Contractor Questions and Government Answers (Round 3)

View the file

Other files for this federal contract opportunity

Other files attached to High Density Storage System at Bradely ANGB, CT, newest first.
File Type Posted
Amendment_2.pdf PDF
RFP_Questions_and_Government_Answers_(Round_2).docx DOCX document
Amendment_1.pdf PDF
Proposal_Checklist-Pricing_Summary_Sheet_(R1).docx DOCX document
RFP.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP Contractor Questions and Government Answers Bradley ANGB, Connecticut

22 Feb 2018 (Round 3) FA8604-18-R-8105, Amendment 2

1. Cover PD, paragraph 3.1.6 – mentions pallet jack interfacing with conveyor in Appendix D. I have no appendix D, nor do I see any mention of conveyor in other appendices.

Government Answer: Appendix D was deleted from the requirement. Reference was therefore deleted in the updated Attachment 1, “Cover PD (Revision 1)” dated 21 February.

2. Appendix B, paragraph 3.2.4.6 – lighting- mentions only motion sensor fixtures. Is there not a requirement for a switch to operate the area?

Government Answer: Although a light switch can be provided, a light switch is not required.

3. Appendix C – may I assume that the display shelving is the “B” & “C” units on Drawing 01 – “upper level of admin office area”?

Government Answer: Yes, you may assume the display shelving is the “B” & “C” units on Attachment XX “Drawing 01 – “upper level of the admin office area. Please not there are also two (2) “B” units located on the floor.

20 Feb 2018 (Round 2) FA8604-18-R-8105 (No Amendment Required)

1. Is there an incumbent? If so who are they and what was the winning bid, contract number and scope?

Government Answer: Each project is a separate project. Therefore, this solicitation is for an individual project not a follow-on or continuation of previous work.

2. When is the submission date extended to? I can’t seem to find that detail in the 12 Feb Amendment.

Government Answer: The submission has not been changed. It remains 06 March 2018 at 1400 EST

3. Is there a past performance requirement?

Government Answer: Please see the solicitation provisions on document pages 172 through 175.

4. I understand there’s a Proposal Checklist, but is there a corresponding section L/M?

Government Answer: There are solicitation provisions in the very back of the solicitation, document pages 164 through 181.

12 Feb 2018 (Round 1) FA8604-18-R-8105, Amendment 1

1. There seem to be missing Attachments. Will there be an amendment to include these missing attachments?

Government Answer: The Solicitation was amended to include all of the attachments, including those that were missing.