Revised Autoclave Performance Work Statement
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Autoclave_Pictures.pdf | ||
| FA8125-15-R-0011-0002.pdf | ||
| WAGE_DETERMINATION_2014.pdf | ||
| FA8125-15-R-0011-0001.pdf | ||
| Appendix_D.pdf | ||
| Appendix_A.pdf | ||
| Safety_Appendix_C.pdf | ||
| Wage_Determination_(25_July_14).pdf | ||
| PWS.pdf | ||
| Combined_Synopsis_Solicitation_FA8125-15-R-0011.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
One-Time Relocation
Of Autoclave
6 March 2015
PREPARED BY:
OC-ALC/OBWK
TINKER AFB 73145
1. DESCRIPTION OF SERVICES/GENERAL INFORMATION.
Scope. The Contractor shall provide all labor, tools, equipment, test equipment, material, parts, quality control, transportation and inspection manuals necessary to perform the Autoclave Relocation at the Oklahoma City–Air Logistics Complex (OC-ALC). The Contractor shall also provide Personal Protective Equipment (PPE) and clothing, to include reflective clothing (belt, vest, etc.); hearing and eye protection, to include prescription safety glasses; safety harnesses;
fall protection equipment; lifting equipment and any incidentals necessary to perform the requirements of this Performance Work Statement (PWS). The Contractor shall be responsible for insuring all services, parts and Original Equipment Manufacturer (OEM) components provided under this contract are in accordance with (IAW) the terms and conditions outlined herein this PWS. The equipment is listed in Appendix A.
1.1. Requested Services: The Contractor shall remove, load, transport and reinstall the Autoclave and accessory equipment from Bldg. 2211 to Bldg. 9001 between the days of, 1 July - 30 Oct 2015. The Contractor shall provide a crane and lifting devices with capacity to lift 20,000 - 30,000 pounds and raise the Autoclave from the floor to a flatbed trailer. The Contracting Officer Representative (COR) will notify the Contractor, fifteen (15) work days in advance of the move.
1.1.1. Contractor shall perform an operational check and inspection of the Autoclave and its accessories prior to disconnection/relocation to acquire an operational baseline and determine overall condition of the Autoclave and accessory equipment prior to relocation. The Contractor shall provide a copy of the operational check and inspection to the Government Technical point of contact (POC) prior to disassembly/relocation of the Autoclave.
1.1.2. The Autoclave shall be set up and bolted to the floor IAW Appendix D. Contractor shall provide all sundry items for this relocation effort. The Contractor shall connect all accessory equipment/interconnections associated wiring and piping: to include power panel, vacuum system, vacuum station, control panel, cooling plumbing, and ventilation. Contractor shall connect control wiring (analog signals and digital signals) from the Autoclave control panel to the data acquisition and control systems.
1.1.3. The Contractor shall perform an operational check and inspection of the Autoclave and its accessories to ensure the condition and function of the Autoclave is the same as it was prior to relocation. The Contractor shall provide a copy of the operational check and inspection after the relocation/assembly and demonstrate to Government personnel that the Autoclave is fully operational upon completion.
1.2. Service Report: Immediately upon completion of the maintenance support services and before leaving the OC-ALC, the Contractor shall provide a written Service Report to the Government identified Technical POC or COR. The Government identified Technical POC will forward the service report to the COR within two (2) business days of receipt. The Contractor shall provide, by fax or email, the final service report within five (5) business days to the COR.
As a minimum, the final service report shall contain the following information:
PWS – Autoclave Relocation
• name of the company
• requested service date
• description of services provided
• additional services recommended (if any)
• printed name and signature of technician who performed the service(s)
• printed name and signature of on-site Government Technical POC or COR
• start and completion dates
• complete breakdown of the labor cost (hours and rate)
• material(s) and part(s) used
• details of any other charges
• printed name and signature stating only new parts and materials were used
1.3. Quality Assurance: According to the contract’s inspection clause, the Government will evaluate the Contractor’s performance under this contract. The COR will participate in the administration of this contract. Any matter concerning a change to the scope, prices, terms or conditions of this contract shall be referred to the Contracting Officer (CO). All services to be performed by the Contractor during the period of this contract will be subject to review by the CO or COR.
