14-1006_Schedule_of_Material_Submittals.xlsx
XLSX spreadsheet 26 KB Posted
- Attached to
- Repair/Survey Sewer Sanitary Lines Federal contract opportunity
- Solicitation number
- FA5575-15-B-0006
About this file
Attachment 3 AF 66 Submittals
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA5575-15-B-0006-001.doc | DOC document | |
| FA5575-15-B-0006 _RPR_Sewer_Lines.pdf | ||
| 14-1006_Drawings.pdf | ||
| 14-1006_Specifications.pdf | ||
| Attachment_5_-_PPI_reference_list.doc | DOC document | |
| 14-1006_Especificaciones.pdf | ||
| 14-1006_AF3052_KTR.xlsx | XLSX spreadsheet | |
| FA5575-15-B-0006 _Synopsis.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals Schedule
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER | |||
| QUUG 14-1006 | PROJECT TITLE | |||
| RPR/SURVEY SEWER SANITARY LINES | SOLICITATION / CONTRACT NO. |
| (To be completed by Project Engineer) | (To be completed by Contract Administrator) | ||||||||||||||||||||||
| NUMBER OF COPIES REQUIRED | |||||||||||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MANUFACTURER'S RECOMMENDATION | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | SCHEDULES, LISTINGS, REPORTS, PLANS | TECHNICAL DATA | TEST REPORTS | FIELD REPORTS | REQUIRED SUBMISSION DATE | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | |
| APPROVED | DISAPPROVED | ||||||||||||||||||||||
| SECTION 01 11 00 | |||||||||||||||||||||||
| 1 | Construction Schedule | 4 | NTP+15 | ||||||||||||||||||||
| SECTION 01 11 01 | |||||||||||||||||||||||
| 2 | Progress Schedule | 4 | NTP+10 | ||||||||||||||||||||
| 3 | Mobility Plan | 4 | NTP+15 | ||||||||||||||||||||
| 4 | Quality Control Plan | 4 | NTP+15 | ||||||||||||||||||||
| 5 | Environmental Protection Plan | 4 | NTP+15 | ||||||||||||||||||||
| 6 | Waste & construction debris management | 4 | Final Inspection | ||||||||||||||||||||
| 7 | As-Built drawings | 4 | FI+15 | ||||||||||||||||||||
| 8 | Spatial Data | 4 | FI+15 | ||||||||||||||||||||
| 9 | Key Personnel | 4 | NTP+15 | ||||||||||||||||||||
| 10 | Personel listing | 4 | NTP+15 | ||||||||||||||||||||
| 11 | Safety Program | 4 | NTP+15 | ||||||||||||||||||||
| 12 | Warranty letter | 4 | FI+30 | ||||||||||||||||||||
| SECTION 33 30 00 | |||||||||||||||||||||||
| 13 | PVC pipe and fittings | 4 | |||||||||||||||||||||
| 14 | Round manhole (less than 1.2 m depth) | 4 | |||||||||||||||||||||
| 15 | Round manhole (more than 1.2 m depth) | 4 | |||||||||||||||||||||
| 16 | Round manhole frame and cover | 4 | |||||||||||||||||||||
| 17 | Sewer pipe protection film and sealant | 4 | |||||||||||||||||||||
| 18 | Pipe Cleaning and Inspection Procedures | 4 | |||||||||||||||||||||
| 19 | Plan and topographic profile for new pipe installation | 4 | NTP+20 | ||||||||||||||||||||
| 20 | Color coding pipe condition drawings | 4 | Final Inspection | ||||||||||||||||||||
| 21 | CCTV Recordings and Report Logs | 4 | Final Inspection | ||||||||||||||||||||
| 22 | Contractor Qualifications for CCTV inspection | 4 |
