02_-_QJKL_15-0034_-_Technical_Specifications-Revised.pdf
PDF 4 MB Posted
- Attached to
- Repair Mechanical-Electrical, Bldg 707, Lodging Federal contract opportunity
- Solicitation number
- FA6633-17-B-0001
About this file
Revised Technical Specifications
View the file
Other files for this federal contract opportunity
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Repair Mechanical and Electrical Lodging – Building 707
Project No. QJKL-15-0034
Location:
934th Airlift Wing, USAFR
760 Military Highway, Building 707 Minneapolis – St. Paul ARS, MN 55450-2100
Project Manual Book 1 of 1
(Architectural, Mechanical, Electrical)
Architect's Project Number: 100116
Kodet Architectural Group, Ltd.
15 Groveland Terrace
Minneapolis, Minnesota 55403
December 15, 2016
BID SET
REVISED 3-6-2017
BLANK PAGE
934th Airlift Wing Kodet Architectural Group, Ltd Centralized Recycling Facility – Building No. 733 Minneapolis, Minnesota USAF Project No. QJKL 03-0002
Certification Page 2
Kodet Architectural Group, Ltd Repair Mechanical and Electrical Lodging – Building 707 Minneapolis, Minnesota Project No. QJKL-15-0034
Section 00 00 10 Page 1
DIVISION 0 BIDDING AND CONTRACT REQUIREMENTS
000001 Title Page 000007 Certification Page 000010 Table of Contents
DIVISION 1 GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 14 00 Work Restrictions 01 30 00 Administrative Requirements 01 32 01.00 10 Project Schedule 01 33 00 Submittal Procedures 01 35 26 Governmental Safety Requirements 01 35 29.13 Health, Safety, And
Emergency Response Procedures for Contaminated Sites 01 42 00 Sources for Reference Publications 01 45 00.00 10 Quality Control 01 50 00 Temporary Construction Facilities and Controls 01 74 19 Construction and Demolition Waste Management 01 78 00 Closeout Submittals 01 78 23 Operation and Maintenance Data 01 91 00.00 40 Commissioning
DIVISION 2 SITE WORK
02 41 00 Demolition and Deconstruction
DIVISION 3 CONCRETE
No Sections under This Division
DIVISION 4 MASONRY
No Sections under This Division
DIVISION 5 METALS
No Sections under This Division
DIVISION 6 WOOD AND PLASTICS
No Sections under This Division
DIVISION 7 THERMAL AND MOISTURE PROTECTION
07 84 00 Firestopping
DIVISION 8 DOORS AND WINDOWS
08 31 13 Access Doors and Frames
DIVISION 9 FINISHES
09 29 00 Gypsum Board Assemblies 09 51 00 Acoustical Ceilings 09 90 00 Paints and Coatings
DIVISION 10 SPECIALTIES
No Sections under This Division
DIVISION 11 EQUIPMENT
No Sections under This Division
DIVISION 12 FURNISHINGS
No Sections under This Division
REVISED
Kodet Architectural Group, Ltd Repair Mechanical and Electrical Lodging – Building 707 Minneapolis, Minnesota Project No. QJKL-15-0034
Section 00 00 10 Page 2
DIVISION 13 SPECIAL CONSTRUCTION
No Sections under This Division
DIVISION 14 CONVEYING SYSTEMS
No Sections under This Division
DIVISION 23 MECHANICAL
23 00 00 Air Supply, Distribution, Ventilation, and Exhaust Systems 23 03 00.00 20 Basic Mechanical Materials and Methods 23 05 15 Common Piping for HVAC 23 05 48.00 40 Vibration and Seismic Controls for HVAC Piping and Equipment 23 05 93 Testing, Adjusting and Balancing for HVAC 23 07 00 Thermal Insulation for Mechanical Systems 23 08 00.00 10 Commissioning of HVAC Systems 23 09 00 Instrumentation and Control for HVAC 23 09 13 Instrumentation and Control Devices for HVAC 23 09 23.02 BACNET Direct Digital Control for HVAC and Other Building Control
Systems 23 31 13.00 40 Metal Ducts 23 36 00.00 40 Air Terminal Units 23 37 13.00 40 Diffusers, Registers and Grilles 23 52 46.00 20 Low Pressure Water Heating Boilers 23 81 00.00 20 Unitary Air Conditioning Equipment
DIVISION 26 ELECTRICAL
26 00 00.00 20 Basic Electrical Materials and Methods 26 05 00.00 40 Common Work Results for Electrical 26 05 19.00 10 Insulated Wire and Cable 26 29 23 Variable Frequency Drive Systems Under 600 Volts 26 52 00.00 40 Emergency Lighting
DIVISION 21 WET PIPE SPRINKLERS
No Sections under This Division
DIVISION 28 FIRE ALARM SYSTEM
No Sections under This Division
DIVISION 31 EARTHWORK
No Sections under This Division
DIVISION 32 EXTERIOR IMPROVEMENTS
No Sections under This Division
DIVISION 33 UTILITIES
No Sections under This Division
END OF SECTION 000010
Kodet Architectural Group, Ltd. Repair Mechanical and Electrical Lodging – Building 707
Section 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK
08/15
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES.
