Attachment_2_-_PWS_4145.docx

DOCX document 24 KB Posted

Attached to
BUILDING 4145 REWIRE Federal contract opportunity
Solicitation number
FA520919U0047
Issued by
Department of the Air Force Pacific Air Forces

About this file

Attachment 2 - PWS 4145

View the file

Other files for this federal contract opportunity

Other files attached to BUILDING 4145 REWIRE, newest first.
File Type Posted
FA520919U0047_-_Site_Visit_Questions.xlsx XLSX spreadsheet
Attachment_3_-_Main_Drawing_4145.pdf PDF
Attachment_3c_-_Drawing_3_4145.pdf PDF
Attachment_5_-_Request_to_Attend_Site_Visit.xls XLS spreadsheet
Attachment_4_-_Reps_and_Certs.docx DOCX document
1._Combined_Synopsis_Building_4145.docx DOCX document
Attachment_3b_-_Drawing_2_4145.pdf PDF
Attachment_1_-_Pricing_Schedule.doc DOC document
Attachment_3a_-_Drawing_1_4145.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 2 Solicitation No. FA520919U0047

PERFORMANCE WORK STATEMENT (PWS)

FOR

PREMISE WIRING UPGRADE BLDG. 4145 AT YOKOTA AIR BASE, JAPAN

1. DESCRIPTION OF SERVICES. The contractor shall provide all personnel, equipment, tools, vehicles, materials, supervision, and other items and services necessary to install CAT 6 network cables at Yokota Air Force Base, Japan - (B4145). The contractor shall perform replacement services in accordance with (IAW) this PWS, manufacturer standards, commercial practice and local standards. All parts and materials must be compliant with the Trade Agreement Act (TAA).

2. OBJECTIVES. The contractor shall install 106 Quad outlets and associated cabling (CAT 6) for a total of 424 data drops. The contractor will purchase and install 2 new communication racks with lockable doors, and install power (1 existing and the 2 new racks), associated grounding and anchoring. The contractor will also install, terminate and test a six strand single mode fiber optic cable from Rack A to B and Rack A to C.

3. SCOPE. Install, terminate, and test CAT 6 network cables and hardware. Hardware includes communication racks, power, anchoring and grounding. Utilize drawings (Appendix A) for rack, and quad outlet locations. Remove old legacy cables, and communication racks.

4. REQUIREMENTS. The newly installed and existing network infrastructure shall fulfill the following requirements:

4.1. Task 1 – Install, Terminate and Label CAT 6 Network Cables.

4.1.1 Subtask 1 – Install raceway, 4 Port Gang Boxes, Patch Panel. Install new raceway, gang boxes and patch panels at predetermined locations throughout facility IAW Attachments 3 – 3c, Utilize flexible conduit in warehouse area.

4.1.2 Subtask 2 – Install CAT 6 Network Cables. All cabling will be installed from the communication rack to the outlet, no splices. Install CAT 6 network cables (blue or gray), utilizing existing ladder rack (if available) and newly installed J-hooks or equivalent.

4.1.3 Subtask 3 – Terminate CAT 6 Network Cables. Terminate CAT 6 cables into gang boxes at designated locations IAW Attachments 3 – 3c. Terminate other side of CAT 6 network cables into communication rack, utilize appropriate wire management techniques. All terminations will be B-standard.

4.1.4 Subtask 4 – Label Network Cables. Label all network cables at the gang boxes and patch panel; example RM101 1-4, RM 101 5-8. Numbering sequence shall be in numerical order at the patch panel.

4.2. Task 2 – Install communication rack, ladder rack, power and associated grounding.

4.2.1 Subtask 1 – Install communication rack. Purchase and install 2 standard (19”W X 73.5”H X 36.5”D) communication racks. Anchor communication rack to the floor. The rack must have side panels, front and back door. Any other style of rack must be approved by the 374 CS/SCXP. Placement of the communication rack will first be approved by the 374 CS/SCXP. Install vertical and horizontal wire management inside the communication rack.

4.2.2 Subtask 2 – Ground communication rack. Ground communication rack to closest approved grounding location. Utilize 6 AWG, green coated ground wire. Utilize NO-OX on grounding lugs and connections to prevent corrosion. Ground test results will be no higher than 10 OHMS.

4.2.3 Subtask 3 – Install power to 3 communication racks. Install electrical power to communication racks from closest available power breaker panel. Specs as followed: 100-110V, 50-60 Hertz 20 AMP 515 NEMA outlet.

