1643_-_DDPM_150001_-_SOW_-_Concrete_Fire_Lane_-_REV_1.pdf
PDF 200 KB Posted
- Attached to
- CONSTRUCT CONCRETE SLABS Federal contract opportunity
- Solicitation number
- FA6675-16-R-0001
About this file
1643 - DDPM 150001 - SOW - Concrete Fire Lane - REV 1
View the file
Other files for this federal contract opportunity
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page | 1
NAVAL AIR STATION FORT WORTH,
JOINT RESERVE BASE
March 3, 2016
Revision #: 1 Revision Date: 3 May 2016
STATEMENT OF WORK For:
CONSTRUCT CONCRETE SLABS FOR FIRE LANES AT BUILDING 1643
PROJECT # DDPM 15 0001
OVERVIEW:
Building 1643 does not currently have a fire lane surrounding the building for emergency vehicle access. Approximately 16,600 square feet (SF) of area located on the east and north sides of the building, in two separate zones, will need to be demolished/prepped and replaced with concrete. These concrete slabs will create an adequate fire lane for emergency access and also eliminate the Foreign Object Damage (FOD) hazard that currently exists.
SCOPE OF WORK:
All approvals and coordination for this scope of work shall be handled by the Contracting Officer (CO). The Contractor is to provide all equipment, material, and labor to perform the following scope of work to include the construction of a 306 cubic yard (CY) concrete pad at Zone 1, a 95 CY concrete pad at Zone 2, and the installation of 96 linear feet (LF) of 6” curbing on the east end of Zone 1 at B1643:
1. Building 1643 Main Pavement (Zone 1)
1.1 Demolish and remove 8,980 SF of existing 4” asphalt, 3,328 SF of vegetation and a 16” diameter tree in the area in the area designated for the new 8” concrete fire lane (See attached Zone 1 DEMO Plan drawing for exact breakdown of the area to be excavated).
1.2 The Contractor shall remove and discard the existing power pole guy wire that currently interferes with the path of the concrete fire lane. The Contractor shall install a new 25 foot high wood power pole approximately 15 feet further out from the existing guy wire near B1644 and the adjacent electrical transformer.
Install a new guy wire that runs from the existing wood power pole to the top of the newly installed 25’ power pole. Contractor shall verify the location of all underground utilities with the Government before any demolition or installation operations and ensure no utilities are damaged or altered.
Building 1643 – Construct Concrete Slabs for Fire Lane
Page | 2
1.3 Excavate 12,308 SF of existing grade land to a depth of 2 feet. Load & Haul 912 Loose Cubic Yards (LCY) of soil/vegetation/asphalt debris mixture from the B1643 storage yard to an approved dump site/landfill located 10 miles from NAS JRB Fort Worth, TX.
1.4 Load & Haul IN from an off base location 304 embankment cubic yards (ECY) of common fill soil consisting of a sandy clay to clayey sand material with a liquid limit (LL) of less than 35 percent and a plasticity index (PI) between 6 and 20. The soil shall be properly compacted (with roller) at a minimum 95% maximum standard Proctor dry density (ASTM D 698), in the range of -2 to +2 points of optimum moisture to support the concrete fire lane slabs. This common fill pavement subgrade soil layer shall measure 8” in thickness.
1.5 Load & Haul IN from an off base location 304 ECY of select fill soil. The soil shall be properly compacted (with roller) at a minimum 95% maximum standard Proctor dry density (ASTM D 698), in the range of 2% and 5% above optimum moisture to support the concrete fire lane slabs. This select fill pavement subgrade soil layer shall measure 8” in thickness.
1.6 Backfill and compact common/select fill into 8” layers with a 130 HP dozer
(crawler).
1.7 Construct concrete forms in a pattern that matches the attached Zone 1 Install
Plan for B1643. Note: Prefer that most concrete slabs match the existing 15’ x 15’ slabs that surround Hanger 1643. However, some of the existing concrete slabs vary from 10’ to 20’ near Area 1 and 12’ to 21’ near Areas 9, 10 and 11.
1.8 Install No. 5 Rebar @ 12” centers throughout the 12,308 SF areas to be poured. Position the rebar in the lower third of the concrete slab.
1.9 Construct proper joints with all existing pavement and structures using 24” No.
6 smooth dowels with ¾” redwood expansion joint material (EJM) and backer rods. The Contractor shall then install a pourable polyurethane sealant or Government approved joint alternative over the redwood EJM. Joint sealing compound shall be installed per manufacturer’s specifications. The Contractor shall position the No. 6 smooth dowels @ 18” centers. The Contractor shall field verify existing conditions. Saw cut concrete in areas deemed necessary to avoid cracking.
