TABLE OF CONTENTS - 1
PROJECT TABLE OF CONTENTS
DIVISION 01 – GENERAL REQUIREMENTS
01 01 00 PROJECT PROVISIONS
01 10 00 SUMMARY
DIVISION 02 – EXISTING CONDITIONS
02 83 04 HANDLING OF LEAD CONTAINING MATERIALS
DIVISION 05 – METALS
05 12 00 STRUCTURAL STEEL FRAMING
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
07 25 00 WEATHER BARRIERS
07 42 14 INSULATED METAL WALL PANELS
07 90 05 JOINT SEALERS
DIVISION 08 – OPENINGS
08 11 13 HOLLOW METAL DOORS AND FRAMES
08 36 13 SECTIONAL DOORS
08 43 13 ALUMINUM-FRAMED STOREFRONTS
08 71 00 DOOR HARDWARE
08 80 00 GLAZING
DIVISION 26 – ELECTRICAL
26 05 19 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
26 05 29 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
26 05 33 RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS
25 05 53 INDENTIFICATION FOR ELECTRICAL SYSTEMS
26 28 16 ENCLOSED SWITCHES AND CIRCUIT BREAKERS
26 56 00 EXTERIOR LIGHTING
END OF TABLE OF CONTENTS
PROJECT PROVISIONS 01 01 00 - 1
SECTION 01 01 00
PROJECT PROVISIONS
1.1 SCOPE
A. The work covered under this Contract consists of furnishing all labor, equipment, devices, and materials and performing all work required to perform complete construction of new infill insulated metal panel wall system, with personnel door, sectional overhead door and storefront windows in existing hangar door opening of
Building 101 at Rome Site in accordance with these technical specifications and applicable drawings.
1.2 SUBMITTALS
A. The Contractor shall provide to the Government’s Representative at the end of the project a chemical inventory including products, quantities used, and material safety data sheets (MSDS).
1.3 REFERENCED CODES AND STANDARDS
A. Codes and Standards referred to in this specification shall be the latest adopted issue at the Date of Bid, unless otherwise specifically indicated.
1.4 LOCATION
A. The work area is designated as :
1) Building 101 on the Contract Drawings at the Air Force Research Laboratory, Research Site, within the City of Rome, New York.
1.5 PRINCIPAL FEATURES
A. The work to be performed includes the following principal features:
1. Construction of a new infill wall system in the existing hangar door opening at
Building 101. Wall system consists of steel columns, girts, and insulated wall panels. Wall includes a sectional overhead door, hollow metal personnel door and storefront window system.
2. Incidental electrical work including power to overhead door, door security, and disconnection of existing hangar doors.
B. The above description of work is for the purpose of general information only and is not intended to include and describe every feature of work or to define the scope of the work.
PROJECT PROVISIONS 01 01 00 - 2
1.6 UTILITIES
A. All reasonable quantities of electricity and water will be made available to the
Contractor without cost to the Contractor. The Contractor will be responsible for all connections of utilities from the existing supply points. The Government will identify service tie-in points. The Government will not be held responsible for interruptions of utility service and will not be liable for Contractor delays, damages, or increased costs occasioned by any such interruption of service.
1.7 SANITARY FACILITIES
A. There are existing sanitary facilities available.
1.8 FIRE PROTECTION
A. The Contractor shall perform all work in a fire-safe manner in accordance with fire prevention standards of the Rome Research Site. The Contractor shall have an approved fire extinguisher at the site at all times during working operations. HALON
AND C02 TYPE FIRE EXTINGUISHERS ARE NOT AUTHORIZED FOR USE. The
Contractor will call the City of Rome Fire Department, 315-339-7784, before working with any flame or spark producing equipment such as tar buckets, grinders, or welders. The Contractor shall contact RIOC Contract Representative for approval of the contractor’s safety measures and to obtain a "Burn Permit" for this type of work.
1.9 POLLUTION CONTROL
A. The Contractor will perform all work consistent with the requirements of all Federal, State and Local laws, rules and regulations pertaining to pollution control.
1.10 WORK CONDITIONS
A. The Contractor is required to protect persons and property throughout the progress of the work. The work area will be kept clean of all debris at all times. All flammables and combustibles stored on-site must be kept in a designated storage area and an approved locker for flammables, both of which are approved by the Contracting Officer or his designated representative.
1.11 HAZARDOUS MATERIALS (HAZMAT) MANAGEMENT
A. In accordance with IAW Far Clause 52.223-3, each offeror must provide the
Contracting Officer with a list of proposed HAZMAT that it plans to use on Rome
Research Site during the performance of the Contract. In accordance with IAW
AFFARS Clause 5352.223-9003, contractors must obtain Air Force authorization prior to using HAZMAT on an Air Force installation, and must report usage data to RIOCV.
B. Contractors must submit to the Contracting Officer a chemical inventory and MSDS’s necessary to obtain HAZMAT usage authorization. The Contracting Officer will transmit the Contractor submittal to RIOCV for processing.
C. For each Contractor-identified HAZMAT that RIOCV determines does not meet the Air Force definition of a HAZMAT, the requirements below do not apply. The HMMP team will notify the Contracting Officer that the Contractor has the authorization to bring and use that material on the installation without reporting usage.
PROJECT PROVISIONS 01 01 00 - 3
D. For each Contractor-identified HAZMAT that meets the Air Force definition of a HAZMAT, RIOCV will require the Contractor to submit for authorization an AF Form
3952.
E. RIOCV ensures entry of the contractor supplied information into the standardized Air
Force HAZMAT tracking system.
F. Contractor will report usage data on the HAZMAT used every 60 days. If the duration of the contract is less than 60 days, Contractor can report usage at the end of the contract.
