12_COMBINED_FIRST_ARTICLE_DOCUMENTS.pdf

PDF 114 KB Posted

Attached to
B-1 Fire Extinguisher Cartridges Federal contract opportunity
Solicitation number
FA8213-21-Q-3004
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

View the file

Other files for this federal contract opportunity

Other files attached to B-1 Fire Extinguisher Cartridges, newest first.
File Type Posted
07C_F01-631-9588.pdf PDF
01_Air_Spec.pdf PDF
13_JFQR_01-336-6648.pdf PDF
08_CADPAD_Item_Marking_Instruction.pdf PDF
07B_F01-631-9582.pdf PDF
07A_F01-255-2382.pdf PDF
03_ADC_SOW.pdf PDF
02_REPSHIP.pdf PDF
FA821321Q3004_______0001.pdf PDF
10_Repair_and_Rework.pdf PDF
06_COMBINED_EDLS.pdf PDF
05_COMBINED_ITEM_DESCRIPTIONS.pdf PDF
11_CDRLs.pdf PDF
09_QALI_50102.pdf PDF
04_Packaging_SOW.pdf PDF
FA821321Q3004.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FIRST ARTICLE REQUIREMENTS 1. DATE

07 APR 2020(AFMCI 64-110, AFMCI 23-102 and FAR Part 9, Sub Part 9.3)(Additional Instructions on Page 3)

2. PR / MIPR NUMBER 3. CAGE / REFERENCE NUMBER

61423 / 877597-1

4. NSN

1377013366648ES

5. FIRST ARTICLE QUANTITY

THE FIRST ARTICLE IS 10 UNIT(S) OF LOT / ITEM ea

AND WILL BE: PART OF PRODUCTION QUANTITY X IN ADDITION TO PRODUCTION QUANTITY

6. ARTICLES

X WILL WILL NOT SERVE AS A MANUFACTURING STANDARD

7. LONG LEAD TIME ITEMS

REQUIRED X NOT REQUIRED

(See FAR 52.209-3 OR -4, alternate II)

8. SPECIAL REQUIREMENT/PRODUCTION FACILITIES (See FAR 52.209-3 OR -4 Alternate I)

X REQUIRED NOT REQUIRED

"The First Article offered must be manufactured at the facilities in which that item is to be produced under the contract, or if the First Article is a component not manufactured by the contractor, such component must be manufactured at the facilities in which the component is to be produced for the contract. A certification to this effect must accompany each First Article which is offered."

9. TEST / INSPECTION REQUIREMENTS

A. X CONTRACTOR TESTING

GOVERNMENT TESTING

Performance or other characteristics which the First Articles must meet are

Items to be functioned and meet performance requirements of current Government-approved ATP. Successful FAT results and FAT report approval required prior to manufacturing of deliverable production items IAW contract requirements.

B. The detailed technical requirements for First Article approval tests are contained in

Latest Government-approved ATP & MIL-C-83124

4 ea units shall be submitted to Vibe followed by T/S/H&A with 2 fired at -65F and 2 fired at 200F. 4 ea items shall be submitted to Shock followed by T/S/H&A with 2 fired at -65F and 2 fired at 200F. The remaining 2 items shall be submitted to T/S/H&A with 1 fired at -65F and 1 fired at 200F.

(Cite Spec and Para number)

C. X TEST PLAN REQUIRED

Number of days for government approval / disapproval 30 days.

D. Contractor's notification to ACO and cognizant engineer

(Requesting Activity) of test time and location due 10 days prior to start of testing.

E. X TEST REPORT REQUIRED

(1) Forwarded to

AFLCMC/EBHJ

6044 Dogwood Ave, BLDG 1256

Hill AFB, UT 84056-5819

& Submitted through WAWF

(2) Government written notice of approval / disapproval due 30 days after receipt of contractor's report.

F. FIRST ARTICLE DELIVERY

(1) Due within calendar days from date contract.

(2) Notify calendar days prior to shipment.

(3) Delivered to government at

N/A contractor test

(Set Forth Consignee and Address)

(4) Government written notice of approval / disapproval within 30 days after receipt of first article package.