&"Arial,Bold"&8Schedule of Material Submittals, Feb 05 (SAF/AQCP) Page &P of &N
MSS Spanish
| RESUMEN MUESTRAS DE MATERIAL | NÚMERO PROYECTO: | |||
| QUUG 14-1006 | TÍTULO DE PROYECTO: | |||
| REPARAR/INSPECCIONAR LÍNEAS DE SANEAMIENTO | SOLICITACIÓN / CONTRATO NO. |
| (A cumplimentar por el ingeniero del proyecto) | (A cumplimentar por administrador del contrato) | ||||||||||||||||||||||
| NUMBER OF COPIES REQUIRED | |||||||||||||||||||||||
| LÍNEA NÚMERO | PARTIDA O DESCRIPCIÓN DE PARTIDA, REFERENCIA DEL CONTRATO, TIPO DE PRESENTACIÓN | CERTIFICADO DE CUMPLIMIENTO | PLANOS DE TALLER | MUESTRAS | SELECCIÓN DE COLOR | RECOMENDACIONES DEL FABRICANTE | GARANTÍA DEL FABRICANTE | DATOS DE CATÁLOGO | INSTRUCCIONES DE FUNCIONAMIENTO | PROGRAMAS, LISTADOS, INFORMES, PLANES | DATOS TÉCNICOS | PRUEBAS | INFORMES DE TRABAJOS DE CAMPO | FECHA DE ENTREGA | FECHA RECEPCIÓN EN CONTRATACIÓN | FECHA EN INGENIERíA CIVIL | FECHA LÍMITE DE DEVOLUCIÓN | NÚMERO DE MUESTRA | FECHA NOTIFICACIÓN A CONTRATISTA | SEGUNDA PRESENTACIÓN DEL CONTRATISTA | APROBACIÓN FINAL | OBSERVACIONES | |
| APROBADO | DESAPROBADO | ||||||||||||||||||||||
| SECCIÓN 01 11 00 | |||||||||||||||||||||||
| 1 | Programa de de obra | 4 | NTP+15 | ||||||||||||||||||||
| SECCIÓN 01 11 01 | |||||||||||||||||||||||
| 2 | Programa de avance de obras | 4 | NTP+10 | ||||||||||||||||||||
| 3 | Plan de movilización | 4 | NTP+15 | ||||||||||||||||||||
| 4 | Plan de control de calidad | 4 | NTP+15 | ||||||||||||||||||||
| 5 | Plan de protección medioambiental | 4 | NTP+15 | ||||||||||||||||||||
| 6 | Gestión de residuos y escombros | 4 | Inspección final | ||||||||||||||||||||
| 7 | Planos As-Builts | 4 | IF+15 | ||||||||||||||||||||
| 8 | Datos espaciales | 4 | IF+15 | ||||||||||||||||||||
| 9 | Personal clave | 4 | NTP+15 | ||||||||||||||||||||
| 10 | Listado de personal | 4 | NTP+15 | ||||||||||||||||||||
| 11 | Plan de seguridad | 4 | NTP+15 | ||||||||||||||||||||
| 12 | Carta de garantía | 4 | IF+30 | ||||||||||||||||||||
| SECCIÓN 33 30 00 | |||||||||||||||||||||||
| 13 | Tubería y accesorios | 4 | |||||||||||||||||||||
| 14 | Arquetas de registro circulares menores de 1.2 m de profundidad | 4 | |||||||||||||||||||||
| 15 | Pozos de registro circulares mayores de 1.2 m de profundidad | 4 | |||||||||||||||||||||
| 16 | Marcos y tapas de pozos de registro circulares | 4 | |||||||||||||||||||||
| 17 | Lámina de protección y sellante para tubería de saneamiento | 4 | |||||||||||||||||||||
| 18 | Procedimientos de limpieza e inspección de tubería | 4 | |||||||||||||||||||||
| 19 | Planta y perfil topográfico para instalación de nueva tubería | 4 | NTP+20 | ||||||||||||||||||||
| 20 | Planos del estado de tuberías con código de colores | 4 | Inspección final | ||||||||||||||||||||
| 21 | Grabaciones e informes de inspección CCTV | 4 | Inspección final | ||||||||||||||||||||
| 22 | Cualificación de empresa de inspección CCTV | 4 |
&"Arial,Bold"&8Resumen de muestras de material, Feb 05 (SAF/AQCP) Página &P de &N