G. If the Contractor needs to bring a material on the installation that was not included in the original HAZMAT listing, the Contractor must first notify the Contracting Officer and then obtain prior authorization if RIOCV team determines the material to be a
HAZMAT.
1.12 WORKMANSHIP
A. All work to be performed under this Contract shall be under the supervision of workmen skilled in the trades involved. Special qualifications for certain work are listed in the appropriate sections of this specification.
1.13 SUBMITTAL PROCEDURES
A. All items indicated in the Schedule of Material Submittals shall be submitted for approval:
1. Any other items required, per specifications, that cannot be visually verified shall be submitted for approval when requested by the Contracting Officer or the designated representative.
2. Submittals that may be required by this Contract, if submitted in printed matter, shall be made in four copies. One copy of the printed submittals will be returned to the Contractor.
3. The Contractor must submit for approval those items that deviate from the specifications. Submission will be on an AF Form 3000.
B. At the pre-construction conference, the Contractor, Contracting Officer’s Technical
Representative, and the Contract Administrator will review the submittal requirements.
The Contractor must be prepared to discuss the delivery dates for those submittals that are required, or for the items the Contractor plans to submit for approval. Once approved, the submission deadlines shall be incorporated into the Schedule of
Materials submittals.
C. The Contractor is reminded that any item(s) installed prior to the Contracting Officer's approval is completed is at risk of not being accepted. If any item does not meet the
Contract requirements as determined by the Contracting Officer, the Contractor will be required to remove these items at his/her own expense.
D. Equipment submittals, unless otherwise specified, shall conform with the following:
1. Submittals shall be complete with the manufacturer's product description literature. SUBMITTALS WITH INSUFFICIENT LITERATURE WILL BE
DISAPPROVED.
PROJECT PROVISIONS 01 01 00 - 4
2. Submittals shall include a complete listing of all associated parameters contained in the Technical Specifications and Drawings (materials, finishes, capacities, temperatures, pressures, electrical characteristics, etc.). THE CONTRACTING
OFFICER OR HIS/HER TECHNICAL REPRESENTATIVE WILL NOT TRANSFER
INFORMATION FROM THE TECHNICAL SPECIFICATIONS AND DRAWINGS TO
THE SUBMITTALS. INCOMPLETE SUBMITTALS WILL BE DISAPPROVED.
3. Submittals shall be clearly marked to differentiate between the applicable and extraneous portions. THE CONTRACTING OFFICER OR HIS/HER TECHNICAL
REPRESENTATIVE WILL NOT MARK THE SUBMITTALS. UNMARKED
SUBMITTALS WILL BE DISAPPROVED.
1.14 INTERRUPTION OF UTILITIES
A. No utility services shall be interrupted to make connections, to relocate, or for any purpose, without approval of the Contracting Officer.
B. Services shall not be interrupted until receipt of approval of the proposed hours and date from the Contracting Officer.
1.15 FIELD MEASUREMENTS
A. The Contractor shall verify all measurements and be responsible for dimensions, fitting and proper trimming of items directly connected with all work described in this
Contract. The Contractor shall immediately notify the Contracting Officer of any discrepancy prior to starting the work.
1.16 SECURITY REQUIREMENTS
A. The work to be done on this project is located in and around area’s that are under the scrutiny of the Department of Defense Police assigned to the RRS Information
Directorate. To gain access to the area(s) to examine the work to be done for job estimation purposes; arrangements must be made through the Contracting Office.
Contractor personnel will be escorted into the area(s) for the purpose of project estimation.
B. When it has been determined which Contractor will accomplish the project a Visit
Request from the company, preferably on Company letterhead, will be necessary prior to initial work commencement. The Visit Request letter needs to be signed by the
Company President or Director of Human Resources. The Visit Request will also be used as the Entry Authority List. The Contractor will supply the Visit Request to
Security (AFRL/RIOF) through the Contracting Office. The Visit Request can be done via
RRS Visit Request Form, AFMC Form 97 (found on the AFRL web page, https://rlweb.rl.af.mil/security/) or a simple Company Letterhead letter identifying all personnel who will be employed during the work. The request will contain a full name to include a middle initial (Frank A. Dude), date of birth (14 Dec 1953), state of driver’s license issuance and place of birth (Austin, Texas). This information will be used to do a Local Files Check. This check will provide Drivers License Info, Wants & Warrants and
Protection Orders and will also provide information on Illegal Immigration and suspected terrorist affiliations. The Local Files Check will also be accomplished prior to work commencing. If the individual is not a US Citizen they will not be allowed within the complex or facilities. If, the individual is not a US Citizen but has a Green Card, Form I-551 or has the I-551 stamp on their passport, Security will need to see either one. There will be no foreign national workers allowed on the Rome Research Site.
PROJECT PROVISIONS 01 01 00 - 5
C. Provide the Company’s phone number and a Project Leaders or Supervisor/Foremen cell-phone number is necessary for the Law Enforcement Desk Sergeant.
D. All facilities are entered using a magnetic media entry badge. Any personnel such as
Supervisor/Foremen or Project Leaders who may need building access for meetings etc, during contract period, can acquire a Local Contractor Entry Badge through the
Division/Branch with oversight of the work. This will be accomplished with the RRS
Form 110 (Unescorted Visitor Badge). The Security Visitation Office is located in the lobby of Bldg 3, West Wing. This badge will be worn at all times within the facility.
These badges will be returned to the Contracting Officer’s Technical Representative upon completion of the final inspection and Acceptance of Work. Any badges lost during the period of work will be reported to Security as soon as possible.
