Repair Thaw Shed Roof Federal contract opportunity
Solicitation number
FA5004-15-B-C004
Issued by
Department of the Air Force Pacific Air Forces

About this file

JA-6 - AF Form 66

View the file

Other files for this federal contract opportunity

Other files attached to Repair Thaw Shed Roof, newest first.
File Type Posted
JA-7_-_Page_4_Ladders.pdf PDF
FA5004-15-B-C004-0006.pdf PDF
FA5004-15-B-C004-0005.pdf PDF
Thaw_Shed_Photos.pdf PDF
Question_and_Answer__2(1).pdf PDF
JA-7_-_Page_4_Ladders.pdf PDF
FA5004-15-B-C004-0004.pdf PDF
FA5004-15-B-C004-0003.pdf PDF
JA-13_-_Specifications_Sec_05_51_33.pdf PDF
FA5004-15-B-C004-0002.pdf PDF
Question_and_Answer__1.pdf PDF
JA-1_-_Specifications.pdf PDF
JA-0_-_Statement_of_Work.pdf PDF
JA-7__-_Work_Areas.pdf PDF
FA5004-15-B-C004-00001.pdf PDF
JA-2_-_Specifications_01030.pdf PDF
JA-3_-_Specifications_Sec_07_53_23.pdf PDF
JA-1_-_Specifications.pdf PDF
JA-12_AF_Form_3065.pdf PDF
JA-7_-_Work_Areas.pdf PDF
JA-5_-_Pictures.pdf PDF
JA-9_-_AF_Form_3000.pdf PDF
JA-4_-_As_Built_Drawings.pdf PDF
JA-10_-_Wage_Determination.pdf PDF
FA5004-15-B-C004.pdf PDF
JA-8_-_AF_Form_103.pdf PDF
JA-0_-_Statement_of_Work.pdf PDF
JA-11_AF_Form_3064.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION/CONTRACT NO.

F MATERIAL SUBMITTALS

KEY: 1 SC -1 WEEK PRIOR TO SUBSTANTIAL COMPLETION INSPECTION 2 CM -2 WEEKS PRIOR TO COMMISSIONING 4 15 -4 WEEKS PRIOR TO ORDERING MATS/EQUIP FOR DIVISION 15 4 SC -4 WEEKS PRIOR TO SUBSTANTIAL COMPLETION INSPECTION 4 CM -4 WEEKS PRIOR TO COMMISSIONING 4 M -4 WEEKS PRIOR TO ORDERING MATS/EQUIP FOR SPEC SECTION

PR -4 WEEKS PRIOR TO CONSTRUCTION ACTIVITY

ED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

L I N E

N U M B E R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

C

ER

TI

FI

C A

TI

O

N O

F C

O M

PL

IA

N C

E

SH

O

P D

R A

W

IN

G S

SA

M

PL

ES

C O

LO

R

S

EL

EC

TI

O N

M A

N U

FA

C

TR

'S

R

EC

O M

M

EN

D A

TI

O

N S

M A

N U

FA

C

TU

R

ER

'S

W A

R R

A N

TY

C A

TA

LO

G D

A

TA

O

PE

R A

TI

N

G

IN

ST

R

U C

TI

O

N S

SE

R

VI

C

E / S

IZ

E

/ U

SE

S C

H

ED

U

LE

O

TH

ER

REQUIRED

SUB-

MISSION

DATE

DATE

RECEIVED

IN CON-

TRACTING

DATE TO

CIVIL

ENGINEER-

ING

RETURN

SUSPENSE

DATE

FOLLOW-UP

DATE

CONTRACTOR

NOTIFIED

CONTRAC-

TOR RE-

SUBMIT-

TAL

FINAL APPROVAL REMARKS

APPROV

ED

DIS-

APPROV

ED

STATEMENT OF WORK

(SOW)