Submit the following in accordance with this section.
SD-01 Preconstruction Submittals
Salvage Plan;
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
This project renovates a major portion of the Mechanical and Electrical systems of Logging (Building 707). The renovations and Repair included the following but is not limited to:
1. Repair the existing Heating, Ventilating and Air-Conditioning (HVAC) systems and related electrical components.
2. Replace the Energy Management Control System (EMCS) backbone and framework.
3. Replace the input and output EMCS sensors and controllers throughout the building
4. Provide single button emergency HVAC shutdown capability for the entire facility
5. Remove and return to the 94th Airlift Wing the existing emergency generator
1.2.1.1 MECHANICAL
1. Individual guest rooms throughout the facility are conditioned by Packaged Terminal Air-Conditioning (PTAC) units. These units are mounted through the exterior wall beneath each window and include packaged DX cooling, electric resistance heating, a supply air fan and a fresh air connection. All PTAC units throughout the facility and their associated wall-mounted thermostats are to be replaced.
2. Two central station variable-air-volume (VAV) air-handling units (AHU-
2.1 & -3.1)serve as make-up air to guest room toilets and also condition the corridors in the east and west wings. These units will remain in place, with new EMCS sensors and controllers. The central station AHU ductwork will be extended to each individual east wing guest room.
3. First floor elevator lobbies are served by dedicated split system AHUs with DX cooling coils and hot water heating coils. The elevator lobbies on the second, third and fourth floors are conditioned by unit ventilators, which utilize DX cooling coils and hot water heating
Minneapolis, Minnesota Project No. QJKL-15-0034
Section 01 11 00 Page 2 coils. These units will remain in place, with new EMCS sensors and controllers.
4. A central station VAV AHU serves the central lobby, office/administration and support areas. This unit consists of a DX cooling coil, hot water heating coil and supply fan with a VFD. The Air-Cooled Condensing Unit (ACCU) and associated DX coil and refrigerant piping serving this AHU (ACCU-1.2) on the roof of the phase 1 building will be replaced due to a coil failure and loss of refrigerant.
5. There are a series of five ACCUs mounted adjacent to each other on the north side of the building between the central section of the building and the west wing. Four of these ACCUs (ACCU-2.3, -2.4, -2.5 and -2.6) are arranged in a manner where the rejected air from each unit interferes with the adjacent unit, causing overheating and the inability for proper operation.
a. Four of these ACCUs (-2.3, -2.4, -2.5 & 2.6) will need to be arranged so that their airflow will not interfere with adjacent units.
b. All of the three-ton ACCUs on both the Northwest (ACCU-2.3, -2.4, -2.5 & -2.6) and Northeast (ACCU- 3.2, -3.3, & -3.4) sides of the building are to be replaced including their associated DX coils and refrigerant piping.
6. A new one-ton split system packaged air-conditioning unit will be installed on the East side of the building to serve the IT closet in Room 1024, including a wallmounted evaporator, on-grade air-cooled condensing unit and associated refrigerant piping and controls.
7. Fan coil units utilizing DX cooling and hot water heating serve various other support areas. Hot water unit heaters heat mechanical and electrical rooms. Cabinet unit heaters utilizing electric resistance heating typically heat stairwells and other support areas located within the building. These units will remain in place, with limited new EMCS sensors and controllers depending on outdoor air connections.