1.10 Pour 306 CY of 4,000 psi concrete throughout the 12,308 SF areas to a thickness of 8”. Apply curing agent and sealant to concrete.
1.11 Construct approximately 96 LF of 6” curbing to separate the concrete fire lane from the existing vegetation. Cut slots in the curbing to allow for proper drainage (See attached drawing of Zone 1 Install Plan).
1.12 Apply a broom finish to top surface of the concrete slabs.
1.13 Grade surfaces at a minimum of 2% slope to properly drain storm water away from Hanger 1643 and towards the east drainage ditch or north concrete swell
Page | 3 to prevent pooling on pavement surfaces (See attached drawing of Zone 1 Install Plan for additional detail).
1.14 The single sewer manhole cover located in Area 3 shall be raised to finished grade.
1.15. The communications hand hole located in Area 9 shall be raised to finished grade. Construct 6” wide concrete curbing around the 4’ x 6’ communication hand hole. The curbing height shall be 2” in height.
2. Building 1643 North Access (Zone 2)
2.1 Demolish and remove 426 SY of existing 4” asphalt and 25 SF of existing 12”
– 36” thick reinforced concrete surrounding the abandoned concrete vault (Ref.
Zone 2 drawing).
2.2 Excavate 3830 SF area to a depth of 2 feet. Load & Haul 284 Loose Cubic
Yards (LCY) of soil/vegetation/asphalt debris mixture from the B1643/B1650 project site to an approved dump site/landfill located 10 miles from NAS JRB Fort Worth, TX
2.3 Load & Haul IN from an off base location 95 ECY of common fill soil consisting of a sandy clay to clayey sand material with a liquid limit (LL) of less than 35 percent and a plasticity index (PI) between 6 and 20. The soil shall be properly compacted (with roller) at a minimum 95% maximum standard Proctor dry density (ASTM D 698), in the range of -2 to +2 points of optimum moisture to support the concrete mobility storage pad. This common fill pavement
2.4 Load & Haul IN from an off base location 95 ECY of select fill soil. The soil shall be properly compacted (with roller) at a minimum 95% maximum standard Proctor dry density (ASTM D 698), in the range of 2% and 5% above optimum moisture to support the concrete access road. This select fill pavement
2.5 Backfill and compact common/select fill into 8” layers with a 130 HP dozer
(crawler).
2.6 Construct concrete forms in a pattern that matches the attached drawing of
Zone 2 for the access road. Note: Prefer that center vertical joint be placed in the center of the 37’ wide Zone 2 and all other concrete joints be placed in 15’ foot sections.
2.7 Install No. 5 Rebar @ 12” centers throughout the 3,830 Square Foot (SF) area to be poured. Position the rebar in the lower third of the concrete slab.
2.8 Construct proper joints with all existing pavement and structures using 24” No.
6 smooth dowels with ¾” redwood expansion joint material (EJM) and backer rods. The Contractor shall then install a pourable polyurethane sealant or Government approved joint alternative over the redwood EJM. Joint sealing compound shall be installed per manufacturer’s specifications. The Contractor
Page | 4 shall position the No. 6 smooth dowels @ 18” centers. The Contractor shall field verify existing conditions. Saw cut concrete in areas deemed necessary to avoid cracking.
2.9 Pour 95 CY of 4,000 psi concrete throughout the 3,830 SF areas to a thickness of 8”. Apply curing agent and sealant to concrete.
2.10 Apply a broom finish to top surface of the concrete slabs.
2.11 Grade surfaces at a minimum of 2% slope to properly drain storm water away from Hanger 1643 & Building 1650 and towards to concrete swell to prevent pooling on pavement surfaces (See attached drawing of Zone 2 for additional detail).
2.12 The single 40” sewer manhole cover shall be raised to finished grade.
2.13 Both 8” natural gas valve access covers shall be raised to finished grade.
2.14 The existing 5’ x 7’ concrete slab surrounding the 40” electric manhole shall remain in place.
2.15 The existing 7’ x 13’ concrete slab surrounding the 40” communications manhole shall remain in place.
Note: The 301st Maintenance Group (Users) shall remove all equipment and storage containers located in the areas scheduled for new concrete.
PART I - GENERAL
REFERENCE PUBLICATIONS:
1.1. US GOVERNMENT/US AIR FORCE PUBLICATIONS: US Government/US Air Force publications can be found via internet at http://www.e-publishing.af.mil/.