G. Estimated cost of government testing / inspection evaluation.

$0.0000

Page 1 of 2AFMC IMT 260, 20020830, V-3 Version 3Generated by PRPS using Jasper Reports on 07 Apr 2020

07 APR 2020(AFMCI 64-110, AFMCI 23-102 and FAR Part 9, Sub Part 9.3)(Additional Instructions on Page 3)

10. DISPOSITION OF FIRST ARTICLES

Approved First Articles will be forwarded to

X 10 (insert quantity) First Articles will be expended in testing. Residual components of disapproved First Articles will be returned to the contractor

X will be retained by vendor pending disposition instructions from the contractor.

First Articles will be installed on aircraft/equipment to determine proper fit/function. Approved article will remain on the aircraft/equipment and will not be forwarded to USAF Supply, but will be considered part of the contract quantity.

Disapproved First Articles will be returned to the contractor will be retained by pending disposition instructions from the contractor.

On purchase requests designated as direct shipments the following disposition will apply. (NOTE: Always applicable on Foreign Military Sales (FMS)).

a. Approved First Articles will be returned to the contractor for shipment with production item.

b. Disposition of disapproved First Articles will remain the same as marked above.

Other Disposition:

11. CONDITION(S) FOR WAIVER OF FIRST ARTICLE APPROVAL

a. Offerors who have previously furnished production quantities of the same or similar article to the prime contractor for delivery to the Government, DoD, Air Force.

b. Offerors currently in production of the same or similar article for a Government, DoD, Air Force contract and who have received First Article approval under the existing contract.

c. Offerors who have previously furnished production quantities of the same or similar articles to the Government, DoD, Air Force, provided articles thus furnished, have exhibited satisfactory performance in service in the opinion of the Air Force.

d. X Provided not more than 60 months have elapsed since completion of the contract.

e. First Article testing will not be waived.

f. X See Remarks in block 12 below.

NOTE TO BUYER: UNDER CONDITIONS A AND C ABOVE, THE COGNIZANT ENGINEERING ACTIVITY WILL DECIDE WHETHER OR NOT THE ITEM HAS EXHIBITED SATISFACTORY PERFORMANCE IN SERVICE AND PREPARE AND RETAIN SUPPORTING DOCUMENTATION TO FULLY JUSTIFY THIS DECISION. THE BUYER MUST SOLICIT DUAL PRICES (That is, both with and without requirement for first article approval) AND MUST FURNISH THE COGNIZANT ENGINEERING ACTIVITY WITH THE FOLLOWING INFORMATION ON THE PREVIOUSLY SUPPLIED ARTICLE:

A. PROCURING OFFICE B. CONTRACT NUMBER C. DATE OF CONTRACT D. SPECIFICATION NUMBER AND REVISION

12. REMARKS

Tanner, Matthew WNAME: 07 APR 2020DATE:

Any request to waive FAT requirement by contractor shall be submitted by vendor with supporting data and reviewed and approved/disapproved by cognizant engineer prior to contract award.

13. COGNIZANT ENG ORGANIZATION RESPONSIBLE FOR APPROVING TEST

(Name, Organization, Phone)

Tanner, Matthew W

AFLCMC/EBHJ

801-777-2926

777-2926

14. COGNIZANT ENG ORGANIZATION RESPONSIBLE FOR CONDUCTING

TEST (Name, Organization, Phone)

Page 2 of 2AFMC IMT 260, 20020830, V-3 Version 3Generated by PRPS using Jasper Reports on 07 Apr 2020

07 APR 2020(AFMCI 64-110, AFMCI 23-102 and FAR Part 9, Sub Part 9.3)(Additional Instructions on Page 3)

2. PR / MIPR NUMBER 3. CAGE / REFERENCE NUMBER

57597 / 201240

4. NSN

1377016319582ES

5. FIRST ARTICLE QUANTITY

THE FIRST ARTICLE IS 10 UNIT(S) OF LOT / ITEM ea

AND WILL BE: PART OF PRODUCTION QUANTITY X IN ADDITION TO PRODUCTION QUANTITY

6. ARTICLES

X WILL WILL NOT SERVE AS A MANUFACTURING STANDARD

7. LONG LEAD TIME ITEMS

REQUIRED X NOT REQUIRED

(See FAR 52.209-3 OR -4, alternate II)