8. Two Fulton Pulsepak natural gas-fired boilers supply heating hot water for the building. The first boiler has an output capacity of 1,260,000 Btu/hr. The second boiler has an output capacity of 855,000 Btu/hr.
These two hot water boilers will be replaced by two new high-efficiency condensing hot water boilers, using a basis-of-design of the KN Series boilers, each sized at an output capacity of 920,000.
FIRE PROTECTION AND LIFE SAFETY
Modifications to the existing systems will be made if needed for extension of new ductwork to east wing guest rooms.
BUILDING AUTOMATION SYSTEM (BAS)
The existing HVAC equipment is controlled by a dedicated direct digital control (DDC) system manufactured by Johnson Controls. This Building Automation System (BAS) is to be replaced and upgraded. There is a central workstation PC located at the main entrance front desk. The original system was designed to setback HVAC equipment during periods of no occupancy.
REVISED
3-6-2017
1283124220C Rectangle
Section 01 11 00 Page 3
The new BAS system shall consist of a front-end graphical navigation that allows for monitoring and manipulation of the building’s mechanical systems.
BAS shall include easily viewable and manageable trends and alarms.
Existing temperature, humidity, and pressure sensors are to be replaced.
Dampers, valves, actuators, and other controls devices are to be reused unless they are found to be faulty, in which case the matter shall be brought to the Government. If additional controls devices are required to achieve the included sequences, they shall be added.
Existing systems (some UH, CUH, EF) that are currently controlled via non-DDC controllers, shall be upgraded to include DDC control and BAS visibility. In spaces where temperature is controlled by multiple pieces of equipment, there shall be a single thermostat and the systems shall control in conjunction, never heating and cooling simultaneously.
EMERGENCY SHUTDOWN
The BAS shall include a physical “Emergency Shutdown” push-pull type button, which shall be used to close off the building in an emergency. When the button is pushed, all outside air and exhaust air dampers shall be closed, air handling units and exhaust fans shall be shut down, and PTAC units shall be shut off (and dampers closed).
INTERFACE WITH HOTEL MANAGEMENT SYSTEM
A special graphic screen shall be created for front desk personnel to allow for scheduling or commanding each room occupied/unoccupied when guests check-
in. This shall require three clicks or fewer to select a number or days and send the room occupied for that long. Room shall automatically go unoccupied at the end of this period.
1.1.2.2 ELECTRICAL
The 707 building has three switchboards and power distribution systems, one for the Main Building, one for the West Wing and one for the East Wing. The electrical design will conform to the applicable references of the codes and standards. There is no site and utilities work for electrical. There will be no emergency generator backup for these buildings. The existing Diesel generator will be removed, emptied and turned over to the Government. A new generator docking station will be provided.
Power Distribution (Main Building) The 1200A, 120/208V three phase, four wire switchboard is existing to remain and is located Electrical Room 1017. This switchboard is fed via a Manual Transfer Switch (MTS) from a pad mounted transformer or a Diesel generator.
The MTS, pad mounted transformer and the generator are located just outside the Electrical Room. As part of this project, the Diesel generator shall be disconnected from the MTS, emptied and turned over to the Government. The conduits and feeder between the generator and the MTS shall be removed.
Power Distribution (West Wing) The 2000A, 120/208V three phase, four wire switchboard is existing to remain and is located in Electrical Room 0103. This switchboard is feeding a lighting inverter EPS-A which is also located in Electrical Room 0103. All emergency lighting in the West Wing is connected to this inverter. This inverter has not been working for a while and it shall be replaced by a new Myers 20KVA, 120/208V inverter to be located in the same place as the existing one. All existing emergency lighting circuits shall be rewired into the new lighting inverter.
Section 01 11 00 Page 4
Power Distribution (East Wing) The 2000A, 120/208V three phase, four wire switchboard is existing to remain and is located in Electrical Room 1209. This switchboard is feeding a lighting inverter EPS-B which is also located in Electrical Room 01209. All emergency lighting in the East Wing is connected to this inverter. This inverter shall be replaced by a new Myers 20KVA, 120/208V inverter to be located in the same place as the existing one. All existing emergency lighting circuits shall be rewired into the new lighting inverter.