1.4. Corrective Action Report/Complaint Contractor Response Time: The Contractor shall provide a written response within two (2) business days which addresses the root cause, corrective action and preventive action(s) in relation to the submitted CAR or Customer Complaint.
1.5. Maintenance Documentation: The Contractor shall notify the Government Technical POC upon completion of each action IAW OC-ALC OI 21-203, Chapter 1, 2 and 3, as applicable.
1.6. Continuation of Essential DoD Contractor Services During Crisis: This requirement has been determined not to be essential and does not require continued support during a crisis as defined in DFARS 252.237-7023.
1.7. Hours of Operation: The Contractor shall perform work required under this contract during the following days and hours: Monday through Friday, 6:30 AM-3:30 PM. These dates and hours exclude Federal Holidays, base closures due to inclement weather and Furlough Days, as applicable. If additional hours are required the Contractor should contact the CO for approval.
Upon approval, the Government Technical POC or COR shall be present with the Contractor.
1.8. Special Qualifications: The Contractor shall be a subject matter expert (SME) in relocating, setting up, operation and troubleshooting of Autoclaves. The Contractor shall provide a resume listing a minimum of three (3) similar installation or relocation efforts performed with Autoclaves at receipt of proposal.
1.9. Contractor Personnel: The Contractor shall provide the name of the Contract Manager (CM) and any alternates who shall act for the Contractor when the CM is absent. They shall be designated to the CO and COR, in writing, within five (5) business days after the contract award date. The Contractor shall provide telephone numbers and email addresses where the CM and alternates may be contacted at any time. The CM or alternate shall have full authority to act for the Contractor on all matters relating to operation of this contract at the OC-ALC on Tinker Air Force Base (AFB). The CM or alternate shall be available to meet on the installation with Government personnel designated by the CO to discuss problem areas. The Contractor shall provide a CM who can read, write, speak, and understand English fluently.
1.10. The Contractor and Contractor personnel shall be required to identify themselves as Contractor personnel by introducing themselves or being introduced as Contractor personnel.
The Contractor personnel shall also display distinguishing badges or other visible identification for meetings with Government personnel or while performing work for the OC-ALC on Tinker AFB. The Contractor and Contractor personnel shall identify themselves as Contractor employees in telephone conversations and in formal and informal written correspondence.
1.11. Listing of Contractor Employees: The Contractor shall provide an initial listing of the Contractor employees’ names and position titles to the COR within five (5) business days after the contract award date. Within five (5) business days, the Contractor shall also provide an updated listing of personnel to the COR when employees affecting the work of this contract change status or position.
1.11.1. The Contractor shall not employ persons on this contract if such employee is identified to the Contractor as a potential threat to the health, safety, security, and/or general well-being, or operational mission of the installation and its population. The Contractor shall not employ any person who is an employee of the United States (US) Government if the employment of the person would create a conflict of interest. The Contractor shall not employ any person who is an employee of the Department of the Air Force (AF), either military or civilian, unless such person seeks and receives approval according to the DoD 5500.7-R Joint Ethics Regulations (JER). In addition, the Contractor shall not employ any person who is an employee of the Department of the AF if such employment would be contrary to the policies contained in Air Force Instruction (AFI) 64-106, Air Force Industrial Labor Relations Activities. The Contractor shall be prohibited from employing off-duty CORs who are providing surveillance on any contracts/sub-contracts awarded to the Contractor. All contract personnel, depending on particular condition, occasion, or place or job assignment shall be required to wear professional and suitable attire.
All Contractor personnel shall conduct themselves in a professional and courteous manner. The selection, assignment, reassignment, transfer, supervision, management, and control of Contractor personnel in performance of this PWS shall be the responsibility and prerogative of the Contractor; however, the Contractor shall comply with the requirements set forth in this PWS and Tinker AFB regulations concerning the conduct of employees as referenced herein. The Contractor shall employ and maintain a technically trained and experienced work force.
