Questions_and_Answers.pdf
PDF 176 KB Posted
- Attached to
- MBFI C-17 Serial Interface Box (SIB) Federal contract opportunity
- Solicitation number
- FA8224-15-T-0009
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA8224-15-T-0009-0004.pdf | ||
| SIB-PD_1__Updated_Version.pdf | ||
| Questions_ _Answers.pdf | ||
| SIB-PD_1__Updated_Version.pdf | ||
| FA8224-15-T-0009-0003.pdf | ||
| UPDATED_SIB-PD_1.docx | DOCX document | |
| FA8224-15-T-0009-0002.pdf | ||
| FA8224-15-T-0009-0001.doc.pdf | ||
| Single_Source_Justification.pdf | ||
| FA8224-15-T-0009.pdf | ||
| SIB-PD.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers
Solicitation FA8224-15-T-0009
Below are questions with responses that the Government received as of November 19, 2014.
Whenever possible, questions are presented as originally asked. Otherwise, the question is presented to capture the main thrust or idea of the question or inquiry.
1. Question: When is the quote due?
Government’s Response: The quote is due 25 November 2014 at 12:00pm Mountain Standard Time.
2. Question: I do not see the BOM or the drawing in the attachment or amendments, how can we get a hold of them?
Government’s Response: The equipment is owned by the F-16 program office and the drawings, BOM etc. are all in JEDMICS. We do not have access to those here.
3. Is this a box build or PCBA?
Government’s Response: Both
4. What is the quantity?
Government’s Response: 7 total
Kimberlene S.C. Butler
Contract Specialist/Negotiator