Some suggested publications would include:
1.1.1. 29 CFR (PART 1910), Occupational Safety and Health Standards
1.1.2. 29 CFR (PART 1926), Safety and Health Regulations for Construction
1.1.3. AFI 91-203, Air Force Consolidated Occupational Safety Instructions, 15 Jun
1.2. NATIONAL INSTITUTE OF BUILDING SCIENCES (NIBS): The NIBS operates a website called the Whole Building Design Guide (WBDG) and it can be found via internet at http://www.wbdg.org/. Some suggested Unified Facilities Criteria’s (UFCs) would include:
1.2.1. UFC 3-201-01, Civil Engineering, 1 June 2013
http://www.e-publishing.af.mil/ http://www.wbdg.org/
Page | 5
1.2.2. UFC 3-250-01FA, Pavement Design for Roads, Streets, Walks, & Open Storage Areas, Chapter 13, 16 January 2004
1.2.3. UFC 3-230-17FA, Drainage for other than Airfields, 11 February 2013
1.2.4. UFC 3-250-04, Standard Practice for Concrete Pavements, Change 2, 29 July 2009
1.3. INDUSTRY STANDARDS
1.3.1. ACCE 7-05 Minimum Design Loads for Buildings and Other Structures, Chapter 1
1.3.2. EPA 841-B-09-001 – EPA Technical Guidance on Implementing the Storm Water Runoff Requirements for Federal Projects under Section 438 of the Energy Independence and Security Act, December 2009
PART II - PRODUCTS
2.1. MATERIALS:
2.1.1. All material selected to accomplish this Statement of Work shall be of good quality and intended for Commercial use. Items shall be of the proper type, size, and material for the use intended.
2.1.2. Contractor Furnished Materials: The Contractor furnished materials shall include all associated equipment and appurtenances required for performing the work in accordance with the equipment manufacturer’s literature.
PART III – EXECUTION
3.1. WORK REQUIREMENTS:
3.1.1. Scheduling and Coordination: The Contractor shall comply with the approved schedule and ensure that work commences in accordance with the issued Notice to Proceed. Work shall be coordinated with the assigned Contract Surveillance Representative (CSR).
Note: The Contractor shall further determine that all required notices have been given and permits obtained.
3.1.2. Scheduling and Sequence of Work: The work shall be performed in such a manner as to minimize interference with the normal daily work of the Government activity. Certain areas of the facility shall be vacated as necessary, in order for the Contractor to perform the required work. Prior to beginning work, the Contractor shall meet with the CSR so that the planned sequence of work and/or schedule may be reviewed and approved.
Page | 6
3.1.3. Interruption of Utilities Services: Interruptions shall be kept to a minimum and may only occur at such times and duration as approved by the CO. All utility interruptions shall be reviewed and accepted by the CSR before submitting to the CO for approval. Ten (10) days prior notification by the Contractor for a utilities shutdown is required.
3.1.4. Material, equipment, tools, and workmen shall be scheduled on the site in a timely manner to avoid delay in work. Items of material shall be inspected to make certain they are in compliance with the specifications and are free from defects and damage.
3.1.5. Measurements: Before fabrication, obtain necessary field measurements and verify all measurements.
3.1.6. Existing Work: The Contractor shall take measures to protect any existing work or property belonging to the government which is to remain in place in the work area. The Contractor shall be responsible for repairing or replacing any government property that is damaged during the performance of the contracted work. Failure to do so shall result in the government withholding contract funds in order to effect required replacement or repairs.
3.1.7. Facilities: The Contractor shall protect electrical and mechanical services and utilities. Where removal of existing utilities and pavement is specified or indicated, provide approved barricades, temporary covering of exposed areas, and temporary services or connections for electrical and mechanical utilities.
3.1.8. Dust and Debris Control: The Contractor shall prevent the spread of dust and debris to occupied portions of the building and avoid the creation of a nuisance or hazard in the surrounding area. Waste and debris resulting from the work being performed shall be cleaned up daily and promptly removed from the activity.
3.1.9. Soil and Concrete Testing: The Contractor shall pay for all necessary soil and concrete compression strength testing.
3.1.10. Geotechnical Testing Reports: Geotechnical Reports are not available for Hanger 1643. The Contractor shall pay for all Geotechnical testing.