1.12. Environmental Protection & Safety: The Contractor shall be knowledgeable of and comply with all applicable federal, state, and local laws, regulations, instructions, and requirements regarding environmental protection and occupational safety and health. The Contractor shall comply with any laws, instructions, or regulation changes during the term of this contract. Contractors shall be compliant with the Tinker AFB Supplement to Air Force Instruction (AFI) 32-7086, “Hazardous Materials Management”, Tinker AFB procedures per Tinker AFB Instruction (TAFBI) 32-7004, “Hazardous Waste Management”, and Complex procedures per OC-ALC Sup to AFI 32-7086, “Hazardous Material Management” and OC- ALC Instruction (OC-ALCI) 32-101 “Air Quality Record Keeping Procedure”. Publications are available digitally on the e-Publishing website at www.e-publishing.af.mil for downloading or ordering.
1.12.1. Material Safety Data Sheet/Safety Data Sheet (MSDS/SDS): Upon the COR’s confirmed receipt of the Contractor’s written certification which states “No HAZMAT Usage”, the requirements of this section are no longer applicable. Said certification letter shall be printed on company letterhead and contain the applicable contract number for which the services are being performed.
1.12.1.1. The Contractor shall not transport, ship or use any chemical, material or substance used in the performance of this PWS on Tinker AFB before the written approval is provided by the 72 ABW/CEIE, Natural Infrastructure Management (Environmental Compliance). The Contractor shall submit to the COR, ten (10) calendar days after the contract award date, all MSDS or SDS and a completed OC-ALC Form 152, MSDS/SDS Information Sheet. The Contractor shall receive approval from the COR prior to shipping any chemical, material, or substance to Tinker AFB. A copy of the manufacturer MSDS/SDS shall accompany the shipment. The Contractor shall comply with the effective dates for SDS requirements IAW the Occupational Safety and Health Administration (OSHA) Hazardous Communication Standard, Title 29, Code of Federal Regulation (CFR) Part 1910.1200. The COR will forward all MSDS/SDS submittals to the 72 ABW/CEIE for approval. A current manufacturer MSDS/SDS shall be submitted to the COR if the Contractor changes manufacturer or vendor for any chemicals that were previously approved.
The Contractor shall maintain copies of the manufacturer MSDS/SDS for all chemicals. The MSDS/SDS shall be readily accessible at all times by Contractor personnel as well as Government employees.
1.12.2. Hazardous Material (HAZMAT): If HAZMAT shall not be brought on base or used in the performance of this contract; the Contractor shall provide certification, in writing and printed on company letterhead, which states “No HAZMAT will be brought on base” or “No HAZMAT Usage”. Said letter shall also contain the contract number for which the statement applies. This certification shall be provided to the COR within ten (10) business days after the contract award date. Upon the receipt of the certification by the COR, the requirements of this section are no longer applicable.
1.12.2.1. The Contractor shall not store chemicals or HAZMAT on Tinker AFB. Contractors shall be compliant with HAZMAT management procedures per the OC-ALC Supplement to AFI 32-7086, “Hazardous Materials Management”. The Contractor shall maintain a log of all http://www.e-publishing.af.mil/
HAZMAT that is used on base. This usage log shall be provided to the COR monthly, the last business day of each month, or when the required work is completed. The COR will forward the records to the Unit Environmental Coordinator (UEC) NLT the fourth (4th) calendar day of the following month or the first (1st) subsequent business day.
1.12.3. Hazardous Waste: If HAZWASTE shall not be generated during the performance of this contract, the Contractor shall provide written certification which states that there is “No Hazardous Waste Generation”. Said certification letter shall be printed on company letterhead and contain the applicable contract number. This certification shall be provided to the COR within ten (10) business days after award. Upon the COR’s confirmed receipt of the Contractor’s written certification which states “No Hazardous Waste Generation”, the requirements of this section are no longer applicable.