E. Access to the RRS Complex is controlled by a Main Gate on Brooks Rd, located just west of the Otis & Brooks intersection. Identification for the contractor to enter with a vehicle will be an access list supported by the electronic badge issued. All commercial vehicles entering the gate will be searched. One-time deliveries can be escorted from the gate to delivery point by project personnel.
F. All commercial vehicles are searched prior to entry into the RRS Complex. Vehicle operators will be aware of the vehicle search pull-off area prior to approaching the Main
Gate. A search of the vehicle will be conducted prior to its entry. All vehicles not needed for delivery of equipment or tools will be parked in the visitor parking area unless cleared through Security. There are No vehicles allowed within 25 meters (80 ft) of the
RRS facilities.
G. All personnel should be aware that the Rome Research Site are Property of the United States Air Force. All personnel will follow all posted signage.
H. Contractor personnel will be notified by RRS Police of any emergencies which would require an evacuation or work stoppage, such as an increase in the Force Protection
Condition.
I. Building/Room Keys: If the contractor needs access to area(s) that are locked (i.e.
mechanical rooms, janitor’s closet, etc.), a request for entry of at least 2 working days prior to the need for access will be submitted to AFRL/RIOC construction representative. The area(s) will be provided on a daily basis. The area(s) will be locked down at the end of the days work.
J. The 24 hour Desk Sgt. can be reached at (315) 330-2961.
1.17 DELIVERY AND STORAGE
A. Materials shall be delivered to the work area in undamaged condition, stored in fully covered, well-ventilated areas, and protected from extreme changes in humidity and temperature.
B. The Contractor is responsible for securing materials in the storage area to protect from pilferage and vandalism.
PROJECT PROVISIONS 01 01 00 - 6
1.18 SAFETY
A. The Contractor shall:
1. Comply with all safety and health requirements necessary for the protection of personnel, facilities and equipment including, but not limited to all applicable Occupational Safety and Health Administration (OSHA) standards, while performing this contract at the Air Force Research Laboratory (AFRL), Rome
Research Site (RRS).
2. Maintain a written Safety Program, as required by OSHA and make said plan available for review by the government upon request by the contracting officer.
3. In the event of a mishap during the performance of this contract on AFRL RRS premise, notify the contracting officer in an expeditious manner. Notification shall include the following information:
a. Contract, Contract number, Name and Title of Person(s) Reporting
b. Date, Time and exact location of accident/incident
c. Brief Narrative of accident/incident (events leading to accident/incident)
d. Cause of accident/incident (if known)
e. Estimated cost of accident/incident (material and labor to replace/repair)
f. Nomenclature of equipment and personnel involved in accident/incident
g. Corrective Actions (taken or proposed)
h. Other pertinent information
1.19 PROPRIETARY EQUIPMENT
A. Reference to any equipment, material, article or patented process by trade name, mark or catalog number shall be regarded as establishing a standard of quality and shall not be construed as limiting competition. The Contractor may use any equipment, material article or process that is equal to that named as approved by the Contracting
Officer.
1.20 PROTECTION
A. Protection of existing work:
1. The Contractor shall take all necessary precautions to insure against damage to the existing work to remain in place, to be reused, or to remain the property of the
Government; i.e. light fixtures, trees, sidewalks, etc.
B. Dust control:
1. The amount of dust resulting from demolition shall be controlled to avoid creation of a nuisance in the surrounding areas.
C. Protection of personnel:
1. Where the safety of non-Contractor personnel is endangered in the area of removal work and new construction, barricades shall be used.
PROJECT PROVISIONS 01 01 00 - 7
1.21 REMOVED MATERIALS AND EQUIPMENT
A. General:
1. All materials and equipment indicated to be removed as part of the work become the property of the Contractor for removal from the job site, unless otherwise shown on the drawings or specified.
B. Items re-used as part of the work:
1. Items indicated to be re-used on the “List of Salvageable Materials”, will be stored by the Contractor until such time as they may be reinstalled.
1.22 DISPOSAL OF REMOVED MATERIALS
A. General:
1. Materials removed from the project which are designated as unusable by the
Government shall be disposed of by the Contractor off the Griffiss Business and
Technology Park and Stockbridge Site in accordance with applicable regulations.
2. All debris to be removed from the work site shall be transported in canvas covered trucks with the canvas tied down to prevent loss of materials while in route to the disposal areas.
3. The Contractor shall police the truck routes continuously and all debris, which has dropped, shall be picked up immediately.
B. Materials for Contractor salvage:
1. This material shall be removed from Government property before completion of the
Contract.
2. Materials for salvage shall not be sold on the site.
1.23 CUTTING AND PATCHING
A. Patch existing construction damaged due to removals. Patching, unless otherwise indicated, will be limited to areas where removals occurred and will match existing in material, color and finish.
B. Cap or otherwise terminate existing utility services to removed equipment on all utilities that are to remain active.
C. Protection: Protect in-place construction during cutting and patching to prevent damage. Provide protection from adverse weather conditions during cutting and patching operations.
D. Cutting: Cut in place construction by sawing, drilling, breaking, chipping, grinding, and similar operations; including excavation, using methods least likely to damage elements retained.
PROJECT PROVISIONS 01 01 00 - 8
E. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other work. Patch with durable seams that are as invisible as practicable. Provide materials and comply with installation requirements specified in other sections, where applicable.
1.24 SPECIAL CONDITIONS
A. Should any materials be encountered during construction which are suspected to contain hazardous materials and are not indicated as such on the drawings or Pre-
Demolition Hazardous Materials Survey, immediately stop work in that area and report the encountered condition to the Contracting Officer’s Technical Representative.
