Solicitation FA6703-15-R-0002
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment_1_SF30.pdf | ||
| photo_1.jpg | JPG image | |
| photo_2.jpg | JPG image | |
| Question_and_Answers.pdf | ||
| SignInRoster.pdf | ||
| Site_Visit_Instructions.pdf | ||
| Attachment_3_Submittal_Register.pdf | ||
| Attachment_5_DARB_5.pdf | ||
| Attachment_2_ETL _Change_1 _Standard_Airfield.pdf | ||
| Attachment_1_FGWB_14-0001_Specs.pdf | ||
| Attachment_7_Financial.pdf | ||
| Attachment_6_Wage_Determination.pdf | ||
| Attachment_4_DARB_4.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rubber Removal and Maintain Markings Indefinite Delivery Indefinite Quantity (iDIQ) Dobbins ARB This solicitation is a 100% Small Business Set-Aside Applicable North American Industry Classif ication Code is 237310. Size Standard is $36.5M All Offerors must be registered in the System for Aw ard Management (SAM) in order to receive aw ard. Offerors can register via the internet at w w w .sam.gov Section K and L w ill be physically removed from the resultant aw ard but w ill be deemed incorporated by reference in that aw ard.
This is an Indefinite Quantity Indefinite Delivery contract for rubber removal and maintain markings on Dobbins ARB, GA. Effective for a 12 month base period from date of aw ard plus four (4) tw elve month Government option periods..
Delivery or performance time for specif ic projects w ill be specif ied in each individual task order and w ill Notice to Offeror: Funds are not presently available for this project. No aw ard w ill be made until funds are available to make payments under a contract. The Government reserves the right to cancel this solicitation, either before or after bid opening/RFP closing, w itih no obligation to the offeror by the Government.
Contractor Off icer information: Thomas MIlloy, Telephone 678-655-5783, thomas.milloy@us.af.mil
KENNETH J. JACOB 678-655-5745
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
20-Apr-2015
(RFP)
(IFB)
X
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
X
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________365 calendar days after receiving aw ard, notice to proceed. This performance period is mandatory, X negotiable. (See _________________________52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________3 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________21 May 2015 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
94 CONF/LGC (JACOB)
1538 ATLANTIC AVENUE
DOBBINS ARB GA 30069-4917
FA6703
PAGE OF PAGES
1 OF
CODE FA6703
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour) Sealed envelopes containing offers
94 CONF/LGC (JACOB)
1538 ATLANTIC AVENUE
DOBBINS ARB GA 30069-4917
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
678-655-5612FAX:TEL: 678-655-5745 TEL: 678-655-4987 FAX: 678-655-5612
FA6703-15-R-0002 147
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
FA6703-15-R-0002
Section B - Supplies or Services and Prices
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 170,000 Square
Foot
RUBBER REMOVAL - R/W
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to remove rubber on the runway in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour operation.
FOB: Destination
NET AMT
0002 30,000 Square
RUBBER REMOVAL - VEDA ALS
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to remove rubber, VEDA ALS, in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
0003 18,750 Square
Maintain Mairkings
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT RUNWAY CENTER LINE 3' WIDE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour operation.CLEAN, LAYOUT, AND PAINT RUNWAY CENTER LINE 3' WIDE
0004 56,400 Square
Maintain Markings
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT RUNWAY EDGE LINE 3' WIDE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour operation.
0005 1,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT CMA LINES (4.5
FT WIDE: 6" BLACK- 6" YELLOW- 6" BLACK- 6" YELLOW -6" BLACK -6"
YELLOW - 6" BLACK-6" YELLOW - 6" BLACK) in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
0006 100 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT VEDA ALS MARKINGS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
0007 50,000 Square
Maintain Markngs
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary for MOLD REMOVAL AND SPECIALIZED SURFACE PREP in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour operation.
0008 14,400 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT THRESHOLD in accordance with the attached specification and drawings for Project FGWB 14- 0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour operation.
0009 2 Each Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT NUMBERS (#29 AND #11) in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway
0010 3 Each Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT GROUND RECEIVER CHECKPOINTS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour operation.
