20191706_Response_to_Questions.pdf

PDF 84 KB Posted

Attached to
Asphalt Federal contract opportunity
Solicitation number
FA663319QA009
Issued by
Department of the Air Force Reserve Command

About this file

Response to Contractor Questions

View the file

Other files for this federal contract opportunity

Other files attached to Asphalt, newest first.
File Type Posted
20191706_Amend1_MFR.pdf PDF
20190530_Clause_Selection.pdf PDF
20190530_SOW.pdf PDF
20190529_Combined_SS.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

17 June 2019

MEMORANDUM FOR RECORD:

SUBJECT: Responses to solicitation FA663319QA0009

1. In response to solicitation FA663319QA0009, asphalt, the following questions and responses are below:

What are you planning on for production rates? … 85 tons per hour … 105 tons per hour? *65-70*

What happens if there is a mechanical break-down on your end… How would we deal with suppliers for that down time? *The government will stop the hauling by contacting the plant and delay the hauling.*

You are taking care of the Prime coat and tack coat correct? *Not correct. It is in the SOW to be provided and applied.* As I understand the request is for 2400 tons Asphalt and 1850 tons RAP. *the government requires approximately 2400 tons of asphalt and need to turn over approximately 1850 tons of RAP. There will be a variation of quantity clause included in the order.*

They would need 5 business days of notice prior to delivery of the materials. Is it okay with you? Of course we understand about Rain/weather delays. *Yes this is fine*

You are looking at mid-August – 3 September which is around 2 weeks job correct? *August 17th for the application of the prime coat and the start of the asphalt binder – September 5th*

Below is the tentative schedule:

Install Prime Coat 1 day Sat 8/17/19 Sat 8/17/19

Paving Binder at Parking Stalls 2 days Sat 8/17/19 Tue 8/20/19 28 14 2

Paving Inside Lane 2 days Tue 8/20/19 Thu 8/22/19 29 14 2 31 Paving Outside Lane 2 days Thu 8/22/19 Sat 8/24/19 30 14 2

Paving Parking Lot 2 days Sat 8/24/19 Tue 8/27/19 31 14 2

Paving Surface at Parking Stalls 2 days Tue 8/27/19 Thu 8/29/19 32 14 2

Paving Surface Inside Lane 2 days Thu 8/29/19 Sat 8/31/19 33 14 2

Paving Surface Outside Lane 2 days Sat 8/31/19 Tue 9/3/19 34 14 2

Paving Surface Parking Lot 2 days Tue 9/3/19 Thu 9/5/19 35 14 2

Note: Prime & Tack Coat are in the SOW but are not a separately priced item.

2. If you have any questions on this amendment please contact the undersigned at 612-713- 1430.

Sharon Frank-Scheierl Contracting Officer

2019-06-17T10:42:59-0500