FA520919U0047_-_Site_Visit_Questions.xlsx
XLSX spreadsheet 11 KB Posted
- Attached to
- BUILDING 4145 REWIRE Federal contract opportunity
- Solicitation number
- FA520919U0047
About this file
Please see attached answers to questions from the Site Visit!
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_1_-_Pricing_Schedule.doc | DOC document | |
| Attachment_3a_-_Drawing_1_4145.pdf | ||
| Attachment_3_-_Main_Drawing_4145.pdf | ||
| Attachment_3c_-_Drawing_3_4145.pdf | ||
| 1._Combined_Synopsis_Building_4145.docx | DOCX document | |
| Attachment_3b_-_Drawing_2_4145.pdf | ||
| Attachment_2_-_PWS_4145.docx | DOCX document | |
| Attachment_5_-_Request_to_Attend_Site_Visit.xls | XLS spreadsheet | |
| Attachment_4_-_Reps_and_Certs.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| FA5209-19-U-0047 - Site Visit Questions - Posting Date August 16th 2019 | |||
| No | Reference | Question | Answers |
| 1 | Attachment 1 (Pricing) | From the site visit, we understand that we should express the price in US dollars. |
A. Will payments be made in US dollars or yen?
| B. If payments will be made in yen, what exchange rate will the Government use to calculate amounts. | This will be coordinated at the time of award. However, our Yen exchange rate is 111.5938 | |||
| 2 | PWS, Item 10 (Page 3 of 5) | We assume the building will be occupied with Government operations ongoing during the contract. Should we anticipate restrictions on work that can be performed during normal duty hours (for example, noise?) | No | |
| 3 | PWS, Item 1 (Page 1 of 5) | Regarding personnel, please describe Government requirements (including any specific qualifications) for on-site management during performance, for example, QC manager, SSHO, translator, etc, as well as duties which may not be held concurrently by the same person. | Please refer to the PWS; however, a translator should be available. | |
| 4 | PWS, Item 5 (Page 3 of 5) | Please specify submittal requirements for the contract. | Brief understanding document | |
| 5 | PWS, Item 2 (Page 1 of 5) | For office space in Attachment 3a, from the site visit we understand that as a general rule, drops may be accomplished via existing columns with the quad outlets mounted on the nearest column surface. Is this correct? | Yes | |
| 6 | PWS, Item 2 (Page 1 of 5) | For office space in Attachment 3c, from the site visit we understand that Contractor may install new columns to accomplish the drops, provided these are finished with a neat and professional appearance. Is this correct? | Yes | |
| 7 | PWS, Item 4.1.3 (Page 1 of 5) | For drop-down on walls, we assume it will be acceptable for gang boxes to mounted *on* the wall (not embedded.) Is this correct? | Yes | |
| 8 | PWS, Item 4.1.2 (Page 1 of 5) | From the site visit, we understand that when Contractor needs to cut the existing ceiling to install cable, it will be acceptable for Contractor to repair the ceiling with an access hatch, provided it is finished with a neat and professional appearance, instead of restoring the ceiling as original. Is this correct? | Yes | |
| 9 | PWS, Item 4.1.1 (Page 1 of 5) | From the site visit, we understand that use of flexible conduit will not be required in warehouse areas. Is this correct? | Yes, a neat and orderly J-hook system is fine. | |
| 10 | PWS, Item 13 (Page 4 of 5) | From the site visit, we understand that when new penetrations of firewalls are necessary, they must be fitted with a sleeve and fire seal; however, existing penetrations may be utilized as-is when possible. Is this correct? | Yes | |
| 11 | PWS, Item 13 (Page 4 of 5) | Please specify rating requirements for fire seals. | Utilizes fire stop. |