B. The contractor will notify the Contracting Officer’s Technical Representative at least 10 working days prior to the completion of the demolition. This will allow for the work specified by others to be accomplished. The contractor will delay his work schedule as necessary for removal of all hazardous materials. The contractor may resume his work schedule after each of these tasks is completed.
1.25 SEQUENCING AND SCHEDULING
A. Provisions must be made to leave each entrance secured at the end of work each day.
B. Traffic control:
1. Routes of ingress and egress on the grounds and within existing buildings to the location of the work shall be over routes as directed by the Government.
2. Areas for parking vehicles belonging to the Contractor and his employees will be designated by the Contracting Officer’s Technical Representative. Maintain the parking areas free of debris and obstructions.
C. Building Closure:
1. Leave building in a secure and closed condition at the end of each work day.
2. Open existing hangar doors to the extent required for installation of insulated panels installed that day.
3. Close gap between insulated panels and hangar door at the end of each day when ambient night time temperatures fall below 50° F.
1.26 CONSTRUCTION SCHEDULING
A. The Contractor may be paid for materials on-site, however, they must appear on the
Contract Progress Schedule and be inventoried by the Contracting Officer’s Technical
Representative prior to payment.
1.27 WORK SCHEDULE
A. Working hours for the Contractor will normally be between the hours of 0700 and
1600 hours (7:00 a.m. and 4:00 p.m.), excluding Saturdays, Sundays and Federal holidays.
B. If the Contractor desires to work during periods other than above, additional government inspection forces may be required:
PROJECT PROVISIONS 01 01 00 - 9
1. The Contractor must make his/her request to the Contracting Officer three (3) days in advance of his/her intention to work during other periods to allow assignment of additional inspection forces.
2. If such force is reasonably available, the Contracting Officer may authorize the
Contractor to perform work during periods other than normal duty hours/days.
However, if inspectors are required to perform in excess of their normal duty duty hours/days solely for the benefit of the Contractor, the actual cost of inspection at overtime rates will be charged to the Contractor. These adjustments to the Contract Price may be made periodically as directed by the Contracting
Officer.
1.28 REMOVAL OF TEMPORARY FACILITIES
A. Maintain all temporary facilities and controls as long as needed for the safe and proper completion of the work.
B. Remove all such temporary facilities and controls as rapidly as progress of the work will permit or as directed by the Contracting Officer.
1.29 CLEAN-UP
A. Debris and rubbish control:
1. Remove all debris and rubbish daily from the site.
2. Remove debris and rubbish into a dumpster; then transport in a manner that will prevent spillage on streets or adjacent areas.
3. The Contractor shall make his/her own arrangements for dumping off the Griffiss
Business and Technology Park.
4. Burning of waste material on Griffiss Business and Technology Park is prohibited.
B. Regulations:
1. All disposal and hauling equipment and methods used shall comply with Federal, State, OSHA, and local regulations.
C. If the Contractor utilizes a collector box, it must be provided with a cover.
END OF SECTION
SUMMARY 01 10 00 - 1
SECTION 01 10 00
SUMMARY
PART 1 - GENERAL
1.1 PROJECT
A. Project Name: Enclosed Hangar Door, Building 101.
B. Project Location: Air Force Research Laboratory, Rome Research Site, Rome, NY.
C. Owner's Name: Air Force Research Laboratory, Rome Research Site, Rome, NY.
D. Architect/Engineer: Beardsley Design Associates, Architecture, Engineering, Landscape Architecture, D.P.C., 64 South Street, Auburn, NY 13021
E. The Project generally consists of furnishing all labor, equipment, devices, and materials and performing all work required to perform complete Construction of new infill insulated metal panel wall system, with personnel door, sectional overhead door and storefront windows in existing hangar door opening of Building 101at Rome Site in accordance with these technical specifications and applicable drawings
1.2 CONTRACT DESCRIPTION
A. Contract Type: A single prime contract based on a Stipulated Price.
1.3 WORK BY OWNER
A. General: Cooperate fully with Air Force Research Laboratory so work may be carried out smoothly, without interfering with or delaying work under this contract or work by Owner. Coordinate the work of this Contract with work performed by Owner.
1.4 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the
Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
3. The term “Provide” means furnish and install complete, in place and ready for operation and use.
4. The term “Furnish” means supply and deliver to the Project Site, ready for unloading, unpacking, assembly, installation, and similar operations.
5. The term “Install” means operations at the Project Site including the actual unloading, temporary storage, unpacking, assembly, erecting, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning, and similar operations.
B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
SUMMARY 01 10 00 - 2
C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:
1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.
2. Abbreviations: Materials and products are identified by abbreviations scheduled on Drawings or reasonably inferred.
3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.
PART 2 - PRODUCTS - NOT USED
PART 3 - EXECUTION - NOT USED
HANDLING OF LEAD CONTAINING MATERIALS 02 83 04 - 1
SECTION 02 83 04
HANDLING OF LEAD CONTAINING MATERIALS
PART 1 - GENERAL
1.1 SUMMARY
A. This Section specifies the requirements for handling lead-containing materials, including:
1. The detection and prevention of lead dust, paint chips, or debris contamination of lead dust control work area.
2. Protection of workers.
3. Post-work cleaning.
4. Predisposal testing.
5. Disposal of removed material.
1.2 INFORMATION AVAILABLE TO THE CONTRACTOR
A. The subject building is not considered a “child occupied facility” or “target housing” as defined by EPA/HUD.
B. Painted surfaces were observed in good condition and are assumed to have detectable lead levels at concentrations above OSHA and EPA standards due to the age of the building.