4.3. Task 3 – Install, terminate and test single mode fiber optic cable.

4.3.1 Subtask 1 – Rack A to Rack B. Install 6 strand single mode fiber optic cable from the Rack A to Rack B. Terminate cable utilizing LC type connectors. Label cable (FOCA TIE Rack A-B SM 1-6) at both termination points. Test and document results (no more than 1 DB loss).

4.3.2 Subtask 2 – Rack A to Rack C. Install 6 strand single mode fiber optic cable from Rack A to Rack C. Terminate cable utilizing LC type connectors. Label cable (FOCA TIE Rack A-C SM 1-6) at both termination points. Test and document results (no more than 1 DB loss).

4.4. Task 4 – Test

4.4.1 Subtask 1 – Test CAT 6 Network Cables. Test all network cables in facility and document results.

4.5. Task 5 – Building Cut Over and Legacy Cable Removal

4.5.1 Subtask 1 – Facility Cut Over. After installation acceptance. Military personnel will program and install the switch. The contractors will cut the facility over and utilize wire management techniques to add jumpers in the communication rack. Jumpers will be added from data ports to switch. Observation will be conducted by the 374 CS/SCOIN work center.

4.5.2 Subtask 2 – Removal of legacy cables. When building is cut over the contractor will remove 90% of the old legacy cables.

5. DELIVERABLES.

Tasks
Acceptable Quality Level (AQL)
Acceptance/Deliverable
4.2 Install communication rack, ladder rack, power and associated grounding
Rack must be anchored, grounding must be no greater than 10 ohms. Vertical and horizontal wire management must be provided.

Electrical power must be 100-110V, 50-60 Hertz 20 AMP 515 NEMA outlet.

Deliverable 1. Will be reviewed upon project completion - 100% Inspection.

4.3 Install, terminate and test single mode fiber optic cable
Test and document results (no more than 1 DB loss).
Deliverable 2. Will be reviewed upon project completion - 100% Inspection.
4.4 Test
All cables shall meet at a minimum a 1 Gig Xfer Rate.
Deliverable 3. Will be reviewed upon project completion - 100% Inspection.

Installation completion

Upon completion of the Task 1-4, the Site POC will schedule inspection with 374 CS/SCXP. AFTO 747 acceptance will be generated by plans work center.

Project completion

Upon completion of the Task 5, the Site POC will schedule inspection with 374 CS/SCXP. AFTO 747 acceptance will be generated by plans work center.

6. PLACE OF PERFORMANCE. All work shall be performed in B4145. See Attachments 3 – 3c for details.

7. PERIOD OF PERFORMANCE. All work shall be completed 5 months after date of award. However the vendor should quote their best estimate in terms of the amount of time to complete the project. The vendor shall be available for a kickoff meeting with the customer no later than two weeks after the award date. As directed by the Site POC, the contractor shall continue performance in emergency or mission essential conditions. Additionally, the contractor may be required to account for the whereabouts of their personnel should this information be requested by the Site POC.

8. INSTALLATION PLAN. The Contractor shall arrange an installation plan and schedule with the Site POC, and obtain an approval from the Site POC prior to the commencement of the work.

9. ARRANGEMENTS OF THE PERFORMANCE TIME. The contractor will coordinate all after hour work with site POC and shall do so at no additional cost to the Government.

10. HOURS OF SERVICE. The contractor’s personnel shall perform scheduled work on weekdays, Monday through Friday (exclusive of the below U.S. legal and other designated holidays), during normal duty hours, 0800 - 1630 hours unless prior arrangements have been made with the Site POCs.

U.S. HOLIDAYS:

1 January
New Year's Day
3rd Monday of January
Martin Luther King, Jr’s Birthday
3rd Monday of February
Washington's Birthday
Last Monday of May
Memorial Day
4th July
Independence Day
1st Monday of September
Labor Day
2nd Monday of October
Columbus Day
11th November
Veterans Day
4th Thursday of November
Thanksgiving Day
25th December
Christmas Day

11. SITE POC. The Site POCs for this contract is 374 CS/SCXP 225-9690. The contractor shall coordinate all aspects of this project with the Site POCs. Completed work shall be subject to inspection and acceptance by the Site POCs.

