This document outlines incentives for meeting schedule metrics on a federal contract for the Advanced-Wing Continuation Kit for the A-10 Thunderbolt aircraft. The contractor may earn up to $17 million in additional profit for timely delivery of the First Article, Low Rate Initial Production Lots 1 through 3. A $12 million incentive is available for First Article delivery within 24 months, with $100,000 deducted for any open issues and $1 million deducted per month of delay. LRIP Lots 1 through 3 have incentives totaling $5 million if delivered within 3, 5, and 7 months of the First Article, respectively, subject to the same issue and delay deductions. The solicitation is for the U.S. Air Force Lifecycle Management Center for the A-10 ATTACK program under solicitation FA8202-18-R-1001.

RFP Attachment 3 - Subcontractor and Joint Venture Partner Consent

View the file

Other files for this federal contract opportunity

Other files attached to A-10 Thunderbolt Advanced-Wing Continuation Kit (ATTACK), newest first.
File Type Posted
Non_Proprietary_Questions_211_-_212.xlsx XLSX spreadsheet
Section_L.docx DOCX document
Non_Proprietary_Questions_162_-_210.xlsx XLSX spreadsheet
TEP_Pricing_Matrix_8-3-2018.xlsx XLSX spreadsheet
Section_M.docx DOCX document
Form_260.pdf PDF
ATTACHMENT_F_-_Government_Furnished_Information_List_Rev_A.pdf PDF
RFP_Attach_1_Instruct_to_Offerors.pdf PDF
9579776_Digital_Data_Delivery_Requirements.pdf PDF
RFP_Attach_3_-_SubKtr_and_Joint_Venture_Partner_Consent.docx DOCX document
TM-86-01_RevA.pdf PDF
ppi_tool.accdb MDB file
Non_Proprietary_Questions_141-161.pdf PDF
A016_CDRL.pdf PDF
A035_CDRL.pdf PDF
A010_CDRL.pdf PDF
A011_CDRL.pdf PDF
A023_CDRL_-.pdf PDF
A003_CDRL.pdf PDF
A009_CDRL.pdf PDF
A008_CDRL.pdf PDF
RFP_Attach_7_SUPPLEMENT_Data_Entry_Form.pdf PDF
Section_L.docx DOCX document
Section_M.docx DOCX document
A030_CDRL.pdf PDF
SOW_ATTACHMENT_C_Contract_Data_Requirements_List_CDRL_and_Distribution.pdf PDF
A029_CDRL.pdf PDF
ATTACK_SOW.pdf PDF
A014_CDRL.pdf PDF
A019_CDRL.pdf PDF
A026_CDRL.pdf PDF
A034_CDRL.pdf PDF
DD_form_2345.pdf PDF
A036_CDRL.pdf PDF
A002_CDRL.pdf PDF
A028_CDRL.pdf PDF
A020_CDRL.pdf PDF
RFP_Attach_6_-_TEP_Pricing_Matrix.xlsx XLSX spreadsheet
A042_CDRL.pdf PDF
RFP_Attach_7_Government_Furnished_Property_List.xlsx XLSX spreadsheet
A040_CDRL.pdf PDF
Non_Proprietary_Questions_(27Apr_thru_RFP).pdf PDF
A006_CDRL.pdf PDF
RFP_Attach_2_Past_Perf_Info_Sheet.docx DOCX document
A021_CDRL.pdf PDF
A029_TMCR.pdf PDF
A001_CDRL.pdf PDF
A013_CDRL.pdf PDF
A022_CDRL.pdf PDF
A024_CDRL.pdf PDF
Show all 50

A-10 Thunderbolt Advanced-Wing Continuation Kit (ATTACK) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CLIN 0005

SCHEDULE INCENTIVE ATTACHMENT

In addition to the profit/fee set forth elsewhere in the contract, the Contractor may earn an additional amount of up to $17,000,000 for meeting appropriate performance and schedule metrics as determined through application of the objective criteria outlined below:

First Article (FA) Incentive: An incentive of $12,000,000 may be earned for a First Article delivered within 24 months after contract award. Deductions will be calculated based on calendar months and open issues without approved corrective action as follows:

- $100,000 will be deducted for every issue without approved corrective action at FA delivery o Request for Variance will be approved or deductions calculated on a case by case basis

- $1,000,000 will be deducted for each month delivery exceeds the 24 month incentivized schedule

Low Rate Initial Production (LRIP) Incentive: An incentive of $5,000,000 may be earned for LRIPs delivered after FA as follows:

- LRIP 1 delivery = FA + 3 months

- LRIP 2 delivery = FA + 5 months

- LRIP 3 delivery = FA + 7 months

Deductions will be calculated based on calendar months and open issues without approved corrective action as follows:

- $100,000 will be deducted for every issue without approved corrective action at LRIP 3 delivery o Request for Variance will be approved or deductions calculated on a case by case basis

- $1,000,000 will be deducted for each month delivery exceeds any monthly deadline stated above

The incentive fee will be based on delivery date.