1.12.3.1. The Contractor shall dispose of HAZWASTE in Government furnished waste containers located in the shop or area where the work is being performed. The Contractor shall notify the COR if the required waste containers are not available on site.
1.12.4. Discharges: Any discharges into Tinker’s Industrial Waste Treatment Plant (IWTP) or sanitary sewer shall be approved and accomplished IAW the Tinker Industrial Waste Water Discharge Permit as instructed by the 72 ABW/CEIE, Natural Infrastructure Management (Environmental Compliance). The COR will submit the required notice of intent documentation to the UEC for the 72 ABW/CEIE approval. The Contractor shall maintain records of any written approval issued by the 72 ABW/CEIE for discharges into the IWTP and sanitary sewer.
1.12.5. Off-Site Discharges: For discharges outside of Tinker AFB, the Contractor shall ensure waste water discharges that may contain pollutants resulting from any contracted service go to a state or federal permitted treatment facility such as a municipal Publicly Owned Treatment Works (POTW). The Contractor shall provide a letter from the POTW to the COR within ten
(10) calendar days after the contract award date. The letter shall state the POTW is permitted for all pollutants that the Contractor may discharge during the contracted service.
1.12.6. Spills: Upon occurrence of any spill that could enter the storm system or cause any harmful environment effects, the Contractor shall immediately call 911 to report the incident.
When possible, the Contractor shall use a base telephone to receive help from Tinker AFB 911.
If using a cell phone, the Contractor shall request Tinker AFB 911. The Contractor shall immediately report all environmental violations to the COR and UEC. The Contractor shall provide five (5) copies of a typed or written report about the incident within four (4) clock hours as follows:
One (1) copy to CO, two (2) copies to the COR, one (1) copy for the UEC, and one (1) copy for the record. The format of the report shall be left up to the Contractor; however, the report shall contain the following information.
• name and contact number of the person reporting the spill
• date and time of incident
• location and source of spill
• substance or pollutant spilled
• amount spilled and rate of discharge
• any damages or injuries involved
• extent of area impacted
• potential hazards
• actions taken
• organizations contacted
• remarks section - that addresses the cause of the spill (e.g. human error, equipment, etc.)
and whether 911 was called and which agencies responded
1.13. Environmental Training: Upon the COR’s confirmed receipt of the Contractor’s written letter which certifies “No Hazardous Waste Generation”, the requirements of this section are no longer applicable. Said certification letter shall be printed on company letterhead and contain the applicable contract number for which the services are being performed.
1.13.1. Contractor personnel performing duties in the service of this PWS shall have training that acquaints the person with the details of Resource Conservation Recovery Act (RCRA) regulations in 40 CFR 260 through 279; applicable state laws and regulations; DoD, AF, and local requirements. This training can be obtained through creditable training institutions or companies. All training shall be approved by the 72 ABW/CEIE, Natural Infrastructure Management (Environmental Compliance). RCRA training is available at http://www.natlenvtrainers.com/RCRA-hazardous-waste.htm;
http://www.skillsoft.com/catalog/detail.asl?CourseCode=esh_sah_a34_sh_enus000000 and http://www.lion.com/Storing-Hazardous-Waste-for-LQGs. The training shall be at the Contractor’s expense. Prior to obtaining training and within ten (10) calendar days after the contract award date, the Contractor shall provide the name of the training institution or company and course description to the COR for approval. Once written approval is received from the COR, the Contractor shall provide the environmental training certificates for employees performing duties in the service of this PWS. The Contractor’s environmental training certificates shall be provided to the COR within thirty (30) calendar days. In addition to the required environmental training, Contractors shall be compliant with Tinker AFB procedures per Tinker AFBI 32-7004, “Hazardous Waste Management”.
