Question and Answers

View the file

Other files for this federal contract opportunity

Other files attached to Munitions Building Remodel, newest first.
File Type Posted
Tab_G-4_-_Primary_Elec_Distribution_Sys_-_One_Line_Diagram_-_20180419.pdf PDF
B813_Panels.png PNG image
FA663318B0002_20180622.pdf PDF
20180622_MFR_Amendments.pdf PDF
FA663318B0002_Specs_revised.pdf PDF
FA663318B0002_20180615.pdf PDF
20180531_Attendance_Sheet.pdf PDF
20180202_Wage_Determination.pdf PDF
Financial_Responsibility_Sheet.doc DOC document
FA663318B0002_20180517.pdf PDF
SF_24_Bid_Bond_Form.pdf PDF
02_-_Specifications_post.pdf PDF
01_-_Drawings.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QJKL 18-0010, Construct Add Munitions Admin, B814

Question 1. Please provide an existing one-line diagram of the distribution for this project.

See attached base one-line drawing.

Question 2. The one-line diagram on E2.1 does not show the refeeding of building 813. Please clarify work on the one-line diagram.

See attached B813_Panels and base one-line drawing.

Question 3. How long can buildings 813 and 814 be shutdown?

Building 813 should be shutdown for the least amount of time possible. No more than a few hours.

Can they be down for multiple days?

No.

Question 4. Please provide information as to where within the building the conductors feeding 813 are located.

See attached B813_Panels additional drawing.

Please provide information as to what they are feeding.

They are feeding a 480v MDP. The panel is within 6 feet of the edge of the wall.

Is this feeder within the building to be demolished as part of this project?

Not necessarily; the feeder can be spliced at the handhole and pulled into the building.

If so, can a site walk of this feeder within the building be provided?

No

Question 5. According to Drawing Note #2 on Systems Plan E1.4, the "Contractor is to terminate cables to existing patch panel termination location to be provided by Owner during construction" (within Comm Room 129). Is it safe to assume that there is enough space in the patch panels to accommodate the added cabling?

No.

Will the Owner be providing any additional patch panels if needed?

No.

If so, will they be loaded or unloaded?

Unloaded

Question 6. Will the data outlets require 4 cables in the TV locations as is with all the other data outlets shown?

No

Question 7. C2/E4.1 shows gray cable for voice and green cable for data, however Specification 271000 Section 2.3.1.1 states the cable shall be blue. Please clarify.

There is no longer a requirement for the separation of voice and data cables. All cable will be CAT6 or greater.

Question 8. Specification 271000 Section 2.4.1 states "Each outlet/connector shall be wired T568B", yet on C2/E4.1 it asks for T568A configuration for the NIPRNET cables. Please clarify.

Only T568B is to be used.

QJKL 18-0010, Construct Add Munitions Admin, B814

Question 9. Drawing A3.2 What is meant by architectural exposed structural steel? It all gets covered and is primed and painted.

Also structural drawing S2.2 shows canopy tube columns. The architectural drawing A3.2 shows a CMU wall.

The architectural drawing is for reference, refer to structural drawings for construction details.