Questions_and_Answers_for_FA5209.docx

DOCX document 12 KB Posted

Attached to
Bldg 703 Rewire Federal contract opportunity
Solicitation number
FA5209-18-Q-BH05
Issued by
Department of the Air Force Pacific Air Forces

About this file

Questions and Answers for FA5209-18-Q-BH05

View the file

Other files for this federal contract opportunity

Other files attached to Bldg 703 Rewire, newest first.
File Type Posted
Questions_and_Answers_2_for_FA5209.docx DOCX document
site_Visit_Word_Doc.docx DOCX document
site_Visit_Word_Doc.docx DOCX document
Attachment_4_Equipment_List.DOCX DOCX document
Attachment_1_PWS.DOCX DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers for FA5209-18-Q-BH05

1: Is it acceptable to utilize the products from different makers other than the ones stated in Attachment 4 if the products are approved to be equal in quality/performance?

A: Yes, approved equal products are acceptable.

2: would it be possible to “comm-out” during the project?

A: No. The process requested is for the contractor to install the new wiring first, at which point the Government will switch the system onto the new wiring. After this, the contractor is able to remove the old wiring. The point of this is to keep communications operational as much as possible.