Bldg228RFIQ&A.doc

DOC document 49 KB Posted

Attached to
Fuel Tanks Federal contract opportunity
Solicitation number
FA8201-18-Q-0002
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

About this file

Responses to submitted questions

View the file

Other files for this federal contract opportunity

Other files attached to Fuel Tanks, newest first.
File Type Posted
STATEMENT_OF_WORK_-_Bldg._228.docx DOCX document
WageDetermination.pdf PDF
FA8201-18-Q-0002.docx DOCX document
Lead_and_Asbestos_Report.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

75TH CIVIL ENGINEER SQUADRON (AFMC)

HILL AIR FORCE BASE, UTAH 84056

1 February 2018

MEMORANDUM FOR: AFMC OL H/PZIOC

FROM: 75 CES/SABER

SUBJECT: Building 228 RFI Questions and Answers

1. Will soil sampling be required at pipe locations that are going to be closed?

Answer: No, unless soil will be removed from the site and disposed off-Base.

2. Whose responsibility is it to file the closure plan and notice? Contractor or Base Environmental?

Answer: There is no Closure Plan nor Closure Notice required in the SOW. 10.3 of SOW provides a link to required Utah DEQ Underground Storage Tank Installation Notification Form. The Contractor should complete the form and provide directly to DERR. A copy of the completed form (.pdf) should be provided to 75 CEG/CEIE via xxxx at the time it is submitted to DERR. Note: By rule, the form needs to be submitted within 30 days of the completion of work (R311-203-2); however, removal of the Red Tags may be contingent on receipt of this form by DERR so it should be submitted as quickly as possible upon completion of the work.

3. For the stainless pipe welding will we need to follow the UFC 3-460.01 and have continuous inspection and/or x-ray?

Answer: Where there’s going to be minimal welding, will be okay for one or two days as needed, wouldn’t need to be here for the length of the project. Yes, IAW the Government SOW, please follow UFC 3-460.01.

4. Confirm that the contractor is to provide the electrical per the SOW. The line leak detector is mechanical and cannot be electrical due to the length of pipe. As such there is no electrical needed on the project. There is also no Veeder-Root modifications needed since the line leak detector is mechanical as well.

Answer: Offerors need to provide a proposal for a functional and working detector in the sump, upon completion of the task order award. If electrical and/or Veeder-Root modifications are not required, then please submit proposal as such.

5. After reviewing this project we anticipate that the overfill valve will need to be a remote-fill style, because it will dump into a "tee" above the man way cover of the north tank. Is this what the government is wanting?

Answer: It was discussed during the Offerors site walk, to reuse existing overfill protection that is already there, not sure what the tee is on top of north tank is for? Mr. Randall Judd mentioned at the site walk, that there isn’t a fill tube installed in the north tank. Offerors shall ensure fill tube is correctly installed and re-use existing high level shutoff valve.

6. Pea-gravel backfill needs to be used to meet the tank sump MFG. recommended practices to maintain warranty. So there will be no way to test compaction as requested in the SOW. Does the government understand this is the way in which the contractor will be required to proceed?

Answer: The Government does understand what is required and recommend following the Manufactures recommendation. The compaction requirements outlined in Sections 7.0, 8.0 and 9.0 are if needed, i.e. if Offerors need to excavate surrounding asphalt and/or concrete to access the sump, then the Offerors need to follow these sections.

7. When are questions due?

Answer: Questions were RFQ were due by January 31, 2018.

8. When is the bid due date?

Answer: Request for Quote Due Date is February 2, 2018.

9. Will bids be acceptable through email or do they need to be submitted by hardcopy?

Answer: Bids will be accepted through email.