0011 1,500 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT VFR HOLD LINES
(4.5 FT WIDE: 6" BLACK- 6" YELLOW- 6" BLACK- 6" YELLOW -6" BLACK
-6" YELLOW - 6" BLACK-6" YELLOW - 6" BLACK) in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
0012 60,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT TAXIWAY LINES
(CENTERLINE: 1.5 FT WIDE: 6" BLACK- 6" YELLOW- 6"
BLACK)(EDGELINE: 2.5 FT WIDE: 6" BLACK- 6" YELLOW- 6" BLACK- 6"
YELLOW -6" BLACK) in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
0013 1,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary for PAINT REMOVAL - 100% in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
0014 100,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary for PAINT REMOVAL - 80% in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
0015 2 Each Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT INSTRUMENT LINE SIGNAGE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
0016 1,500 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT INSTRUMENT LINE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway
0017 18,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT FIXED DISTANCE MARKERS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled
0018 1 Each Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT HELIPAD in accordance with the attached specification and drawings for Project FGWB 14- 0001. The performance will normally be scheduled during a runway closure period
0019 16,200 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT TOUCHDOWN ZONE MARKINGS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
0020 1 Each Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT STOP CONTACT TOWER MARKINGS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
0021 300 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT FOD CHECKPOINT LINE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
0022 2 Each Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND 'PAINT CHECK FOR FOD' in accordance with the attached specification and drawings for Project FGWB 14- 0001. The performance will normally be scheduled during a runway closure period
0023 2 Each Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT INS CHECKPOINTS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
0024 2,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT 6" EQUIPMENT SET-BACK LINES in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
0025 4,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT 6" RESTRICTED AREA LINE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway
0026 100 Each Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT RESTRICTED AREA SIGNAGE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
0027 1 Each Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT LG CLOSED PAVEMENT MARKING in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled
0028 1 Each Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT SM CLOSED PAVEMENT MARKING in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled
0029 1 Each Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT ENTRY CONTROL POINTS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway
0030 9,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT CHEVRONS in accordance with the attached specification and drawings for Project FGWB 14- 0001. The performance will normally be scheduled during a runway closure period
0031 1 Each Mobilize
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary for Mobilizaion in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
0032 1 Each DeMobilize
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary for DeMobilizaion in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
1001 170,000 Square
OPTION RUBBER REMOVAL - R/W
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to remove rubber on the runway in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
1002 30,000 Square
OPTION RUBBER REMOVAL - VEDA ALS
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to remove rubber, VEDA ALS, in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
1003 18,750 Square
OPTION Maintain Mairkings
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT RUNWAY CENTER LINE 3' WIDE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour operation.CLEAN, 1004 56,400 Square
OPTION Maintain Markings
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT RUNWAY EDGE LINE 3' WIDE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
1005 1,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT CMA LINES (4.5
FT WIDE: 6" BLACK- 6" YELLOW- 6" BLACK- 6" YELLOW -6" BLACK -6"
YELLOW - 6" BLACK-6" YELLOW - 6" BLACK) in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
1006 100 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT VEDA ALS MARKINGS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
1007 50,000 Square
OPTION Maintain Markngs
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary for MOLD REMOVAL AND SPECIALIZED SURFACE PREP in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway
1008 14,400 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT THRESHOLD in accordance with the attached specification and drawings for Project FGWB 14- 0001. The performance will normally be scheduled during a runway closure period
1009 2 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT NUMBERS (#29 AND #11) in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway
1010 3 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT GROUND RECEIVER CHECKPOINTS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled
1011 1,500 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT VFR HOLD LINES
(4.5 FT WIDE: 6" BLACK- 6" YELLOW- 6" BLACK- 6" YELLOW -6" BLACK
-6" YELLOW - 6" BLACK-6" YELLOW - 6" BLACK) in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
1012 60,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT TAXIWAY LINES
(CENTERLINE: 1.5 FT WIDE: 6" BLACK- 6" YELLOW- 6"
BLACK)(EDGELINE: 2.5 FT WIDE: 6" BLACK- 6" YELLOW- 6" BLACK- 6"
YELLOW -6" BLACK) in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
1013 1,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary for PAINT REMOVAL - 100% in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
1014 100,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary for PAINT REMOVAL - 80% in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
1015 2 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT INSTRUMENT LINE SIGNAGE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
1016 1,500 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT INSTRUMENT LINE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway
1017 18,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT FIXED DISTANCE MARKERS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled
1018 1 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT HELIPAD in accordance with the attached specification and drawings for Project FGWB 14- 0001. The performance will normally be scheduled during a runway closure period