1 Work Plan, SOW 3.4.1 5 4 wks prior to work

01000 DESCRIPTION OF

WORK AND COORDINATION

2 AF Form 103 01010 1.8 A 3 2 wks prior to work start

3 Welding Permits 01000 - 8.1 (If applicable) 2 2 wks prior to work

01030 SAFETY,

ENVIRONMENTAL

PROTECTION,

REGULATIONS, AND CODES

5 Construction Operations and Safety Plan - 1.6 2 4 wks prior to work 6 Safety and Health Plan - 1.8

2 4 wks prior to work

7 Environmental Protection Plan (EPP) - 1.20 2 6 wks prior to work 8 Hazardous Materials Inventory -

1.21 2 2 wks prior to work

9 Hazardous Waste Accumulation Log - 1.22 2 As Applicable

02070 DEMOLITION

10 Schedule- 4.2 2 4 wks prior to work

06100 ROUGH CARPENTRY

11 Product Data - 3.1 2 2 wks prior to ordering materials

07530 SINGLE-PLY

MEMBRANE ROOFING

12 Product Data - 2.1 2 2 wks prior to ordering materials

13 Manufacturer's Warranty - 2.2 2 1 wk after complete

07650 - FLEXIBLE FLASHING

14 Product Data - 3.1 2 2 wks prior to ordering materials

FTQW 10-2603 Repair Thaw Shed Roof, CH&PP (B6203)

FA5004-15-B-C004

EIELSON AFB, ALASKA

ATTACHMENT JA-6

AF FORM 66

SOLICITATION/CONTRACT NO.

F MATERIAL SUBMITTALS

KEY: 1 SC -1 WEEK PRIOR TO SUBSTANTIAL COMPLETION INSPECTION 2 CM -2 WEEKS PRIOR TO COMMISSIONING 4 15 -4 WEEKS PRIOR TO ORDERING MATS/EQUIP FOR DIVISION 15 4 SC -4 WEEKS PRIOR TO SUBSTANTIAL COMPLETION INSPECTION 4 CM -4 WEEKS PRIOR TO COMMISSIONING 4 M -4 WEEKS PRIOR TO ORDERING MATS/EQUIP FOR SPEC SECTION

PR -4 WEEKS PRIOR TO CONSTRUCTION ACTIVITY

ED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

L I N E

N U M B E R

ITEM OR DESCRIPTION

OF ITEM, CONTRACT

REFERENCE, TYPE OF

SUBMITTAL

C

ER

TI

FI

C A

TI

O

N O

F C

O M

PL

IA

N C

E

SH

O

P D

R A

W

IN

G S

SA

M

PL

ES

C O

LO

R

S

EL

EC

TI

O N

M A

N U

FA

C

TR

'S

R

EC

O M

M

EN

D A

TI

O

N S

M A

N U

FA

C

TU

R

ER

'S

W A

R R

A N

TY

C A

TA

LO

G D

A

TA

O

PE

R A

TI

N

G

IN

ST

R

U C

TI

O

N S

SE

R

VI

C

E / S

IZ

E

/ U

SE

S C

H

ED

U

LE

O

TH

ER

REQUIRED

SUB-

MISSION

DATE

DATE

RECEIVED

IN CON-

TRACTING

DATE TO

CIVIL

ENGINEER-

ING

RETURN

SUSPENSE

DATE

FOLLOW-UP

DATE

CONTRACTOR

NOTIFIED

CONTRAC-

TOR RE-

SUBMIT-

TAL

FINAL APPROVAL REMARKS

APPROV

ED

DIS-

APPROV

ED

FTQW 10-2603 Repair Thaw Shed Roof, CH&PP (B6203)

15 Shop Drawings - 3.2 3 4 wks prior to work

07 53 23 - ETHYLENE

PROPYLENE DIENE

MONOMER ROOFING

16 Shop Drawings - SD-02 3 4 wks prior to work

17 Product Data - SD-03 2 4 wks prior to work

18 Design Data - SD-05 2 4 wks prior to work

19 Certificates - SD-07 2 4 wks prior to work

20 Manufacturer's Instructions - SD-08 2 4 wks prior to work

21 Closeout Submittals - SD-11 2 1 wks wk after complete

FA5004-15-B-C004

EIELSON AFB, ALASKA

ATTACHMENT JA-6

AF FORM 66

submittal list