3.2 PERFORMANCE:
3.2.1. Workmanship: Skilled personnel shall execute in a careful, neat, and proficient manner and in compliance with accepted trade practices and prevailing industry standards. All work, including any required design, shall be executed in accordance with Unified Facilities Guide Specifications (UFGS), Uniform Building Code (UBC), OSHA standards, and specifically 29 CFR 1910 and 29 CFR 1926. All work on this contract shall comply with all Local, State, and Federal Environmental Laws.
3.2.2. As used herein, “replace” means provide new materials to replace existing or missing materials.
Page | 7
3.2.3. Minor Materials and Work: Minor materials and work not specifically mentioned herein but necessary for the proper completion of the specified work shall be furnished without additional cost to the Government.
3.2.4. Unforeseen Major Repairs: Should deteriorated materials of a major nature be uncovered in the course of the work, it shall be brought to the attention of the CO and CSR. Repairs shall be made as directed by the CO, in writing, and an adjustment will be made in contract price in accordance with the terms of the modifications.
3.2.5. Existing Work: Where existing work is changed or removed, or where new work adjoins, connects to, or abuts existing work, the existing work shall be altered as necessary and connected in a substantial and workmanlike manner. All new work shall match, as nearly as practicable, existing, adjoining, and/or adjacent similar work.
Operations affecting existing work shall be conducted with care not to damage work in place, and all existing work damaged by such operations shall be rectified or replaced without additional expense to the Government.
PART IV: OTHER REQUIREMENTS
4.1. SCHEDULE:
The Contractor shall provide a Construction Schedule for CO approval. Work will be accomplished during normal Base operating hours, approximately 0730-1630 hours, Monday-Friday. No work will be scheduled on weekends without prior written approval by the CO, and concurrence of the CSR.
4.2. IDENTIFICATION OF EMPLOYEES:
The Contractor shall be responsible for furnishing to each employee, and for requiring each employee engaged on the Work to display, identification as approved and directed by the CO. Prescribed identification shall immediately be delivered to the CO upon release of any employee. All Contractor and Sub-Contractor personnel shall wear identifying markings on hard hats clearly identifying the Company for whom the employee works.
4.3. JOB SITE TOOLS AND EQUIPMENT:
All hand tools and equipment shall be maintained in good working order and properly stored when not in use. Construction attire shall be in accordance with applicable OSHA regulations.
4.4. SANITATION/TOILET FACILITIES:
The Contractor shall provide and maintain within the construction area minimum field type sanitary facilities approved by the CO. The portable sanitary facilities shall be securely attached to the ground to prevent blowing over. Government toilet facilities will not be available to the Contractor’s personnel.
Page | 8
4.5. CLEANUP:
At the end of each Working day the Contractor shall clean up the Work Site by the removal of all construction debris, waste materials, packaging material, and the like.
All construction waste shall be stored in appropriate size dumpsters, and covered in order to keep contents inside. Cleanup of the Work Site shall include the construction site and any other adjacent areas that have been affected. Any dirt or mud which is tracked on to any Base street, parking area, sidewalk, patio, or driveway shall be cleaned away daily.
4.6. OCCUPATIONAL SAFETY:
4.6.1. The Contractor shall be subject to No Notice Inspections under Occupational Safety and Health Act (OSHA) Program by Base Safety Inspectors, OSHA Safety Inspectors, and the Department of Labor.
4.6.2. The Primary Contractor shall enforce safety guidelines for all subcontracted personnel hired to perform work outlined in this SOW.
4.7. EXPLOSIVE OPERATED HANDTOOLS:
4.7.1. The Contractor shall comply with OSHA Standard 1910.215(c) when utilizing explosive operated hand tools. Storage of explosive cartridges on the Installation shall be in metal containers and limited to one (1) days' supply. The Contractor shall provide adequate controls to prevent loss/theft of cartridges used and stored on the Installation.
4.7.2. The Construction Contractor shall comply with AFMAN 91-201, NAVSEA OP 5, and NASFTWJRBINST 8000.3J when storing explosive cartridges for power tools.
The Construction Contractor shall notify the 301st Fighter Wing Weapons Safety Manager, the Navy Explosives Safety Officer, and the Navy Fire Department of the location of the stored explosive cartridges and the exact type of each explosive cartridge.
4.8. GENERATED REFUSE:
4.8.1. The Contractor shall take positive action to prevent Work generated refuse from entering the sewer system. The Contractor shall use contractor provided approved waste containers. All refuse and waste material shall be hauled in trucks with tight fitting beds and covers to prevent spillage on roadways. The Construction Site shall be kept neat, orderly, and safe for Workmen at all times.