1019 16,200 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT TOUCHDOWN ZONE MARKINGS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
1020 1 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT STOP CONTACT TOWER MARKINGS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
1021 300 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT FOD CHECKPOINT LINE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
1022 2 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND 'PAINT CHECK FOR FOD' in accordance with the attached specification and drawings for Project FGWB 14- 0001. The performance will normally be scheduled during a runway closure period
1023 2 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT INS CHECKPOINTS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
1024 2,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT 6" EQUIPMENT SET-BACK LINES in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
1025 4,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT 6" RESTRICTED AREA LINE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway
1026 100 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT RESTRICTED AREA SIGNAGE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
1027 1 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT LG CLOSED PAVEMENT MARKING in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled
1028 1 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT SM CLOSED PAVEMENT MARKING in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled
1029 1 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT ENTRY CONTROL POINTS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway
1030 9,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT CHEVRONS in accordance with the attached specification and drawings for Project FGWB 14- 0001. The performance will normally be scheduled during a runway closure period
1031 1 Each OPTION Mobilize
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary for Mobilizaion in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
1032 1 Each OPTION DeMobilize
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary for DeMobilizaion in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
2001 170,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to remove rubber on the runway in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
2002 30,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to remove rubber, VEDA ALS, in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
2003 18,750 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT RUNWAY CENTER LINE 3' WIDE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour operation.CLEAN, 2004 56,400 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT RUNWAY EDGE LINE 3' WIDE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
2005 1,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT CMA LINES (4.5
FT WIDE: 6" BLACK- 6" YELLOW- 6" BLACK- 6" YELLOW -6" BLACK -6"
YELLOW - 6" BLACK-6" YELLOW - 6" BLACK) in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
2006 100 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT VEDA ALS MARKINGS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
2007 50,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary for MOLD REMOVAL AND SPECIALIZED SURFACE PREP in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway
2008 14,400 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT THRESHOLD in accordance with the attached specification and drawings for Project FGWB 14- 0001. The performance will normally be scheduled during a runway closure period
2009 2 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT NUMBERS (#29 AND #11) in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway
2010 3 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT GROUND RECEIVER CHECKPOINTS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled
2011 1,500 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT VFR HOLD LINES
(4.5 FT WIDE: 6" BLACK- 6" YELLOW- 6" BLACK- 6" YELLOW -6" BLACK
-6" YELLOW - 6" BLACK-6" YELLOW - 6" BLACK) in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
2012 60,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT TAXIWAY LINES
(CENTERLINE: 1.5 FT WIDE: 6" BLACK- 6" YELLOW- 6"
BLACK)(EDGELINE: 2.5 FT WIDE: 6" BLACK- 6" YELLOW- 6" BLACK- 6"
YELLOW -6" BLACK) in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
2013 1,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary for PAINT REMOVAL - 100% in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
2014 100,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary for PAINT REMOVAL - 80% in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
2015 2 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT INSTRUMENT LINE SIGNAGE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
2016 1,500 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT INSTRUMENT LINE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway
2017 18,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT FIXED DISTANCE MARKERS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled
2018 1 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT HELIPAD in accordance with the attached specification and drawings for Project FGWB 14- 0001. The performance will normally be scheduled during a runway closure period
2019 16,200 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT TOUCHDOWN ZONE MARKINGS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
2020 1 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT STOP CONTACT TOWER MARKINGS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
2021 300 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT FOD CHECKPOINT LINE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
2022 2 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND 'PAINT CHECK FOR FOD' in accordance with the attached specification and drawings for Project FGWB 14- 0001. The performance will normally be scheduled during a runway closure period
2023 2 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT INS CHECKPOINTS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
2024 2,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT 6" EQUIPMENT SET-BACK LINES in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
2025 4,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT 6" RESTRICTED AREA LINE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway
2026 100 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT RESTRICTED AREA SIGNAGE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
2027 1 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT LG CLOSED PAVEMENT MARKING in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled
2028 1 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT SM CLOSED PAVEMENT MARKING in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled
2029 1 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT ENTRY CONTROL POINTS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway
2030 9,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT CHEVRONS in accordance with the attached specification and drawings for Project FGWB 14- 0001. The performance will normally be scheduled during a runway closure period
2031 1 Each OPTION Mobilize
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary for Mobilizaion in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
2032 1 Each OPTION DeMobilize
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary for DeMobilizaion in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
3001 170,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to remove rubber on the runway in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
3002 30,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to remove rubber, VEDA ALS, in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
3003 18,750 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT RUNWAY CENTER LINE 3' WIDE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour operation.CLEAN, 3004 56,400 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT RUNWAY EDGE LINE 3' WIDE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
3005 1,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT CMA LINES (4.5
FT WIDE: 6" BLACK- 6" YELLOW- 6" BLACK- 6" YELLOW -6" BLACK -6"
YELLOW - 6" BLACK-6" YELLOW - 6" BLACK) in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
3006 100 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT VEDA ALS MARKINGS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
3007 50,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary for MOLD REMOVAL AND SPECIALIZED SURFACE PREP in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway
3008 14,400 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT THRESHOLD in accordance with the attached specification and drawings for Project FGWB 14- 0001. The performance will normally be scheduled during a runway closure period
3009 2 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT NUMBERS (#29 AND #11) in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway
3010 3 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT GROUND RECEIVER CHECKPOINTS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled
3011 1,500 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT VFR HOLD LINES
(4.5 FT WIDE: 6" BLACK- 6" YELLOW- 6" BLACK- 6" YELLOW -6" BLACK
-6" YELLOW - 6" BLACK-6" YELLOW - 6" BLACK) in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
3012 60,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT TAXIWAY LINES
(CENTERLINE: 1.5 FT WIDE: 6" BLACK- 6" YELLOW- 6"
BLACK)(EDGELINE: 2.5 FT WIDE: 6" BLACK- 6" YELLOW- 6" BLACK- 6"
YELLOW -6" BLACK) in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
3013 1,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary for PAINT REMOVAL - 100% in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
3014 100,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary for PAINT REMOVAL - 80% in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
3015 2 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT INSTRUMENT LINE SIGNAGE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
3016 1,500 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT INSTRUMENT LINE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway
3017 18,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT FIXED DISTANCE MARKERS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled
3018 1 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT HELIPAD in accordance with the attached specification and drawings for Project FGWB 14- 0001. The performance will normally be scheduled during a runway closure period
3019 16,200 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT TOUCHDOWN ZONE MARKINGS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
3020 1 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT STOP CONTACT TOWER MARKINGS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
3021 300 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT FOD CHECKPOINT LINE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
3022 2 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND 'PAINT CHECK FOR FOD' in accordance with the attached specification and drawings for Project FGWB 14- 0001. The performance will normally be scheduled during a runway closure period
3023 2 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT INS CHECKPOINTS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
3024 2,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT 6" EQUIPMENT SET-BACK LINES in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
3025 4,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT 6" RESTRICTED AREA LINE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway
3026 100 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT RESTRICTED AREA SIGNAGE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a
3027 1 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT LG CLOSED PAVEMENT MARKING in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled
3028 1 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT SM CLOSED PAVEMENT MARKING in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled
3029 1 Each OPTION Maintain Markings
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT ENTRY CONTROL POINTS in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway
3030 9,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT CHEVRONS in accordance with the attached specification and drawings for Project FGWB 14- 0001. The performance will normally be scheduled during a runway closure period
3031 1 Each OPTION Mobilize
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary for Mobilizaion in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
3032 1 Each OPTION DeMobilize
FFP
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary for DeMobilizaion in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
4001 170,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to remove rubber on the runway in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
4002 30,000 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to remove rubber, VEDA ALS, in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour
4003 18,750 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND PAINT RUNWAY CENTER LINE 3' WIDE in accordance with the attached specification and drawings for Project FGWB 14-0001. The performance will normally be scheduled during a runway closure period and allow for 24 hour operation.CLEAN, 4004 56,400 Square
Contractor to provide all labor, materials, equipment, supervision, and transportation necessary to CLEAN, LAYOUT, AND…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .