Q&As_Rev1.pdf

PDF 9 KB Posted

Attached to
A10 Aircraft Windshield Canopy Bow Federal contract opportunity
Solicitation number
FA8212-18-R-0029
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

View the file

Other files for this federal contract opportunity

Other files attached to A10 Aircraft Windshield Canopy Bow, newest first.
File Type Posted
Q&AsRev3.pdf PDF
FA821218R0029_______0001.pdf PDF
Q&AsRev2.pdf PDF
Q&As.pdf PDF
CDRL_FA_Test_Report.pdf PDF
PKGRQMT_REPORT.pdf PDF
Section_L_Price_Only_QR.pdf PDF
FA821218R0029.pdf PDF
Section_M_Price_Only_QR.pdf PDF
SPI.pdf PDF
EDL.pdf PDF
CDRL_IMP_IMS.pdf PDF
SOW.pdf PDF
MQR.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers

A10 Windshield Canopy Bow

Questions:

1. When is the anticipated award date?

2. Is the Requirement to not drill the four attach point holes (As shown in Section D-D of Drawing 160D117102) and to ship the four bushings with the bows. Please clarify if this requirement (not drilling the holes) is to be part of the bridge contract as well.

3. On the drawing on note 11 it states there are 3D Models for these parts. Are those models available to us?

Answers:

1. Estimated award date is 9 July 2018.

2. Correct, the 4 attach point holes shown in Section D-D of Drawing 160D117102 are to not be drilled and the required bushings are to be shipped with each bow.

3. The 3D Models referenced by note 11 are available. They are listed on the EDL, REV 11 dated 22 May 2018 that was posted on FBO 25 May 2018. The models are 160D117102-21 REV M and 160D117102C-19 REV P.