Draft_OC14851_Product_Description_CNC_Upgrade.pdf
PDF 79 KB Posted
- Attached to
- Progressive Surface CNC Upgrade Federal contract opportunity
- Solicitation number
- FA8132-16-Q-0013
About this file
Draft OC14851 Product Description CNC Upgrade
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SF30_SOW_Amendment.pdf | ||
| Updated_SOW.docx | DOCX document | |
| FA8132-16-Q-0013-0001.pdf | ||
| Technical_Proposal_Evaluation-Critical_Factor_List.pdf | ||
| SOW_14851_03042016.pdf | ||
| Redacted_JA_Fanuc_Upgrade_14851.pdf | ||
| OC14851_Product_Description.docx | DOCX document | |
| FA8132-16-Q-0013_CNC_Upgrade_Solicitation.pdf | ||
| Draft_SOW_CNC_Upgrade.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRODUCT DESCRIPTION
FOR
OC14851 CNC UPGRADE PURCHASE
24 Feb 2016 Tinker Air Force Base
Oklahoma City, OK 73145
1. PURPOSE AND SCOPE
1.1. The purpose of this Product Description is to upgrade and update the electrical components of the Shotpeening system including the CNC, Servo Drives, motors, and PLC system for OC 14851. This machine is used for the F100 core workload for 76
PMXG.
1.2. The systems shall be modified to have FanucTM components and PRIMSTM software on the PLC system to interface with the CNC.
2. BACKGROUND
2.1. The Allen Bradley electrical components on the OC14851 are degrading and need to be replaced with components that are supportable. The current Allen Bradley CNC components are no longer being manufactured and refurbished replacement parts must be located and configured to work with the equipment. However these refurbished components have also proven to be unreliable.
2.2. The CNC precisely positions the nozzle and the shot flow and air pressure parameters. It works in direct conjunction with the motors and servo drives which direct the shot stream onto the surface of the part. Therefore when the components are inoperable the entire process ceases. This equipment needs upgrading to prevent future breakdown of the machine.
2.3. The current PLC utilizes PRIMS software to interface with the CNC PRIMS user interface is the standard operator interface on the PLC for the 76th Propulsion Maintenance Group uses to program and control the robotic arm/gantry motions, air pressure, and shot flow parameters, for its shot peening equipment. Use of this software aids in the minimization of single point failures due to transferability between similar equipment. Machine operators and robot programmers are trained and experienced in its operation and the software has proven to be reliable.
3. PROJECT OBJECTIVES
3.1. The Government requires the following materials in the specified quantity:
LINE NSN NOUN TOTAL
QTY
1 NA Fanuc 31i-A5 CNC with servo drives, motors, and cables for 5 axis system
| 2 | NA Control Panel to house CNC & Servo Drives 1 |
| 3 | NA Air Conditioner for control Panel 1 |
| 4 | NA PLC with PRIMS software 1 |
| 5 | NA 19” touchscreen monitor and industrial keyboard 1 |
| 6 | NA Drawings and Manual updates for modified machine 1 |
| 7 | NA Conversion software to convert AB processing programs |
to Fanuc
3.2. The Government requires that all items are packaged in such a manner to prevent damage during the shipping process.
3.3. The Government requires turnkey removal of the old system and installation of the new system.
3.4. The Government requires that the supplier provide 2 days of training on the upgraded equipment.
3.5. The Government requires that the supplier provide a 12 month (minimum) warranty, from the date of shipment, of the equipment to be free of defects due to workmanship and materials.
3.5.1. Any reported findings of these defects shall be repaired by the contractor, without financial obligation to the Government (including, but not limited to shipping costs).