1.3 REFERENCES
A. New York State Department of Environmental Conservation (DEC) 6NYCRR:
1. Part 360 Solid Waste Management Facilities.
2. Part 364 Waste Transporter Permits.
3. Part 370 Hazardous Waste Management System-General.
4. Part 371 Identification and Listing of Hazardous Wastes.
5. Part 372 Hazardous Waste Manifest System and Related Standards for
Generators, Transporters and Facilities.
6. Part 373 Hazardous Waste Management Facilities.
B. New York State Department of Transportation (DOT): Follow all regulations of 49 CFR
Part 100 through 199.
C. Occupational Safety and Health Administration (OSHA):
1. 29 CFR 1910-General Industry Standards
2. 29 CFR 1910.1025-Lead Standard for General Industry
3. 29 CFR 1926-Construction Industry Standards
4. 29 CFR 1926.62-Construction Industry Lead Standard
D. U.S. Environmental Protection Agency (EPA):
1. Resource Conservation and Recovery Act (RCRA) Section 3004 Hazardous and
Solid Waste Amendments.
2. Toxicity Characteristics Leaching Procedure EPA Method 1311.
3. 40 CFR Part 261-Identification and Listing of Hazardous Waste
HANDLING OF LEAD CONTAINING MATERIALS 02 83 04 - 2
1.4 DEFINITIONS
A. Authorized Personnel: Government Representative, and all other personnel who are authorized officials of any regulating agency, be it State, Local, Federal or Private entity who possess legal authority for enforcement or inspection of the work.
B. Containment: The enclosure within the building which establishes a contaminated area and surrounds the location where lead handling is taking place and establishes a Lead Control Work Area.
C. Fixed Object: Mechanical equipment, electrical equipment, fire detection systems, alarms, and all other fixed equipment, furniture, fixtures or other items which cannot be removed from the work area.
D. HEPA: High Efficiency Particulate Absolute filtration efficiency of 99.97 percent down to
0.3 microns. Filtration provided on specialized vacuums and air filtration devices to trap particles.
E. Lead Based Paint (LBP): Paints or other surface coatings that contain lead equal to or greater than 1.0 milligrams per square centimeter or 0.5 percent of lead by weight.
F. Lead Containing Material: Materials coated with lead-containing paint.
H. Lead Dust Control Work Area: A cordoned off area with drop clothes or an enclosed area or structure with containment to prevent the spread of lead dust, paint chips, or debris from lead-containing paint disturbance operations.
I. PPE: Personal Protective Equipment.
1.5 ABBREVIATIONS
A. ASTM: American Society for Testing and Materials
1916 Race Street Philadelphia, PA 19103
B. CFR: Code of Federal Regulations
Government Printing Office Washington, DC 20402
C. DOT: Department of Transportation
Main Office, 50 Wolf Road Albany, NY 12232
D. NIOSH: National Institute for Occupational Safety and Health
Building J, N.E. Room 3007 Atlanta, Georgia 30333
E. OSHA: Occupational Safety and Health Administration
200 Constitution Avenue Washington, DC 20210
F. USEPA: United States Environmental Protection Agency
401 M Street SW Washington, DC 20460
HANDLING OF LEAD CONTAINING MATERIALS 02 83 04 - 3
1.6 SUBMITTALS
A. Quality Control Submittals:
1. Workers removing lead-containing paints and their supervisors shall be experienced in this type of work. Submit a copy of documentation of completion of current valid lead awareness training.
2. Submit a copy of documentation for each worker of respirator fit testing results.
3. Submit one copy of the site specific work plan required under Quality Assurance
Article.
B. Contract Closeout Submittals:
1. Contractor’s certification that the work area has been cleaned and decontaminated in accordance with all applicable regulations.
2. Copies of waste shipment records and disposal site receipt showing that the lead-containing materials have been properly disposed.
1.7 QUALITY ASSURANCE
A. Comply with applicable codes and standards including those referenced in Section 1.3.
Where multiple requirements are specified, adhere to the more stringent requirements.
B. Before the Work of this Section is scheduled to commence, a conference will be held by the Government Representative at the Site with the contractor and the lead handling subcontractor (if any) for the purpose of reviewing the Contract Documents, discussing requirements for the Work, and reviewing the Work procedures.
C. Before the physical Work begins, prepare a detailed site specific lead-containing material handling work plan.
1. The work plan shall include, but not be limited to, the location and details of lead dust control work areas, containment, work procedures, types of equipment, crew size, and emergency procedures for fire and medical emergencies.
1.8 PROJECT CONDITIONS
A. Cover and seal all fin-tube radiator covers, diffusers, duplex outlets, speakers, smoke and heat detectors, etc. Use temporary plasticized partitions as required.
1. Prevent lead containing dust from entering hard to clean areas within the dust containment area.
2. Items judged to be too difficult to protect may be disconnected, removed and replaced at contractor’s option.
B. Remove or encase all movable equipment in the work area with two layers of six mil fire retardant polyethylene sheeting.
1.9 HEALTH AND SAFETY
A. Where in the performance of the work, workers, supervisory personnel or sub-contractors may encounter, disturb, or otherwise function in the immediate vicinity of contaminated items and materials, all personnel shall take appropriate continuous measures as necessary to protect all adjacent building occupants/workers from the potential lead exposure.
1. Such measures shall include the procedures and methods described herein and shall be in compliance with all applicable regulations of Federal, State and Local agencies.
HANDLING OF LEAD CONTAINING MATERIALS 02 83 04 - 4
2. Workers not directly involved with the handling of lead-containing paints shall not be permitted within the work area.