Lighting System There shall be no electrical work on the existing lighting systems, other than the rewiring of the emergency lighting loads in the West and East Wings into the new lighting inverters.
1.2.2 Location
The work is located at the Lodging (Building 707) at Minneapolis-Saint Paul Air Reserve Station, MN, approximately as indicated. The exact location will be shown by the Contracting Officer.
1.3 OCCUPANCY OF PREMISES
Building(s) Lodging (Building 707) will be occupied during performance of work under this Contract. [Occupancy notifications will be posted in a prominent location in the work area.
Before work is started, Contractor to arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.4 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.5 NOT USED
1.6 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
Pursuant to Contract Clause "FAR 52.245-1, Government Property", the Government will furnish the following materials and equipment for installation by the Contractor:
DESIGNATION NO. DESCRIPTION QUANTITY
Section 01 11 00 Page 5
DESIGNATION NO. DESCRIPTION QUANTITY
NA.
1.7 GOVERNMENT-INSTALLED WORK
NA.
1.8 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area as determined by the Contracting Officer. Area to be located within at Minneapolis-Saint Paul Air Reserve Station.
Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section –
Section 01 11 00 Page 6
Section 01 14 00 Page 1
SECTION 01 14 00
WORK RESTRICTIONS
11/11
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals. Submit the following in accordance with Section 01 33 00
Construction Progress Schedule (AF IMT 3064)
Material Approval Schedule (AF IMT 3000)
List of Contact Personnel
Personnel List
Vehicle List
1.2 SPECIAL SCHEDULING REQUIREMENTS
a. NA
b. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.
c. The Lodging (Building 707) will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.
d. Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 15 Fifteen calendar days prior to the desired date of interruption.
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry.
Mark Contractor equipment for identification.
1.3.1.1 Subcontractors and Personnel Contacts
Section 01 14 00 Page 2
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.3.1.2 Identification Badges and Base Access
Access onto and across the grounds shall be as directed by the Government.
Employee parking shall be as directed by the Contracting Officer. Also, the Government may impose restrictions regarding methods and points of contractor access in order to maintain orderly operation of the facility during the construction period.
1.3.1.3 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.3.2 Working Hours
Regular working hours must consist of an 8 1/2 hour period between 7 a.m.
and 3:30 p.m., Monday through Friday, excluding Government holidays.
1.3.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 Fifteen calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours.
During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.
1.3.4 Exclusionary Period
NA
1.3.5 Occupied Buildings
The Contractor shall be working on an existing building which is occupied.
Do not enter the building without prior approval of the Contracting Officer.
The existing buildings and their contents must be kept secure at all times.
Provide temporary closures as required to maintain security as directed by the Contracting Officer.
Provide dust covers or protective enclosures to protect existing work that remains and Government material located in the building during the construction period.
Relocate movable furniture approximately 6 feet away from the Contractor's working area as required to perform the work, protect the furniture, and
Section 01 14 00 Page 3 replace the furniture in their original location upon completion of the work. Leave attached equipment in place, and protect them against damage, or temporarily disconnect, relocate, protect, and reinstall them at the completion of the work.
1.3.6 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required paragraph WORK OUTSIDE REGULAR HOURS.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, are considered utility cutovers pursuant to the paragraph WORK
OUTSIDE REGULAR HOURS.
1.4 SECURITY REQUIREMENTS
Applicable contract Clauses include but are not limited to: FAR 52.204-9 Personal Identity Verification of Contractor Personnel and AFFARS 5352.242- 9000 Contractor Access to Air Force Installations.
Not Used
Section 01 14 00 Page 4
Section 01 30 00 Page 1
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
08/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 SUBMITTALS
Government approval is required for submittals. Submit the following in
View Location Map
Progress and Completion Pictures
SD-04 Samples
Color Boards
1.3 COLOR BOARDS FOR AIR FORCE PROJECTS
Submit five sets of color boards within 90 calendar days after Contract Award. Each set of boards must include samples of colors and finishes of interior surfaces, such as walls, floors, and ceilings. Present the samples on 8 by 10-1/2 inches boards (modules) with a maximum spread of 24 by 31-1/2 inches for foldouts. Design modules to fit in a standard loose-leaf, three-ring binder. Where special finishes such as architectural concrete, carpet, or prefinished textured metal panels are required, submit samples not less than 12 inches square with the board. If more space is needed, more than one board per set may be submitted. Certify that the color samples have been reviewed in detail, and that the color samples are in strict accordance with contract drawings and specifications, except as may be otherwise explicitly stated. Submittal of color samples does not relieve the Contractor of the responsibility to submit samples required elsewhere herein.