1.14. Forms, Technical Orders (TO’s), AFI, AFMCI and Publications: The Contractor shall obtain the forms and publications expressly required to perform the work in this contract via the internet at www.e-publishing.af.mil. In the event a form or publication is not available online, the COR will provide the form, instruction, or publication to the Contractor upon the Contractor’s written request (e-mail is acceptable). In the event, laws, regulations, T.O.’s, AFI’s, or AFMCI’s change during the term of this contract, the Contractor shall be required to comply as the changes come into effect. Contractors delivering or handling official United States Air Force (USAF) records shall comply with the applicable records management regulations in AFI 33-322, Chapter 3, in its entirety.
http://www.natlenvtrainers.com/RCRA-hazardous-waste.htm http://www.skillsoft.com/catalog/detail.asl?CourseCode=esh_sah_a34_sh_enus000000 http://www.lion.com/Storing-Hazardous-Waste-for-LQGs http://www.e-publishing.af.mil/
1.15. Housekeeping: The Contractor shall keep the work areas clean and neat IAW Industry Standards, OSHA, Fire and Safety Standards and this PWS.
1.16. Foreign Object Damage (FOD) and Dropped Object Prevention (DOP): Contractor personnel who work in or travel though areas near operational and production aircraft, engines, munitions, missiles, drones, space systems, support equipment, Aerospace Ground Equipment (AGE), trainers, and the Contactor personnel operating vehicles and equipment on flight lines, runways, taxiways, parking ramps, and in aircraft hangers and maintenance areas are required to receive the FOD/DOP training and to comply with AFI 36-2232, AFMC Supp 1, paragraph 9.2., and A4.3.4. (Initial)/A4.3.5. (Refresher). The Contractor and Contractor personnel shall acknowledge the FOD/DOP training either by viewing the Digital Versatile Disc (DVD) provided by the COR or the You Tube site, http://www.youtube.com/watch?v=tYcbodjFPnM.
1.16.1. The Contractor shall provide a Contractor devised certificate to the COR for each employee within five (5) business days after the contract award date. The certificates shall have the title of the training, the name of the person who received the training, and the date of the training. The Contractor shall also ensure all new employees view the FOD/DOP training and provide a Contractor devised certificate of training to the COR prior to the employees starting work in the OC-ALC shops. On an annual basis, the Contractor and Contractor personnel shall be required to review the FOD/DOP training and to provide an updated Contractor devised certificate of training to the COR within five (5) business days of the new period of performance (PoP) start date.
1.17. Tool Control and Accountability: While performing contract services in or around Maintenance Production Shops, which includes ramp areas, the Contractor shall comply with AFI 21-101_AFMC Supp 1, 21-101, Chapter 10 (all paragraphs) and OC-ALCI 21-112, paragraph 14.1. and 14.5.3. The Contractor shall provide the completed MXRIWRS Form 032 prior to performing work in the OC-ALC industrial areas. The MXRIWRS Form 032 is available from the COR. The Contractor shall provide a Contractor Tool Listing, MXRIWRS Form 032, to the COR within five (5) business days after the relocation action. The Contractor or Contractor’s personnel shall inventory the container or bag of tools at the beginning of each work day and at the end of each work day. The Contractor personnel shall immediately notify the COR of any tools that are missing or lost from the work area or container (e.g. tool or job box or tool bag). The COR will report any missing Contractor’s tools which have not been located within one (1) hour after notification to the appropriate Government personnel. The Contractor shall obtain the Form 32 from the COR. The CM shall ensure each employee on the job site receives a briefing from the COR about Housekeeping, FOD/DOP, and Tool Control prior to starting work in OC-ALC Industrial Areas.
1.18. Privately Owned Motor Vehicles (POV): Contractor personnel shall comply with the directives pertaining to operation of POVs on Tinker AFB per AFMAN 31-116, in its entirety, “Motor Vehicle Traffic Supervision”. The Contractor shall comply with Tinker AFBI 24-301, in its entirety for the operation of POVs within Tinker AFB.
http://www.youtube.com/watch?v=tYcbodjFPnM
1.19. Visitors Pass: The Contractor shall contact the COR seven (7) business days before arriving on Tinker AFB in order to make arrangements for Visitors Passes. The COR will assign a sponsor for the Contractor from within the organization. The Contractor and the sponsor shall arrange to meet at Pass and Registration, Building 6611 at the Tinker Gate which is South of I-40 off of Air Depot. The Contractor shall provide two (2) forms of identification, one of which shall be a picture ID, to the 72 SFS. The 72 SFS will provide an AF Form 75, Visitors Pass, which will be valid for up to thirty (30) calendar days.