1.10 FIRE PROTECTION, EMERGENCY EGRESS, AND SECURITY
A. Establish a system for alerting workers of fire or other hazards that require escape routes, evacuation of the work area, and development of an assigned meeting place.
B. Provide a person on-site who is trained in First Aid and in the treatment of heat stress and hypothermia.
C. Provide chemical fire extinguishers on-site for emergencies.
1.11 PERSONAL PROTECTIVE CLOTHING AND EQUIPMENT
A. Workers must wear protective suits, protective gloves, eye protection and a minimum of half-face respirator with new HEPA filter cartridge for all projects. Respiratory protection shall be in accordance with OSHA regulation 1910.134 and ANSI Z88.2.
B. Workers must be trained per OSHA, have medical clearance and must have recently received pulmonary function test (PFT) and respirator fit tested by a trained professional.
1. A personal air sampling program shall be in place as required by OSHA.
2. The use of respirators must also follow a complete respiratory protection program as specified by OSHA.
PART 2 - PRODUCTS
2.1 RESPIRATORS
A. Type: Approved by the Mine Safety and Health Administration (MSHA), Department of
Labor, or the National Institute for Occupational Safety and Health (NIOSH), Department of Health and Human Services.
2.2 VACUUM CLEANERS
A. Type: HEPA Vacuums equipped with new HEPA filters.
2.3 PLASTIC SHEETS
A. Type: Minimum 6 mil., clear, fire retardant polyethylene sheets.
B. Floor Protective Layer: Minimum 10 mil., reinforced polyethylene sheets.
2.4 DISPOSAL BAGS
A. Type: Minimum 6 mil thick, clear polyethylene bags with preprinted Caution Label.
Properly containerize/drum prior to disposal.
2.5 EQUIPMENT
A. Temporary lighting, heating, hot water heating units, ground fault interrupters, and all other equipment on site shall be UL listed and shall be safe, proper, and sufficient for the purpose intended.
B. All electrical equipment shall be in compliance with the National Electric Code, Article
305 - Temporary Wiring.
HANDLING OF LEAD CONTAINING MATERIALS 02 83 04 - 5
PART 3 - EXECUTION
3.1 EMPLOYEE PROTECTION
A. Comply with all applicable Occupational Safety and Health Administration (OSHA)
Requirements.
3.2 LEAD-CONTAINING/COATED MATERIAL HANDLING, REMOVAL, AND DISPOSAL
A. Handle and dispose of lead-containing materials in accordance with OSHA 1926.62 and the approved lead-containing material work plan. Use procedures and equipment required to limit occupational and environmental exposure to lead when material containing or coated with lead containing paint is handled and disposed of in accordance with referenced standards.
B. Cut and altar existing materials as required to perform the work. Limit cutting to the smallest amount necessary. Core drill round holes and saw cut other openings where possible for removal work.
1. Remove paints as necessary prior to welding or cutting of existing structural steel to prevent vaporization of lead and/or creation of lead dust.
C. Provide all necessary dust barriers to prevent the spread of dust from the work area and prevent lead exposure to the public and environment.
D. The following work methods are prohibited on painted surfaces:
1. Dry hand tool cleaning
2. Power tools not equipped with shrouds and HEPA exhaust
3. Blast cleaning
4. High speed grinding
5. Torch cutting
6. Welding
3.4 CLEANING CRITERIA
A. Maintain surfaces of the lead control area free of accumulations of paint chips and dust.
Keep waste from being distributed over the work area. Do not dry sweep or use compressed air to clean up the area. At the end of each shift and when the lead material handling operations have been completed, clean the area of visible lead paint debris by vacuuming with a HEPA filtered vacuum cleaner, wet mopping the area and wet wiping the area. Re-clean areas showing dust or residual paint chips or debris. After visible dust, chips and debris are removed, wet wipe and HEPA vacuum all surfaces in the work area.
B. If adjacent areas become contaminated at any time during the work, clean, visually inspect, and then wipe sample all contaminated areas. The project supervisor shall then certify in writing that the area has been cleaned of lead contamination before restarting work.
3.5 CERTIFICATION OF CLEANING
A. The Contractor shall document in writing that the work procedures performed conform to all standards set forth by all authorities having jurisdiction, mentioned in the references, and that there are no visible accumulations of material and dust containing lead left at the work site. Do not remove the lead control area or roped off boundary and warning signs prior to the Government Representative’s acknowledgement upon receipt of the Contractor certification.
HANDLING OF LEAD CONTAINING MATERIALS 02 83 04 - 6
B. The Government shall have final determination of an acceptable clearance level.
3.6 PRE-DISPOSAL TESTING
A. Prior to disposal, test the removed materials for toxicity in accordance with EPA Method
1311, Toxicity Characteristic Leaching Procedure (TCLP).
1. Test results indicating a value greater than 5 ppm lead or 5 mg/L classifies the removed material as Hazardous Waste.
3.7 DISPOSAL OF LEAD-CONTAINING/COATED MATERIAL AND RELATED DEBRIS
A. Transport and dispose of lead-containing material classified as Hazardous Waste in accordance with the standards referenced in Part 1 of this Section.
B. Transport and dispose of lead-containing material classified as Non- Hazardous Waste in accordance with the standards referenced in Part 1 of this Section.
3.8 RESTORATION
A. Remove temporary decontamination facilities and restore area designated for these facilities to its original condition or better.
B. Where existing construction is damaged or contaminated during the course of performing this project, restore area to its original condition or better.
STRUCTURAL STEEL FRAMING 05 12 00 - 1
SECTION 05 12 00
STRUCTURAL STEEL FRAMING
PART 1 - GENERAL
1.1 DEFINITIONS
A. Structural Steel: Elements of structural-steel frame, as classified by AISC 303, "Code of Standard Practice for Steel Buildings and Bridges."