1.4 VIEW LOCATION MAP
Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
Section 01 30 00 Page 2
1.5 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color 150 minimum resolution in JPEG file format showing the sequence and progress of work.
Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten views from points located by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file. Include a date designator in file names. Cross reference submittals in the appropriate daily report. Photographs provided are for unrestricted use by the Government.
1.6 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 52.228-5 Insurance- Work on a Government Installation, during the entire period of performance under this contract. Provide other insurance coverage as required by Minnesota law.
1.7 FIRST TIER CONTRACTOR REQUIREMENTS FOR ASBESTOS CONTAINING MATERIALS
Accomplish all contract requirements of Section assigned to the directly with a first tier subcontractor.
1.8 SUPERVISION
1.8.1 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.
1.8.2 Superintendent Qualifications
The project superintendent must have a minimum of 10 years’ experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
For routine projects where the superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section 01 45 00.00 40 QUALITY CONTROL, the superintendent must have qualifications in accordance with that section.
Section 01 30 00 Page 3
]1.8.2.1 Duties
The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.
The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.8.3 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.9 PRECONSTRUCTION
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work must also attend.
1.10 INTEGRATED PRODUCT TEAM
To most effectively accomplish this contract, the Government requires the formation of a cohesive team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from the Contracting, the End User (who will occupy the facility), the Government Design and Construction team and Subject Matter Experts, the Installation, the Contractor and Subcontractors, and the Designer of Record will be invited to participate in the teaming process. The Contracting Officer will provide a list of key and optional personnel when IPT meetings are needed.
The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.
1.11 ELECTRONIC MAIL (E-MAIL) ADDRESS
Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when
Section 01 30 00 Page 4 emergency conditions warrant, such as hurricanes or terrorist threats.
Multiple email addresses are not allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this email address.
934Airlift Wing
Section 01 32 01.00 10 Page 1
SECTION 01 32 01.00 10
PROJECT SCHEDULE
02/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AACE INTERNATIONAL (AACE)
AACE 29R-03 (2011) Forensic Schedule Analysis
AACE 52R-06 (2006) Time Impact Analysis - As Applied in
Construction
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1-1-11 (1995) Administration -- Progress, Schedules, and Network Analysis Systems
Preliminary Project Schedule Initial Project Schedule Periodic Schedule Update
1.3 PROJECT SCHEDULER
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports.
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.
2.1.1 Not Used
Section 01 32 01.00 10 Page 2
2.1.2 Contractor Software
Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.
2.1.2.1 Government Software
Provide export file in a version importable by the Government system.
2.1.2.2 Not Used
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules. Prepare each Project Schedule using the Precedence Diagram Method (PDM).
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading.
Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
3.2.2 Withholdings / Payment Rejection
Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.
Section 01 32 01.00 10 Page 3
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.
3.3.3 Procurement Activities
Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.3.4 Mandatory Tasks
Include the following activities/tasks in the initial project schedule and all updates.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals
(individual activity for each).
b. Submission, review and acceptance of features require design completion
c. Submission of mechanical/electrical/information systems layout drawings.
d. Long procurement activities
e. Submission and approval of O & M manuals.
f. Submission and approval of as-built drawings.
g. Submission and approval of DD1354 data and installed equipment lists.
h. Submission and approval of testing and air balance (TAB).
i. Submission of TAB specialist design review report.
j. Submission and approval of fire protection specialist.
k. Submission and approval of Building Commissioning Plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with
Section 01 32 01.00 10 Page 4 all building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.
l. Air and water balancing.
m. Building commissioning - Functional Performance Testing.
n. Controls testing plan submission.
o. Controls testing.
p. Performance Verification testing.
q. Other systems testing, if required.
r. Contractor's pre-final inspection.
s. Correction of punch list from Contractor's pre-final inspection.
t. Government's pre-final inspection.
u. Correction of punch list from Government's pre-final inspection.
v. Final inspection.