1.20. Foreign National(s): The Contractor shall notify the COR before sending a Foreign National representative to perform services. Special rules apply for foreign nationals visiting a US Government facility.
1.21. Health and Safety on Government Installations: While performing work under this contract on a Government installation, the Contractor shall comply with federal, state and local regulations, and AFI 91-203, “Air Force Consolidated Occupational Safety Instruction”, as established by this contract and Appendix C. The Contractor shall notify the CO, COR, and Government Contract Administrator (CA) within one (1) business day of any injuries that occur to Contractor personnel while they are on the installation. The Contractor shall notify the CO, COR, and Government Contract Administrator (CA) within one (1) business day of damage to Government property or equipment during the execution of the contract.
1.22. Emergency Procedures: The Contractor personnel shall follow the direction of the Government personnel with regard to emergency procedures, such as fire, tornado, active shooter, bomb threats, or other emergency. It is the responsibility of the Contractor to provide guidance and to establish procedures for its employees to respond to an emergency. It is the Contractor’s responsibility to account for their employees following an emergency evacuation.
The Contractor personnel shall participate with the Government personnel in all fire and tornado drills at no additional cost to the Government.
1.23. Contractor Manpower Reporting (CMR): The Contractor shall report ALL Contractor labor hours, to include sub-Contractor labor hours, required for the performance of the services provided under this contract via a secure data collection site. The Contractor is required to completely fill in all required data fields at the website http://www.ecmra.mil.
1.23.1. The Contractor shall report all labor hours executed during the Period of Performance (PoP) for each Government Fiscal Year (FY) which runs from 1 October through 30 September the following year. Although the labor hours executed may be completed any time during the FY, all data shall be completed no later than (NLT) 31 October of each calendar year.
Contractors may direct questions to the CMR help desk email listed at http://www.ecmra.mil.
1.24. Training – General: The Government COR will provide training via slides, video, or classroom prior to the Contractor performing work at the OC-ALC. The Government will be responsible for all approved costs associated with the training identified below. The COR will document training on and maintain copies of the completed AF IMT 1151, Training Attendance and Rating, as part of the contract surveillance file. For purposes of identification and http://www.ecmra.mil/ http://www.ecmra.mil/ compliance with Personally Identifiable Information (PII) requirements, only the last four (4) of the Contractor employee’s Social Security Number (SSN) will be input on the form.
1.24.1. The Contractor shall contact the COR prior to work being performed in order to accomplish the required training or to verify the required training as listed below has been completed:
Lockout/Tagout Initial and Refresher Course for Affected Personnel, CBT
CTEMAS0003001CB
2. SERVICE SUMMARY.
The Contractor shall be aware that in the absence of any contract requirement from the Service Summary does not detract from its enforceability nor limit the rights of remedies of the Government under any other provision of the contract. The Contractor shall ensure the following service summary requirements are accomplished.
Service Summary (SS) Table 2-1
SS PERFORMANCE OBJECTIVE PWS
PARA.
PERFORMANC
E THRESHOLD
SS 1
The Contractor shall remove, load, transport and reinstall the Autoclave and accessory equipment from Bldg. 2211 to Bldg. 9001 between the days of, 1 July - 30 Oct 2015. The Contractor shall provide a crane and lifting devices with capacity to lift 20,000 - 30,000 pounds and raise the Autoclave from the floor to a flatbed trailer. The Contracting Officer Representative (COR) will notify the Contractor, fifteen (15) work days in advance of the move.
1.1. 100% Compliance
SS 2
Contractor shall perform an operational check and inspection of the Autoclave and its accessories prior to disconnection/relocation to acquire an operational baseline and determine overall condition of the Autoclave and accessory equipment prior to relocation. The Contractor shall provide a copy of the operational check and inspection to the Government Technical point of contact (POC) prior to disassembly/relocation of the Autoclave.
