FalconUp_SOW_10Dec14.docx

DOCX document 43 KB Posted

Attached to
F-16 Falcon Up Kits Federal contract opportunity
Solicitation number
FA8232-14-R-3007
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

About this file

Revised SOW.

View the file

Other files for this federal contract opportunity

Other files attached to F-16 Falcon Up Kits, newest first.
File Type Posted
FA823214R3007_______0008.pdf PDF
FA823214R3007_______0007.pdf PDF
FA823214R3007_______0006.pdf PDF
FA823214R3007_______0005.pdf PDF
Update1_Kit_Drawing_201414025.docx DOCX document
FA823214R3007_______0004.pdf PDF
PartsListKitList10B.docx DOCX document
PartsListKitList10A.docx DOCX document
FA823214R3007_______0003.pdf PDF
CDRLs.pdf PDF
Q_and_A_Set2_29July2014_(2).docx DOCX document
FalconUp_SOW_07252014.docx DOCX document
FA823214R3007_______0002.pdf PDF
TCTO-1F-16-2709.pdf PDF
Updated_Parts_List_Quantity_201414025-10.docx DOCX document
Q_and_A_Set1_22July2014.docx DOCX document
Part_List_V4.pdf PDF
FA823214R3007_______0001.pdf PDF
FalconUp_SOW_05202014.docx DOCX document
Parts_List_Quantity_201414025-10.docx DOCX document
Kit_Drawing_201414025.pdf PDF
CSI_Critical_Characteristics.docx DOCX document
FA823214R3007.pdf PDF
Engineering_Data_List.pdf PDF
First-Article-Reqs-AFMCForm260.pdf PDF
Show all 25

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

FOR

UNITED STATES NAVY

F-16

KIT MANFACTURING AND/OR PROCUREMENT

PURCHASE REQUEST #

FD20201450954

Prepared by:

AFLCMC/WWMPBB

HILL AIR FORCE BASE, UT

December 2014

Preparer:

Darrin K. Pasco, AFLCMC/WWMPBB, DSN 775-2944

ACRONYM LIST

AFIAir Force Instruction
ATCHAttachment
CDRLSContract Data Requirements Lists
COContracting Officer
CORContracting Officer Representative
CSICritical Safety Item
DCMADefense Contracting Management Agency
DFARDefense Federal Acquisition Regulation
DODDepartment of Defense
DODIDepartment of Defense Instruction
ECPEngineering Change Proposals
IAWIn Accordance With
IUIDItem Unique Identification
MIL-STDMilitary Standard
POCPoint Of Contact
SOWStatement Of Work
LPTALowest Price, Technically Acceptable
TCTOTime Change Technical Order
USNUnited States Navy

1.0 Introduction

1.1 Purpose

The purpose of this effort is to manufacture/procure, and deliver in the form of a kit (as defined in Atch A) all parts, pieces and components for up to eleven (11 each) Falcon Up kits (as defined in Atch B). All components must be acquired from/manufactured by Lockheed Martin Aeronautics qualified vendors in support of USN F-16A aircraft.

1.2 Scope

To ensure proper and complete kit assembly, the Contractor shall utilize the Lockheed Martin structures modification data (approved Engineering Change Proposals (ECPs), Time Compliance Technical Orders (TCTOs) and technical data packages. This is a Lowest Price, Technically Acceptable (LPTA) solicitation and contractors will be evaluated on technical acceptability.

Reference Documents

Draft TCTO 1F-16-2709
Incorporates ECP’s : 1871, 1910, 1987 and 4087
Navy Kit Drawing #201414025 (JEDMICS Technical Data)
AFMC 761 Screening Analysis Worksheet

AFMC 807 Quality Assurance Provisions & Special Inspection Requirements AFMC 260 First Article Testing

Parts List Quantity Falcon Up Modification Kit #201414025-10(A) (1) #201414025-10(B) (10) Master Modification Kit Parts List (MKPL)

2.0 Program Management

2.1 The Government System Program Office will be responsible for the F-16A System Sustainment for all non-recurring engineering data.

2.2The Government Program Manager will coordinate with other organizations as required.
2.3Responsibility for contracting activities rests solely with the Government Contracting Officer. No conversation, recommendations, or direction, whether given directly by, or implied by

Government personnel, that will affect the scope, schedule, or price of the program covered by this SOW, shall be acted upon by the contractor unless specifically approved by the Government Contracting Officer (CO).

3.0 Contractor Tasking/Requirements

3.1 The Contractor shall manufacture/procure and deliver up to eleven (11) fully qualified aircraft kits utilizing the list of parts, pieces and components in Attachment A, B, and D. The contractor shall utilize Lockheed Martin qualified manufacturing sources for the components.

3.2 The Contractor shall provide all monthly reports and a final report IAW CDRL A001. Reports will include/address:

a. Current budget status

b. Current kit procurement status; real time status of all parts and pieces

c. Schedule(s); production and delivery schedule(s) through completion

d. IUID marking plan

e. Corrective action plan(s) as applicable

f. DCMA approval confirmation for all CSI

3.3 The Government Program Manager will have the right to reject or require correction of any deficiencies found in deliverables. In the event of rejection of any deliverable, the Contractor will be notified in writing by the Government Contracting Officer of the specific reasons why the deliverable(s) were rejected. Unless otherwise specified, the Contractor shall have five (5) workdays to correct the rejected deliverable and resubmit to the Government Program Manager for re-inspection.