3.3.5 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: approvals, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.6 Standard Activity Coding Dictionary
Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11. This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site:
http://rms.usace.army.mil.
The SDEF format is as follows:
Field Activity Code Length Description
1 WRKP 3 Workers per day
2 RESP 4 Responsible party
3 AREA 4 Area of work
4 MODF 6 Modification Number http://rms.usace.army.mil/
Section 01 32 01.00 10 Page 5
Field Activity Code Length Description
5 BIDI 6 Bid Item (CLIN)
6 PHAS 2 Phase of work
7 CATW 1 Category of work
8 FOW 20 Feature of work*
*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.
3.3.6.1 Workers Per Day (WRKP)
Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.
3.3.6.2 Responsible Party Coding (RESP)
Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.
a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.
b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);
ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).
3.3.6.3 Area of Work Coding (AREA)
Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings. Activities cannot have more than one Work Area Code.
Not all activities are required to be Work Area coded. A lack of Work Area coding indicates the activity is not resource or space constrained.
Section 01 32 01.00 10 Page 6
3.3.6.4 Modification Number (MODF)
Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.
3.3.6.5 Bid Item Coding (BIDI)
Assign a Bid Item Code to all activities using the Contract Line Item Schedule (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.
3.3.6.6 Phase of Work Coding (PHAS)
Assign Phase of Work Code to all activities. Examples of phase of work are procurement phase and construction phase. Each activity can have only one Phase of Work code.
a. Code proposed fast track design and construction phases proposed to allow filtering and organizing the schedule by fast track design and construction packages.
b. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.
3.3.6.7 Category of Work Coding (CATW)
Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to construction submittal, procurement, fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities. Each activity can have no more than one Category of Work Code.
3.3.6.8 Feature of Work Coding (FOW)
Assign a Feature of Work Code to appropriate activities based on the Definable Feature of Work to which the activity belongs based on the approved QC plan.
Definable Feature of Work is defined in Section 01 45 00.00 10 QUALITY CONTROL. An activity can have only one Feature of Work Code.
3.3.7 Contract Milestones and Constraints
Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.
Mandatory constraints that ignore or effect network logic are prohibited.
No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.
Section 01 32 01.00 10 Page 7
3.3.7.1 Project Start Date Milestone and Constraint
The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.
3.3.7.2 End Project Finish Milestone and Constraint
The last activity in the schedule must be a finish milestone titled "End Project."
Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path.
The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.
3.3.7.3 Interim Completion Dates and Constraints
Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.
3.3.7.3.1 Start Phase
Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.
3.3.7.3.2 End Phase
Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.
3.3.8 Calendars
Schedule activities on a Calendar to which the activity logically belongs.
Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop sSeasonal Calendar(s) and assign to seasonally affected activities as applicable.
If an activity is weather sensitive it should be assigned to a calendar showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the anticipated days provided in the contract clause TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. Assign non-work days over a seven-day week as weather records are compiled on seven-day weeks, which may cause some of the weather related non-work days to fall on weekends.
3.3.9 Open Ended Logic
Section 01 32 01.00 10 Page 8
Only two open ended activities are allowed: the first activity "NTP Acknowledged" may have no predecessor logic, and the last activity -"End Project" may have no successor logic.
Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.
3.3.10 Default Progress Data Disallowed
Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the Contractor's schedule.
3.3.11 Out-of-Sequence Progress
Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer. Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule.
Address out of sequence progress or logic changes in the Narrative Report and in the periodic schedule update meetings.
3.3.12 Added and Deleted Activities
Do not delete activities from the project schedule or add new activities to the schedule without approval from the Contracting Officer. Activity ID and description changes are considered new activities and cannot be changed without Contracting Officer approval.
3.3.13 Original Durations
Activity Original Durations (OD) must be reasonable to perform the work item. OD changes are prohibited unless justification is provided and approved by the Contracting Officer.
3.3.14 Leads, Lags, and Start to Finish Relationships
Lags must be reasonable as determined by the Government and not used in place of realistic original durations, must not be in place to artificially absorb float, or to replace proper schedule logic.
a. Leads (negative lags) are prohibited.
b. Start to Finish (SF) relationships are prohibited.