1.1.1. 100% Compliance
SS 3
The Autoclave shall be set up and bolted to the floor IAW Appendix D. Contractor shall provide all sundry items for this relocation effort. The Contractor shall connect all accessory
1.1.2. 100% Compliance
SS PERFORMANCE OBJECTIVE PWS
PARA.
PERFORMANC
E THRESHOLD
equipment/interconnections associated wiring and piping: to include power panel, vacuum system, vacuum station, control panel, cooling plumbing, and ventilation. Contractor shall connect control wiring (analog signals and digital signals) from the Autoclave control panel to the data acquisition and control systems.
SS 4
The Contractor shall perform an operational check and inspection of the Autoclave and its accessories to ensure the condition and function of the Autoclave is the same as it was prior to relocation.
The Contractor shall provide a copy of the operational check and inspection after the relocation/assembly and demonstrate to Government personnel that the Autoclave is fully operational upon completion.
1.1.3. 100% Compliance
SS 5
Immediately upon completion of the maintenance support services and before leaving the OC-ALC, the Contractor shall provide a written Service Report to the Government identified Technical POC or COR. The Government identified Technical POC will forward the service report to the COR within two (2) business days of receipt.
The Contractor shall provide, by fax or email, the final service report within five (5) business days to the COR.
1.2. 100% Compliance
SS 6
The Contractor shall provide a written response within two (2) business days which addresses the root cause, corrective action and preventive action(s) in relation to the submitted CAR or Customer Complaint.
1.4. 100% Compliance
SS 7
The Contractor shall notify the Government Technical POC upon completion of each action IAW OC-ALC OI 21-203, Chapter 1, 2 and 3, as applicable.
1.5. 100% Compliance
SS 8
The Contractor shall be a subject matter expert (SME) in relocating, setting up, operation and troubleshooting of Autoclaves. The Contractor shall provide a resume listing a minimum of three
(3) similar installation or relocation efforts performed with Autoclaves at receipt of proposal.
1.8. 100% Compliance
SS 9 The Contractor shall provide the name of the Contract Manager (CM) and any alternates who 1.9. 100%
Compliance
PERFORMANC
E THRESHOLD
shall act for the Contractor when the CM is absent.
They shall be designated to the CO and COR, in writing, within five (5) business days after the contract award date.
SS 10
The Contractor shall provide an initial listing of the Contractor employees’ names and position titles to the COR within five (5) business days after the contract award date. Within five (5) business days, the Contractor shall also provide an updated listing of personnel to the COR when employees affecting the work of this contract change status or position.
1.11.
100% Compliance
SS 11
The Contractor shall submit to the COR, ten (10) calendar days after the contract award date, all MSDS or SDS and a completed OC-ALC Form 152, MSDS/SDS Information Sheet.
1.12.1.
100% Compliance
SS 12
This certification shall be provided to the COR within ten (10) business days after the contract award date.
1.12.2.
100% Compliance
SS 13
The Contractor shall maintain a log of all HAZMAT that is used on base. This usage log shall be provided to the COR monthly, the last business day of each month, or when the required work is completed.
1.12.2.1.
100% Compliance
SS 14 This certification shall be provided to the COR within ten (10) business days after award. 1.12.3. 100%
Compliance
SS 15
Contractor shall immediately call 911 to report the incident. When possible, the Contractor shall use a base telephone to receive help from Tinker AFB
911. If using a cell phone, the Contractor shall request Tinker AFB 911. The Contractor shall immediately report all environmental violations to the COR and UEC. The Contractor shall provide five (5) copies of a typed or written report about the incident within four (4) clock hours.
1.12.6.
100% Compliance
SS 16
Prior to obtaining training and within ten (10) calendar days after the contract award date, the Contractor shall provide the name of the training institution or company and course description to the COR for approval. Once written approval is received from the COR, the Contractor shall provide the environmental training certificates for employees performing duties in the service of this PWS. The Contractor’s environmental training
1.13.1.
