FA4877-19-Q-0391_Questions_and_Answers.docx
DOCX document 14 KB Posted
- Attached to
- Maintenance Shelters/Tents Federal contract opportunity
- Solicitation number
- FA487719Q0391
About this file
Questions and Answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Provisions_and_Clauses.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4877-19-Q-0391 Questions
1. Is the shelter fabric required to be certified to MIL-PRF-44103D? YES
2. Is the shelter required to include a 3rd party test report verifying it meets a blowing rain load of 5 inches per hour with 40 MPH wind? YES Do you require the quote to include a 3rd party test report to verify that rain load? YES
3. Is the shelter required to include a 3rd party test report verifying it meets a sustained wind load of 65 MPH with 85 MPH gusts? YES Do you require the quote to include a 3rd party test report to verify that wind/gust load? YES
4. Is the entire shelter frame required to be powder coated for corrosion resistance? YES
5. Are the shelters required to include a 5-year non-prorated warranty? The Government will accept the commercially standard warranty
6. Environmental Control Units (ECUs) include many different features that are important to the proper operation of the units, including:
a. An Operational Temperature Range of -25F to +132F (with certified test report demonstrating this Operational Temperature Range);
b. (1) 27’ long, 60A power cable with MIL-C-22992 Class L connector;
c. (1) Scroll compressor;
d. (1) Hot-gas by-pass valve;
e. (1) Micro channel condenser coil with corrosion resistant coating;
f. (1) Power relay that monitors correct phasing, loss of phase low voltage and high voltage;
g. (4) Sets of forklift pockets, 1 per each side of cabinet;
h. (4) Removable legs that are at least 4” high; and
i. The capability to be stacked four (4) high without the use of wood crates or pallets.
Are the ECUs required to include all of these features? YES
7. Are the ECUs required to include a 5-year non-prorated warranty? The Government will accept the commercially standard warranty
8. Is the EnerLayer® system required to be mold and mildew resistant and successfully tested to ASTM E2149-10 and AATCC 30, Test III? YES Do you require the quote to include a test report to verify compliance? YES
9. Is the maximum allowable weight of the EnerLayer® system 330 lbs.? YES
10. Is the EnerLayer® system required to include a 5 year non-prorated warranty? The Government will accept the commercially standard warranty
11. Is the EnerLayer system required to have been tested to provide a 30% reduction in heat load needed to maintain 70ºF interior temperature at -25ºF ambient temperature? YES If so, please confirm that offers are required to include a copy of a test report showing compliance with this requirement. YES
12. Is the EnerLayer system required to have been tested to provide a 17% reduction in cooling load needed to maintain 70ºF interior temperature at +125ºF ambient temperature? YES If so, please confirm that offers are required to include a copy of the test report showing compliance with this requirement. YES