3.4 The Contractor shall have a thorough understanding of Item Unique Identification (IUID) marking requirements, marking equipment, databases and their interfaces, engineering evaluation requirements, verification, and data and configuration management relating to IUID marking. The Contractor shall maintain the IUID tags (markings) on all kits and spare parts for all delivered kits, CSI/Fracture critical items and all individual parts with a value of $5,000 or more. The contractor will produce and report an IUID Marking Plan via https://www.bpn.gov/iuid (CDRL A002) IAW MIL-STD-130N, dated 16 November 2012, contract clauses, DFARS (252.211-7003, 252.211-7007).

3.5 The Contractor shall manage Critical Safety Items (CSI) (Attachment C) as defined below. (Critical Safety Item Management Handbook, Chapter 7 and AFI 20-106, Management of Aviation Critical Safety Items were used as a guide in establishing the requirements.)

3.5.1 The Contractor shall identify items as Fracture Critical and identify Critical features and processes per existing procedures as identified in 16PP159 and attachment C in order to satisfy CSI requirements.

3.5.2 The Contractor shall create and revise internal command media to establish procedures relative to CSI.

3.5.3 The Contractor shall develop and implement a notification process for delivered non-conforming CSI per DFAR 252.246-7003.

3.5.4 The Contractor shall maintain records documenting manufacture of CSI hardware for 10 years. This requirement must be flowed down to subcontractors

3.5.5 Configuration management of CSIs shall be accomplished per existing procedures established by 16PP153.

4.0 Packaging and Shipping

4.1 The Falcon Up kits shall be packaged utilizing MIL-STD-2073-1e, dated 7 Jan 11 and MIL- STD-129R, dated 18 Feb 14, and in accordance with Atch A. Delivery of all kits will be IAW CDRL A003.

4.2 The contractor shall clearly label each package to include but not limited to contract number, government provided kit number, shipping address, Point of Contact (POC), phone number, etc.

4.3 Kits will be inspected and accepted by the Government via DD Form 250 (Material Inspection and Receiving Report) via Wide Area Work Flow.

5.0 First Article Testing/Kit Delivery

Initial kit delivery is required at the OO-ALC depot for Non-Destructive First Article Testing, Not Later Than 1 September 2015 IAW CDRL A004. All kit components must be acquired from/manufactured by Lockheed Martin-qualified vendors. Upon satisfactory completion of First Article testing, the first set of three (3) production kits will be delivered within 180 days. All subsequent option kits will be delivered on or before 270 days After Receipt of Contract Mod Executing the Option Contract Line Item.

6.0 Procedures and Controls

Contractor shall establish and maintain procedures and controls, which ensure products obtained from qualified vendors and subcontractors meet Lockheed Martin Aeronautical structural data requirements. The Contractor shall establish, implement and maintain documented procedures, which detect and preclude the use of substandard or counterfeit parts in the production process and impose similar requirements on subcontractors, delivered under CDRL A005.

7.0 Kick-Off Meeting

The contractor will conduct a kick-off meeting at their location within 30 days of contract award. The government will provide the agenda and requirements prior to the meeting.

8.0 Services – No services are required.

9.0 Security Clearance – Unclassified.

10 Safety and Health

10.1 While performing work under this contract the contractor shall comply with all applicable federal, state and local regulations regarding occupational safety and health. The contractor shall notify the CO, within eight (8) hours of any damage to government property where the dollar value exceeds $500,000.00 and within two workdays, for any damage to government property less than $500,000.00 during the execution of the contract.

10.2 Mishap notifications shall contain, as a minimum, the following information:

a. Contract, Contract Number, Name and Title of Person(s) reporting

b. Date, Time and exact location of accident/incident

c. Brief Narrative of accident/incident (Events leading to accident/incident)

d. Cause of accident/incident, if known

e. Estimated cost of accident/incident (material and labor to repair/replace)

f. Nomenclature of equipment and personnel involved in accident/incident

g. Corrective actions (taken or proposed)

h. Other pertinent information

10.3 If requested by the designated CO, the contractor shall immediately secure the mishap scene/damaged property and impound pertinent maintenance and training records, until released by the Procuring Safety Office. Contractors will not dispose of contract data related to a mishap until notified to do so by the CO. In case of an accident a report shall be filed IAW the attached CDRL A006.

11 Contract Authorization

Responsibility for contracting activities rests solely with the Government CO. The contractor shall take no direction that will affect cost, schedule, or scope of this effort unless specifically approved in writing by the Government CO. In addition, only the Government CO can provide direction that affects the cost, schedule, and scope of contracts existing between the Government and other contractors.

12 Government POC’s Contracting Officer’s Representative (COR) Everett Williams

AFLCMC/WWMPBB

F-16 COR

6080 Gum Lane (Building 1212) Hill AFB, UT 84056-5825 Telephone: (801) 775-3543 Email: everett.williams.2@us.af.mil

Government Program Manager Darrin K. Pasco

AFLCMC/WWMPBB

F-16 Program Manager 6080 Gum Lane (Building 1212) Hill AFB, UT 84056-5825 Telephone: (801) 775-2944 Email: darrin.pasco@us.af.mil

Engineering Austin Rickards

AFLCMC/WWMEX

F-16 Engineer 6080 Gum Lane (Building 1212) Hill AFB, UT 84056-5825 Telephone: (801) 775-4607 Email: austin.rickards@hill.af.mil

13 Contract Data Requirements Listing (CDRL) Matrix

Data Item
Authority/Title
SOW Paragraph
A001
Monthly & Final Reports
3.2
A002
IUID Marking and Verification Report
3.4
A003
Kit Packaging and Shipping
4.1
A004
First Article Testing
5.0
A005
Counterfeit Controls
6.0
A006
Accident Report
10.3

14 Mission Essential Services

Specific to DoDI 3020.37, Continuation of Essential DoD Contractor Services During Crises. AFI 63-124, Performance-Based Services Acquisition, (9 Feb 2004), paragraph 1.2.7.2, continued contractor services will not be required during crises situations.