3.3.15 Retained Logic
Schedule calculations must retain the logic between predecessors and successors ("retained logic" mode) even when the successor activity(s) starts and the predecessor activity(s) has not finished (out-of-sequence
Section 01 32 01.00 10 Page 9 progress). Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") are not be allowed.
3.3.16 Percent Complete
Update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete to allow for proper schedule management.
3.3.17 Remaining Duration
Update the remaining duration for each activity based on the number of estimated work days it will take to complete the activity. Remaining duration may not mathematically correlate with percentage found under paragraph entitled Percent Complete.
3.3.18 Cost Loading of Closeout Activities
Cost load the "Correction of punch list from Government pre-final inspection" activity(ies) not less than 1 percent of the present contract value. Activity(ies) may be declared 100 percent complete upon the Government's verification of completion and correction of all punch list work identified during Government pre-final inspection(s).
3.3.18.1 As-Built Drawings
If there is no separate contract line item (CLIN) for as-built drawings, cost load the "Submission and approval of as-built drawings" activity not less than $35,000 or 1 percent of the present contract value, which ever is greater, up to $200,000. Activity will be declared 100 percent complete upon the Government's approval.
3.3.18.2 O & M Manuals
Cost load the "Submission and approval of O & M manuals" activity not less than $20,000. Activity will be declared 100 percent complete upon the Government's approval of all O & M manuals.
3.3.19 Anticipated Adverse Weather
Paragraph applicable to contracts with clause entitled TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER. There shall be no time extensions for unusually severe weather.
3.3.20 Early Completion Schedule and the Right to Finish Early
An Early Completion Schedule is an Initial Project Schedule (IPS) that indicates all scope of the required contract work will be completed before the contractually required completion date.
a. No IPS indicating an Early Completion will be accepted without being fully resource-loaded (including crew sizes and manhours) and the Government agreeing that the schedule is reasonable and achievable.
Section 01 32 01.00 10 Page 10
b. The Government is under no obligation to accelerate work items it is responsible for to ensure that the early completion is met nor is it responsible to modify incremental funding (if applicable) for the project to meet the contractor's accelerated work.
3.4 PROJECT SCHEDULE SUBMISSIONS
Provide the submissions as described below. The data CD/DVD, reports, and network diagrams required for each submission are contained in paragraph SUBMISSION REQUIREMENTS. If the Contractor fails or refuses to furnish the information and schedule updates as set forth herein, then the Contractor will be deemed not to have provided an estimate upon which a progress payment can be made.
Review comments made by the Government on the schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents.
3.4.1 Preliminary Project Schedule Submission
Within 15 calendar days after the NTP is acknowledged submit the Preliminary Project Schedule defining the planned operations detailed for the first 90 calendar days for approval. The approved Preliminary Project Schedule will be used for payment purposes not to exceed 90 calendar days after NTP.
Completely cost load the Preliminary Project Schedule to balance the contract award CLINS shown on the Price Schedule. The Preliminary Project Schedule may be summary in nature for the remaining performance period. It must be early start and late finish constrained and logically tied as specified. The Preliminary Project Schedule forms the basis for the Initial Project Schedule specified herein and must include all of the required plan and program preparations, submissions and approvals identified in the contract (for example, Quality Control Plan, Safety Plan, and Environmental Protection Plan) as well as design activities, planned submissions of all early design packages, permitting activities, design review conference activities, and other non-construction activities intended to occur within the first 90 calendar days. Government acceptance of the associated design package(s) and all other specified Program and Plan approvals must occur prior to any planned construction activities. Activity code any activities that are summary in nature after the first 90 calendar days with Bid Item (CLIN) code (BIDI), Responsibility Code (RESP) and Feature of Work code
(FOW).
3.4.2 Initial Project Schedule Submission
Submit the Initial Project Schedule for approval within 42 calendar days after notice to proceed is issued. The schedule must demonstrate a reasonable and realistic sequence of activities which represent all work through the entire contract performance period. No payment will be made for work items not fully detailed in the Project Schedule.
3.4.3 Periodic Schedule Updates
Update the Project Schedule on a regular basis, monthly at a minimum.
Provide a draft Periodic Schedule Update for review at the…