Solicitation FA8213-17-R-0106 Contractor Questions 15 November 2017
Question #7:
Can you explain the reason for the multiple extensions that have occurred the day before the bid is due?
Government Response:
Due to the Government making multiple changes to the requirements, the Government needs to allow all contractors adequate time for contractors to complete their proposals. The Government has allowed perspective contractors to request extension to the proposal due date and the Government has extended the proposal due date. As long as there are no changes to the requirements the Government will not be extending the proposal again.