8. SPECIAL REQUIREMENT/PRODUCTION FACILITIES (See FAR 52.209-3 OR -4 Alternate I)

X REQUIRED NOT REQUIRED

"The First Article offered must be manufactured at the facilities in which that item is to be produced under the contract, or if the First Article is a component not manufactured by the contractor, such component must be manufactured at the facilities in which the component is to be produced for the contract. A certification to this effect must accompany each First Article which is offered."

9. TEST / INSPECTION REQUIREMENTS

A. X CONTRACTOR TESTING

GOVERNMENT TESTING

Performance or other characteristics which the First Articles must meet are

Items to be functioned and meet performance requirements of current Government-approved ATP. Successful FAT results and FAT report approval required prior to manufacturing of deliverable production items IAW contract requirements.

B. The detailed technical requirements for First Article approval tests are contained in

Latest Government-approved ATP & MIL-C-83124

4 ea units shall be submitted to Vibe followed by T/S/H&A with 2 fired at -65F and 2 fired at 200F. 4 ea items shall be submitted to Shock followed by T/S/H&A with 2 fired at -65F and 2 fired at 200F. The remaining 2 items shall be submitted to T/S/H&A with 1 fired a -65F and 1 fired at 200F.

(Cite Spec and Para number)

C. X TEST PLAN REQUIRED

Number of days for government approval / disapproval 30 days.

D. Contractor's notification to ACO and cognizant engineer

(Requesting Activity) of test time and location due 10 days prior to start of testing.

E. X TEST REPORT REQUIRED

(1) Forwarded to

AFLCMC/EBHJ

6044 Dogwood Ave, BLDG 1256

Hill AFB, UT 84056-5819

& Submitted through WAWF

(2) Government written notice of approval / disapproval due 30 days after receipt of contractor's report.

F. FIRST ARTICLE DELIVERY

(1) Due within calendar days from date contract.

(2) Notify calendar days prior to shipment.

(3) Delivered to government at

N/A contractor test

(Set Forth Consignee and Address)

(4) Government written notice of approval / disapproval within 30 days after receipt of first article package.

G. Estimated cost of government testing / inspection evaluation.

Page 1 of 2AFMC IMT 260, 20020830, V-3 Version 3Generated by PRPS using Jasper Reports on 07 Apr 2020

07 APR 2020(AFMCI 64-110, AFMCI 23-102 and FAR Part 9, Sub Part 9.3)(Additional Instructions on Page 3)

10. DISPOSITION OF FIRST ARTICLES

Approved First Articles will be forwarded to

X 10 (insert quantity) First Articles will be expended in testing. Residual components of disapproved First Articles will be returned to the contractor

X will be retained by vendor pending disposition instructions from the contractor.

First Articles will be installed on aircraft/equipment to determine proper fit/function. Approved article will remain on the aircraft/equipment and will not be forwarded to USAF Supply, but will be considered part of the contract quantity.

Disapproved First Articles will be returned to the contractor will be retained by pending disposition instructions from the contractor.

On purchase requests designated as direct shipments the following disposition will apply. (NOTE: Always applicable on Foreign Military Sales (FMS)).

a. Approved First Articles will be returned to the contractor for shipment with production item.

b. Disposition of disapproved First Articles will remain the same as marked above.

Other Disposition:

11. CONDITION(S) FOR WAIVER OF FIRST ARTICLE APPROVAL

a. Offerors who have previously furnished production quantities of the same or similar article to the prime contractor for delivery to the Government, DoD, Air Force.

b. Offerors currently in production of the same or similar article for a Government, DoD, Air Force contract and who have received First Article approval under the existing contract.

c. Offerors who have previously furnished production quantities of the same or similar articles to the Government, DoD, Air Force, provided articles thus furnished, have exhibited satisfactory performance in service in the opinion of the Air Force.

d. X Provided not more than 60 months have elapsed since completion of the contract.

e. First Article testing will not be waived.

f. X See Remarks in block 12 below.