1.2 PERFORMANCE REQUIREMENTS
A. Connections: Provide details of simple shear connections required by the Contract
Documents to be selected or completed by structural-steel fabricator to withstand loads indicated and comply with other information and restrictions indicated.
1. Select and complete connections using schematic details indicated and
AISC 360.
B. Moment Connections: Type PR, partially restrained.
C. Construction: as indicated.
1.3 SUBMITTALS
A. Product Data: For each type of product indicated.
B. Shop Drawings: Show fabrication of structural-steel components.
1. Include details of cuts, connections, splices, camber, holes, and other pertinent data.
2. Include embedment drawings.
3. Indicate welds by standard AWS symbols, distinguishing between shop and field welds, and show size, length, and type of each weld. Show backing bars that are to be removed and supplemental fillet welds where backing bars are to remain.
4. Indicate type, size, and length of bolts, distinguishing between shop and field bolts. Identify pretensioned and slip-critical high-strength bolted connections.
C. Qualification Data: For qualified Installer fabricator testing agency.
D. Welding certificates.
E. Paint Compatibility Certificates: From manufacturers of topcoats applied over shop primers, certifying that shop primers are compatible with topcoats.
F. Product Test Reports: For the following:
1. Shop primers.
2. Nonshrink grout.
G. Source quality-control reports.
STRUCTURAL STEEL FRAMING 05 12 00 - 2
1.4 QUALITY ASSURANCE
A. Fabricator Qualifications: A qualified fabricator that participates in the AISC Quality
Certification Program and is designated an AISC-Certified Plant, Category STD.
B. Installer Qualifications: A qualified installer who participates in the AISC Quality
Certification Program and is designated an AISC-Certified Erector, Category CSE.
C. Welding Qualifications: Qualify procedures and personnel according to
AWS D1.1/D1.1M, "Structural Welding Code - Steel."
D. Comply with applicable provisions of the following specifications and documents:
1. AISC 303.
2. AISC 360.
3. RCSC's "Specification for Structural Joints Using ASTM A 325 or A 490 Bolts."
1.5 COORDINATION
A. Coordinate selection of shop primers with topcoats to be applied over them. Comply with paint and coating manufacturers' recommendations to ensure that shop primers and topcoats are compatible with one another.
B. Coordinate installation of anchorage items to be embedded in or attached to other construction without delaying the Work. Provide setting diagrams, sheet metal templates, instructions, and directions for installation.
PART 2 - PRODUCTS
2.1 STRUCTURAL-STEEL MATERIALS
A. W-Shapes: ASTM A 992/A 992M.
B. Channels, Angles -Shapes: ASTM A 36/A 36M.
C. Plate and Bar: ASTM A 36/A 36M.
D. Welding Electrodes: Comply with AWS requirements.
E. Cold Formed Metal Framing “Z” and “C” Shapes: Structural-Steel Sheet: Hot-rolled, ASTM A 1011/A 1011M, Structural Steel (SS), Grades 30 through 55, or High-
Strength Low-Alloy Steel (HSLAS), Grades 45 through 70; or cold-rolled, ASTM A 1008/A 1008M, Structural Steel (SS), Grades 25 through 80, or High-
Strength Low-Alloy Steel (HSLAS), Grades 45 through 70.
2.2 BOLTS, CONNECTORS, AND ANCHORS
A. High-Strength Bolts, Nuts, and Washers: ASTM A 325 (ASTM A 325M), Type 1, heavy-hex steel structural bolts; ASTM A 563, Grade C, (ASTM A 563M, Class 8S) heavy-hex carbon-steel nuts; and ASTM F 436 (ASTM F 436M), Type 1, hardened carbon-steel washers; all with plain finish.
STRUCTURAL STEEL FRAMING 05 12 00 - 3
B. Tension-Control, High-Strength Bolt-Nut-Washer Assemblies: ASTM F 1852, Type 1, heavy-hex head assemblies consisting of steel structural bolts with splined ends, heavy-hex carbon-steel nuts, and hardened carbon-steel washers.
1. Finish: Plain.
C. Headed Anchor Rods: ASTM F 1554, Grade 36, straight.
1. Nuts: ASTM A 563 (ASTM A 563M) heavy-hex carbon steel.
2. Plate Washers: ASTM A 36/A 36M carbon steel.
3. Washers: ASTM F 436 (ASTM F 436M), Type 1, hardened carbon steel.
4. Finish: Plain.
D. Threaded Rods: [ASTM A 36/A 36M] [ASTM A 193/A 193M, Grade B7] .
1. Nuts: ASTM A 563 (ASTM A 563M) heavy-hex carbon steel.
2. Washers: ASTM F 436 (ASTM F 436M), Type 1, hardened ASTM A 36/A 36M carbon steel.
3. Finish: Plain.
2.3 PRIMER
A. Primer: SSPC-Paint 25, Red or Gray Type II, zinc oxide, alkyd, linseed oil primer.
B. Galvanizing Repair Paint: ASTM A 780.
2.4 GROUT
A. Nonmetallic, Shrinkage-Resistant Grout: ASTM C 1107, factory-packaged, nonmetallic aggregate grout, noncorrosive and nonstaining, mixed with water to consistency suitable for application and a 30-minute working time.
2.5 FABRICATION
A. Structural Steel: Fabricate and assemble in shop to greatest extent possible.
Fabricate according to AISC's "Code of Standard Practice for Steel Buildings and
Bridges" and AISC 360.