100% Compliance
PERFORMANC
E THRESHOLD
certificates shall be provided to the COR within thirty (30) calendar days. In addition to the required environmental training, Contractors shall be compliant with Tinker AFB procedures per Tinker AFBI 32-7004, “Hazardous Waste Management”.
SS 17
The Contractor shall provide a Contractor devised certificate to the COR for each employee within five (5) business days after the contract award date.
The certificates shall have the title of the training, the name of the person who received the training, and the date of the training. The Contractor shall also ensure all new employees view the FOD/DOP training and provide a Contractor devised certificate of training to the COR prior to the employees starting work in the OC-ALC shops. On an annual basis, the Contractor and Contractor personnel shall be required to review the FOD/DOP training and to provide an updated Contractor devised certificate of training to the COR within five (5) business days of the new period of performance (PoP) start date.
1.16.1.
100% Compliance
SS 18
The Contractor shall provide the completed MXRIWRS Form 032 prior to performing work in the OC-ALC industrial areas. The MXRIWRS Form 032 is available from the COR. The Contractor shall provide a Contractor Tool Listing, MXRIWRS Form 032, to the COR within five (5) business days after the relocation action. The Contractor or Contractor’s personnel shall inventory the container or bag of tools at the beginning of each work day and at the end of each work day. The Contractor personnel shall immediately notify the COR of any tools that are missing or lost from the work area or container (e.g. tool or job box or tool bag). The COR will report any missing Contractor’s tools which have not been located within one (1) hour after notification to the appropriate Government personnel. The Contractor shall obtain the Form 32 from the COR. The CM shall ensure each
1.17.
100% Compliance
PERFORMANC
E THRESHOLD
employee on the job site receives a briefing from the COR about Housekeeping, FOD/DOP, and Tool Control prior to starting work in OC-ALC Industrial Areas.
SS 19
The Contractor shall contact the COR seven (7) business days before arriving on Tinker AFB in order to make arrangements for Visitors Passes.
1.20.
100% Compliance
3. GOVERNMENT FURNISHED PROPERTY AND SERVICES.
3.1. Government Furnished Property (GFP). On-Base Repair. GFP is not applicable to this contract in accordance with FAR Parts 45 and 52.245 plus supplements.
3.2. Shared Property of the Government. Not Applicable.
3.3. Government Furnished Services (GFS). Government Furnished Services are applicable to the performance of this contract.
3.3.1. Security Forces. The Government will provide general on-base security forces' service.
The security forces’ telephone numbers are 911 for emergencies, 734-2000 for crime in progress, and 734-3737 for non-emergency calls.
3.3.2. Fire Emergency and Routine Services. The Government will provide general on-base fire protection services. The Contractor shall comply with fire prevention rules and regulations enforced by the TAFB Fire Prevention Branch. Call 911 for emergencies. For routine fire prevention matters call 734-3981. For routine calls to dispatch call 734-7964.
3.3.3. Utilities. The Government will provide utility services. These utilities include natural gas, electricity, water, and sewer for the sole purpose of accomplishing this contract. If the contractor requires additional utility services, it shall be the contractor’s responsibility to provide.
Contractor shall use due care and diligence in efforts to conserve utilities to reduce utility costs.
3.4. Intangible Government Property. Not Applicable.
3.5. Contractor Acquired Property (CAP). On-Base Repair.
3.5.1. Reimbursement. The Government will reimburse the Contractor for CAP at a direct cost IAW the contract terms and conditions which includes this PWS and the Contracting Officer’s approval.
3.5.2. Title to Government Property (CAP). This PWS incorporates FAR 52.245-1(e) (2)-(3)(ii) by reference.
| PERFORMANCE WORK STATEMENT (PWS) |
| PREPARED BY: |
| OC-ALC/OBWK |
| 3. GOVERNMENT FURNISHED PROPERTY AND SERVICES. |
| 3.1. Government Furnished Property (GFP). On-Base Repair. GFP is not applicable to this contract in accordance with FAR Parts 45 and 52.245 plus supplements. |