NOTE TO BUYER: UNDER CONDITIONS A AND C ABOVE, THE COGNIZANT ENGINEERING ACTIVITY WILL DECIDE WHETHER OR NOT THE ITEM HAS EXHIBITED SATISFACTORY PERFORMANCE IN SERVICE AND PREPARE AND RETAIN SUPPORTING DOCUMENTATION TO FULLY JUSTIFY THIS DECISION. THE BUYER MUST SOLICIT DUAL PRICES (That is, both with and without requirement for first article approval) AND MUST FURNISH THE COGNIZANT ENGINEERING ACTIVITY WITH THE FOLLOWING INFORMATION ON THE PREVIOUSLY SUPPLIED ARTICLE:

A. PROCURING OFFICE B. CONTRACT NUMBER C. DATE OF CONTRACT D. SPECIFICATION NUMBER AND REVISION

12. REMARKS

Tanner, Matthew WNAME: 07 APR 2020DATE:

Any request to waive FAT requirement by contractor shall be submitted by vendor with supporting data and reviewed and approved/disapproved by cognizant engineer prior to contract award.

13. COGNIZANT ENG ORGANIZATION RESPONSIBLE FOR APPROVING TEST

(Name, Organization, Phone)

Tanner, Matthew W

AFLCMC/EBHJ

801-777-2926

777-2926

14. COGNIZANT ENG ORGANIZATION RESPONSIBLE FOR CONDUCTING

Page 2 of 2AFMC IMT 260, 20020830, V-3 Version 3Generated by PRPS using Jasper Reports on 07 Apr 2020

07 APR 2020(AFMCI 64-110, AFMCI 23-102 and FAR Part 9, Sub Part 9.3)(Additional Instructions on Page 3)

2. PR / MIPR NUMBER 3. CAGE / REFERENCE NUMBER

54181 / 2-102060-1

4. NSN

1377016319588ES

5. FIRST ARTICLE QUANTITY

THE FIRST ARTICLE IS 10 UNIT(S) OF LOT / ITEM ea

AND WILL BE: PART OF PRODUCTION QUANTITY X IN ADDITION TO PRODUCTION QUANTITY

6. ARTICLES

X WILL WILL NOT SERVE AS A MANUFACTURING STANDARD

7. LONG LEAD TIME ITEMS

REQUIRED X NOT REQUIRED

(See FAR 52.209-3 OR -4, alternate II)

8. SPECIAL REQUIREMENT/PRODUCTION FACILITIES (See FAR 52.209-3 OR -4 Alternate I)

X REQUIRED NOT REQUIRED

"The First Article offered must be manufactured at the facilities in which that item is to be produced under the contract, or if the First Article is a component not manufactured by the contractor, such component must be manufactured at the facilities in which the component is to be produced for the contract. A certification to this effect must accompany each First Article which is offered."

9. TEST / INSPECTION REQUIREMENTS

A. X CONTRACTOR TESTING

GOVERNMENT TESTING

Performance or other characteristics which the First Articles must meet are

Items to be functioned and meet performance requirements of current Government-approved ATP. Successful FAT results and FAT report approval required prior to manufacturing of deliverable production items IAW contract requirements.

B. The detailed technical requirements for First Article approval tests are contained in

Latest Government approved ATP & MIL-C-83124

4 ea units shall be submitted to Vibe followed by T/S/H&A with 2 fired at -65F and 2 fired at 200F. 4 ea items shall be submitted to Shock followed by T/S/H&A with 2 fired at -65F and 2 fired at 200F. The remaining 2 items shall be submitted to T/S/H&A with 1 fired a -65F and 1 fired at 200F.

(Cite Spec and Para number)

C. X TEST PLAN REQUIRED

Number of days for government approval / disapproval 30 days.

D. Contractor's notification to ACO and cognizant engineer

(Requesting Activity) of test time and location due 10 days prior to start of testing.