4.8.2. The Contractor shall submit a monthly waste tracker log to the CO for all solid waste/refuse and recyclable items transported from the job site to an off-base landfill/recycling center.
Page | 9
4.9. SCHEDULE OF SUBMITTALS:
4.9.1. The Government shall provide as part of the solicitation a submittal register identifying to the Contractor those materials that shall be submitted for approval prior to performance under this contract.
4.9.2. The Contractor shall submit a Stormwater Pollution Plan as part of the submittal package. The Contractor shall also include a drawing and description of their plan to prevent soil erosion.
4.10. DIGGING PERMITS:
4.10.1. This Permit, NAS JRB Fort Worth Digging Permit (Change 2), shall be coordinated through the CSR, as appropriate, for coordination and shall be completed for Onsite excavation. The CO shall ensure that the Contractor has the completed Form at the Site prior to starting excavation work.
4.10.2. The Contractor shall contact 1-800-DIG-TESS for the location of public utilities.
4.10.3. All excavations other than building foundations, must have site restoration (sod, hydro-mulch, pavement, or other scheduled restoration), completed within fourteen (14) calendar days (excluding approved rain delay days) after excavation has been initiated.
4.11 BURN PERMITS:
All Burn Permits shall be coordinated through the CSR.
4.12 DRAWINGS AND MEASURMENTS:
4.12.1. All Government provided drawings and measurements are for reference purpose only. It is expected that the contractor will confirm all site conditions and validate all Government provided data.
4.12.2. Design Drawings and Specifications are a Contract deliverable and submittal requirement. Approved Drawings and Specifications shall become the property of the Government.
4.12.3. All Contract Drawings shall be well prepared, complete, and accomplished in accordance with the best professional practice to show clearly and concisely the type and extent of Work to be performed. The Drawings shall be drawn to appropriate scales and dimensioned completely and accurately. Extensive explanatory notes on the Drawings should be held to a minimum or placed in specifications. Dimensions shall be shown in Standard English units. Standard building material indications and symbols for architectural and structural items shall be used to the greatest extent possible. Drawings shall be delivered in hard copy, standard black line quality paper, Page | 10 at the conclusion of the construction project. All Review Drawings and Corrected Final Drawings shall be half size (11” x 17”)
4.12.4. The Contractor shall be allowed to work as their own in-house design architect for the purpose of this design deliverable.
4.12.5. The Contract will not be required to disclose the name of their Design Manager for the purpose of this design deliverable.
4.12.6. A Background File shall be made available by the Government to the Awarded Contractor for use in preparing the overall Design Drawing Submittals post contract award.
4.12.7. Drawings shall be prepared on AutoCAD 2015 or compatible format. Two (2) hard copies of all Drawings shall be provided to the Contracting Officer (CO) for review.
When the Design Drawings are accepted, the Construction Contractor may then begin construction while the As-Constructed Drawings are being developed with Base Civil Engineer (BCE) approval. Two (2) hard copies of As-Constructed Drawings shall be submitted to the Government upon completion of Construction and shall be reviewed for accuracy. Upon approval, the Construction Contractor shall provide two (2) electronic versions of the As-Constructed Drawings on AutoCAD 2015 or compatible format, and as .PDF to the Government on CD/DVD. The Drawings shall be drawn to appropriate scales and dimensioned completely and accurately. Extensive explanatory notes on the Drawings should be held to a minimum. Dimensions shall be shown in Standard English units. Standard building material indications and symbols for architectural items and for mechanical and electrical equipment shall be used to the greatest extent possible.
4.12.8. All drawings and load calculations submitted to the CO shall be performed by a Professional Engineer (PE) and verified by a visible PE stamp.
Note: All measurements, dimensions, and materials identified or described by the Government is for reference purposes only and need to be field validated by the Contractor.
4.13 SITE VISITATION:
Prior to submitting proposals, it is highly recommended that prospective contractors visit the site in order to satisfy themselves as to the nature of the project site, details, character, and amount of work to be accomplished. The Contractor is responsible for the verification of all statement of work details, critical measurements, drawing specification and dimensions, etc., prior to preparation of their proposal, ordering of materials, and execution of work. Failure to attend a site visit shall not relieve the contractor of responsibility for being knowledgeable of those conditions that can only be readily observed by attending a site visit.
Site visitation may be arranged by the CO.
Page | 11
4.14 TIME OF COMPLETION:
Contractor shall submit planned performance period for review and acceptance by the Government