1. Camber structural-steel members where indicated.
2. Fabricate beams with rolling camber up.
3. Identify high-strength structural steel according to ASTM A 6/A 6M and maintain markings until structural steel has been erected.
4. Mark and match-mark materials for field assembly.
5. Complete structural-steel assemblies, including welding of units, before starting shop-priming operations.
B. Thermal Cutting: Perform thermal cutting by machine to greatest extent possible.
1. Plane thermally cut edges to be welded to comply with requirements in
AWS D1.1/D1.1M.
C. Bolt Holes: Cut, drill, or punch standard bolt holes perpendicular to metal surfaces.
STRUCTURAL STEEL FRAMING 05 12 00 - 4
D. Finishing: Accurately finish ends of columns and other members transmitting bearing loads.
E. Cleaning: Clean and prepare steel surfaces that are to remain unpainted according to one or more of the following: SSPC-SP 1, "Solvent Cleaning SSPC-SP 2, "Hand Tool
Cleaning and SSPC-SP 3, "Power Tool Cleaning."
F. Holes: Provide holes required for securing other work to structural steel and for other work to pass through steel framing members only where indicated on structural drawings.
1. Cut, drill, or punch holes perpendicular to steel surfaces. Do not thermally cut bolt holes or enlarge holes by burning.
2. Baseplate Holes: Cut, drill, mechanically thermal cut, or punch holes perpendicular to steel surfaces.
3. Weld threaded nuts to framing and other specialty items indicated to receive other work.
2.6 SHOP CONNECTIONS
A. High-Strength Bolts: Shop install high-strength bolts according to RCSC's
"Specification for Structural Joints Using ASTM A 325 or A 490 Bolts" for type of bolt and type of joint specified.
1. Joint Type: Snug tightened.
B. Weld Connections: Comply with AWS D1.1/D1.1M for tolerances, appearances, welding procedure specifications, weld quality, and methods used in correcting welding work.
1. Assemble and weld built-up sections by methods that will maintain true alignment of axes without exceeding tolerances in AISC 303 for mill material.
2.7 SHOP PRIMING
A. Shop prime steel surfaces except the following:
1. Surfaces embedded in concrete or mortar. Extend priming of partially embedded members to a depth of 2 inches (50 mm).
2. Surfaces to be field welded.
3. Surfaces to be high-strength bolted with slip-critical connections.
4. Surfaces to receive sprayed fire-resistive materials (applied fireproofing).
5. Galvanized surfaces.
B. Surface Preparation: Clean surfaces to be painted. Remove loose rust and mill scale and spatter, slag, or flux deposits. Prepare surfaces according to one or more of the following specifications and standards:
1. SSPC-SP 2, "Hand Tool Cleaning."
2. SSPC-SP 3, "Power Tool Cleaning."
STRUCTURAL STEEL FRAMING 05 12 00 - 5
C. Priming: Immediately after surface preparation, apply primer according to manufacturer's written instructions and at rate recommended by SSPC to provide a minimum dry film thickness of 1.5 mils (0.038 mm). Use priming methods that result in full coverage of joints, corners, edges, and exposed surfaces.
1. Apply two coats of shop paint to surfaces that are inaccessible after assembly or erection. Change color of second coat to distinguish it from first.
2.8 SOURCE QUALITY CONTROL
A. Testing Agency: Contractor will engage an independent testing and inspecting agency to perform shop tests and inspections and prepare test reports.
1. Provide testing agency with access to places where structural-steel work is being fabricated or produced to perform tests and inspections.
B. Correct deficiencies in Work that test reports and inspections indicate does not comply with the Contract Documents.
C. Bolted Connections: Shop-bolted connections will be inspected according to RCSC's "Specification for Structural Joints Using ASTM A 325 or A 490 Bolts."
D. Welded Connections: In addition to visual inspection, shop-welded connections may be tested and inspected according to AWS D1.1/D1.1M and one or more of the following inspection procedures, at testing agency's option:
1. Liquid Penetrant Inspection: ASTM E 165.
2. Magnetic Particle Inspection: ASTM E 709; performed on root pass and on finished weld. Cracks or zones of incomplete fusion or penetration will not be accepted.
3. Ultrasonic Inspection: ASTM E 164.
4. Radiographic Inspection: ASTM E 94.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify, with steel Erector present, elevations of concrete- and masonry-bearing surfaces and locations of anchor rods, bearing plates, and other embedments for compliance with requirements.
1. Prepare a survey of bearing surfaces, anchor rods, bearing plates, and other embedments showing dimensions, locations, angles, and elevations.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Provide temporary shores, guys, braces, and other supports during erection to keep structural steel secure, plumb, and in alignment against temporary construction loads and loads equal in intensity to design loads. Remove temporary supports when permanent structural steel, connections, and bracing are in place unless otherwise indicated.
STRUCTURAL STEEL FRAMING 05 12 00 - 6
1. Do not remove temporary shoring supporting composite deck construction until cast-in-place concrete has attained its design compressive strength.
3.3 ERECTION
A. Set structural steel accurately in locations and to elevations indicated and according to AISC 303 and AISC 360.
B. Base Bearing and Leveling Plates: Clean concrete- and masonry-bearing surfaces of bond-reducing materials, and roughen surfaces prior to setting plates. Clean bottom surface of plates.
1. Set plates for structural members on wedges, shims, or setting nuts as required.
2. Weld plate washers to top of baseplate.
3. Snug-tighten anchor rods after supported members have been positioned and plumbed. Do not remove wedges or shims but, if protruding, cut off flush with edge of plate before packing with grout.
4. Promptly pack grout solidly between bearing surfaces and plates so no voids remain. Neatly finish exposed surfaces; protect grout and allow to cure.