E. X TEST REPORT REQUIRED

(1) Forwarded to

AFLCMC/EBHJ

6044 Dogwood Ave, BLDG 1256

Hill AFB, UT 84056-5819

& Submitted through WAWF

(2) Government written notice of approval / disapproval due 30 days after receipt of contractor's report.

F. FIRST ARTICLE DELIVERY

(1) Due within calendar days from date contract.

(2) Notify calendar days prior to shipment.

(3) Delivered to government at

N/A contractor test

(Set Forth Consignee and Address)

(4) Government written notice of approval / disapproval within 30 days after receipt of first article package.

G. Estimated cost of government testing / inspection evaluation.

Page 1 of 2AFMC IMT 260, 20020830, V-3 Version 3Generated by PRPS using Jasper Reports on 07 Apr 2020

07 APR 2020(AFMCI 64-110, AFMCI 23-102 and FAR Part 9, Sub Part 9.3)(Additional Instructions on Page 3)

10. DISPOSITION OF FIRST ARTICLES

Approved First Articles will be forwarded to

X 10 (insert quantity) First Articles will be expended in testing. Residual components of disapproved First Articles will be returned to the contractor

X will be retained by vendor pending disposition instructions from the contractor.

First Articles will be installed on aircraft/equipment to determine proper fit/function. Approved article will remain on the aircraft/equipment and will not be forwarded to USAF Supply, but will be considered part of the contract quantity.

Disapproved First Articles will be returned to the contractor will be retained by pending disposition instructions from the contractor.

On purchase requests designated as direct shipments the following disposition will apply. (NOTE: Always applicable on Foreign Military Sales (FMS)).

a. Approved First Articles will be returned to the contractor for shipment with production item.

b. Disposition of disapproved First Articles will remain the same as marked above.

Other Disposition:

11. CONDITION(S) FOR WAIVER OF FIRST ARTICLE APPROVAL

a. Offerors who have previously furnished production quantities of the same or similar article to the prime contractor for delivery to the Government, DoD, Air Force.

b. Offerors currently in production of the same or similar article for a Government, DoD, Air Force contract and who have received First Article approval under the existing contract.

c. Offerors who have previously furnished production quantities of the same or similar articles to the Government, DoD, Air Force, provided articles thus furnished, have exhibited satisfactory performance in service in the opinion of the Air Force.

d. X Provided not more than 60 months have elapsed since completion of the contract.

e. First Article testing will not be waived.

f. X See Remarks in block 12 below.

NOTE TO BUYER: UNDER CONDITIONS A AND C ABOVE, THE COGNIZANT ENGINEERING ACTIVITY WILL DECIDE WHETHER OR NOT THE ITEM HAS EXHIBITED SATISFACTORY PERFORMANCE IN SERVICE AND PREPARE AND RETAIN SUPPORTING DOCUMENTATION TO FULLY JUSTIFY THIS DECISION. THE BUYER MUST SOLICIT DUAL PRICES (That is, both with and without requirement for first article approval) AND MUST FURNISH THE COGNIZANT ENGINEERING ACTIVITY WITH THE FOLLOWING INFORMATION ON THE PREVIOUSLY SUPPLIED ARTICLE:

A. PROCURING OFFICE B. CONTRACT NUMBER C. DATE OF CONTRACT D. SPECIFICATION NUMBER AND REVISION

12. REMARKS

Tanner, Matthew WNAME: 07 APR 2020DATE:

Any request to waive FAT requirement by contractor shall be submitted by vendor with supporting data and reviewed and approved/disapproved by cognizant engineer prior to contract award.

13. COGNIZANT ENG ORGANIZATION RESPONSIBLE FOR APPROVING TEST

(Name, Organization, Phone)

Tanner, Matthew W

AFLCMC/EBHJ

801-777-2926

777-2926

14. COGNIZANT ENG ORGANIZATION RESPONSIBLE FOR CONDUCTING

Page 2 of 2AFMC IMT 260, 20020830, V-3 Version 3Generated by PRPS using Jasper Reports on 07 Apr 2020

01-336-6648 First Article Requirements
01-631-9582 First Article Requirements
01-631-9588 First Article Requirements