12. GOVERNMENT-FURNISHED EQUIPMENT (GFE)/GOVERNMENT-FURNISHED INFORMATION

(GFI). None

13. OTHER PERTINENT INFORMATION OR SPECIAL CONSIDERATIONS.

The Contractors shall be responsible for gathering all information needed for the work to be completed. All questions shall be submitted in writing to the Contracting Officer (CO) and Contract Administrator (CA) three days prior to the site visit.

The Contractor shall have at least three (3) years of experience in construction, network cabling installation and/or maintenance and testing. At minimum, key personnel shall have a professional knowledge of communications engineering concepts, principles and practices and extensive familiarity with other engineering disciplines; knowledge of a broad range of networking standards, methods, practices, techniques, materials and equipment to ensure work is in compliance with regulations and standards, and at least 3 years of experience.

The Contractor shall be responsible for the transportation of all system equipment to the site locations. Upon request of the Contractor, the Government may provide a temporary storage. In such case, the Contractor shall be responsible for inventory and reconciliation of all shipments, which will be coordinated with and verified by a Government representative. Also the Contractor shall transport all equipment from the temporary storage area to the final destination.

The Contractor shall coordinate the site visit through the Site POC and the CO/CA. The Site POC will provide any applicable forms regarding site visits. The Contractor shall provide all necessary site visit information to the government’s Site POC (374 CS/SCXP) at least 10 days prior to any site visit. The Contractor shall coordinate all deliveries with the Site POC at least 10 days prior to delivery and provide any site visit information required for the delivery. This will ensure visit clearances can be obtained from the local Security/Visitor Control Office. Visits include, but are not limited to, meetings, surveys, testing, etc.

The Contractor shall provide a standard commercial warranty to correct possible defects in materials and workmanship. The warranty shall be provided for one years commencing at the time of final system acceptance and shall include all equipment purchased, including but not limited to, infrastructure equipment.

Inspection and Acceptance Criteria. Two inspections and acceptances will be completed. One inspection and acceptance will be completed after installation, and one after facility is cut over and legacy cables are removed.

14. TECHNICAL STANDARDS. The following are technical standards. The Contractor will use the most up to date version.

Technical Standards

|X| ANSI/TIA/EIA 606, Administration Standards for the Telecommunications Infrastructure of Commercial Buildings |X| ANSI/TIA/EIA 607, Ground and Bonding Requirements for Telecommunications in Commercial Buildings |X| ANSI/TIA/EIA 568A, Commercial Building Telecommunications Wiring |X| ANSI/TIA/EIA 569B, Commercial Building Standard for Telecommunications Pathways and Spaces |X| ANSI/TIA/EIA 569D, Commercial Building Standard for Telecommunications |X| National Electric Code, NFPA 70, NEC 2002 |X| BICSI Telecommunications Cabling Installation Manual, 10th Edition, 2003 |X| FED-STD-1037B, Telecommunications: Glossary of Telecommunication Terms |X| IEEE-315-1975, Graphic Symbols for Electrical and Electronic Diagrams |X| IEEE-315A-1994, Supplement to Graphic Symbols for Electrical and Electronic Diagrams |X| RUS Bulletin 1751F-802, Electrical Protection Grounding Fundamentals |X| TIA/EIA-568-A.1, Commercial Building Telecommunications Wiring Standard |X| TIA/EIA-568-A.2, 100 Ohm Twisted-Pair Cabling Standard |X| TIA/EIA-568-A.4, Shielded Twisted-Pair Cabling Standard |X| TIA/EIA-569-B, Commercial Building Standard for Telecom. Pathways and Spaces |X| TIA/EIA-67, Transmission Performance Specifications for Field Testing of Unshielded Twisted-Pair Cabling Systems |X| TIA/EIA-TSB 75, Additional Horizontal Cabling Practices for Open Offices.

|X| TIA/EIA-TSB 95, Additional Transmission Performance Guidelines for 4-pair 100W Category 5e Cable |X| TIA/EIA-606, Administration Standard for the Telecommunications Infrastructure of Commercial Buildings |X| TIA/EIA-607, Commercial Building Grounding/Bonding Requirements |X| TIA/EIA-758, 758-1, Customer Owned Outside Plant Telecommunications Cabling Standard.

|X| NFPA-70, National Electric Code (NEC) |X| ISO/IEC 11801, 2nd Edition, Generic Cabling for Customer Premises.

|X| ISO/IEC 61935, Test Methods for Copper Cabling.

The Technical Standards above facilitate the assurance that the maximum technical standards are provided.