FA520919U0047_-_Site_Visit_Questions.xlsx

XLSX spreadsheet 11 KB Posted

Attached to
BUILDING 4145 REWIRE Federal contract opportunity
Solicitation number
FA520919U0047
Issued by
Department of the Air Force Pacific Air Forces

About this file

Please see attached answers to questions from the Site Visit!

View the file

Other files for this federal contract opportunity

Other files attached to BUILDING 4145 REWIRE, newest first.
File Type Posted
Attachment_1_-_Pricing_Schedule.doc DOC document
Attachment_3a_-_Drawing_1_4145.pdf PDF
Attachment_3_-_Main_Drawing_4145.pdf PDF
Attachment_3c_-_Drawing_3_4145.pdf PDF
1._Combined_Synopsis_Building_4145.docx DOCX document
Attachment_3b_-_Drawing_2_4145.pdf PDF
Attachment_2_-_PWS_4145.docx DOCX document
Attachment_5_-_Request_to_Attend_Site_Visit.xls XLS spreadsheet
Attachment_4_-_Reps_and_Certs.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

FA5209-19-U-0047 - Site Visit Questions - Posting Date August 16th 2019
NoReferenceQuestionAnswers
1Attachment 1 (Pricing)From the site visit, we understand that we should express the price in US dollars.

A. Will payments be made in US dollars or yen?

B. If payments will be made in yen, what exchange rate will the Government use to calculate amounts.This will be coordinated at the time of award. However, our Yen exchange rate is 111.5938
2PWS, Item 10 (Page 3 of 5)We assume the building will be occupied with Government operations ongoing during the contract. Should we anticipate restrictions on work that can be performed during normal duty hours (for example, noise?)No
3PWS, Item 1 (Page 1 of 5)Regarding personnel, please describe Government requirements (including any specific qualifications) for on-site management during performance, for example, QC manager, SSHO, translator, etc, as well as duties which may not be held concurrently by the same person.Please refer to the PWS; however, a translator should be available.
4PWS, Item 5 (Page 3 of 5)Please specify submittal requirements for the contract.Brief understanding document
5PWS, Item 2 (Page 1 of 5)For office space in Attachment 3a, from the site visit we understand that as a general rule, drops may be accomplished via existing columns with the quad outlets mounted on the nearest column surface. Is this correct?Yes
6PWS, Item 2 (Page 1 of 5)For office space in Attachment 3c, from the site visit we understand that Contractor may install new columns to accomplish the drops, provided these are finished with a neat and professional appearance. Is this correct?Yes
7PWS, Item 4.1.3 (Page 1 of 5)For drop-down on walls, we assume it will be acceptable for gang boxes to mounted *on* the wall (not embedded.) Is this correct?Yes
8PWS, Item 4.1.2 (Page 1 of 5)From the site visit, we understand that when Contractor needs to cut the existing ceiling to install cable, it will be acceptable for Contractor to repair the ceiling with an access hatch, provided it is finished with a neat and professional appearance, instead of restoring the ceiling as original. Is this correct?Yes
9PWS, Item 4.1.1 (Page 1 of 5)From the site visit, we understand that use of flexible conduit will not be required in warehouse areas. Is this correct?Yes, a neat and orderly J-hook system is fine.
10PWS, Item 13 (Page 4 of 5)From the site visit, we understand that when new penetrations of firewalls are necessary, they must be fitted with a sleeve and fire seal; however, existing penetrations may be utilized as-is when possible. Is this correct?Yes
11PWS, Item 13 (Page 4 of 5)Please specify rating requirements for fire seals.Utilizes fire stop.