Q&A_MFR.pdf

PDF 184 KB Posted

Attached to
Wastewater Piping Federal contract opportunity
Solicitation number
FA4819-18-Q-7003
Issued by
Department of the Air Force Air Combat Command

About this file

Responses to questions asked during the 21 Feb 18 site visit.

View the file

Other files for this federal contract opportunity

Other files attached to Wastewater Piping, newest first.
File Type Posted
FA4819-18-Q-7003-0001.pdf PDF
Attachment_3_Pricing_Schedule.PDF PDF
Attachment_4_Wage_Determination.pdf PDF
Attachment_1_Statement_of_Work_(SOW).pdf PDF
Attachment_2_SOW_Appendix_A.pdf PDF
FA4819-18-Q-7003.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE325TH FIGHTER WING (ACC)

TYNDALL AIR FORCE BASE FLORIDA

26 February 2018

MEMORANDUM FOR RECORD

SUBJECT: FA4819-17-Q-7003, DFAC Wastewater Piping, Q&A Posting

1. A site visit was held on 21 February 2018 at 0900 to discuss the statement of work (SOW) and assess the projected work for Tyndall project XLWU 18-1012.

2. The SOW includes the following the following works to be discussed: Repairing the wasterwater system, security requirements, permits, mobilization, demolition and construction.

3. During the course of the site visit there were some questions raised about the nature of the work to be conducted at the DFAC. Among these questions raised were the following:

1. Q: Would weekend work requests or extended hours be available? A: Weekend work request will be available upon request if given proper notification (see SOW) and extended hours of 0600-1800 will also be available if requested.

2. Q: Would a floor sink be acceptable?

A: A contractor may propose a floor sink at the above location as long as it meets the requirements listed in the SOW.

3. Q: What is the cleanliness expectation for work completion?

A: The expectation is for the area to be as clean as found or better.

4. Q: After equipment is removed, will the remaining non-removalbe items, ie. fire sprinkler heads, need to be protected?

A: Yes, all leftover area should be protected from any potential damage.

5. Q: When will the access badge process need to be completed?

A: Immediately upon award the contractor will need to submit paperwork to ensure timelines are met.

6. Q: Will there be a pre-construction meeting? A: Yes, shortly after the Notice-to- Proceed (NTP)

7. Q: Is a Bid Bond required?

A: No, see SOW

8. Q: What is the timeline for this project after award?

A: After award, there will be three weeks for the government to remove equipment for the work area. During this time, the dining facility will be shut down and waiting for awardee to gain base access, receive NTP, and mobilize to begin construction.

4. All eight (8) questions will be posted as a Q&A document to the RFQ posting.

5. The site visit ended at 1000.

JEFFREY S. MORRIS, USAF, MSgt Contract Specialist

2018-02-26T10:50:58-0600
MORRIS.JEFFREY.SCOTT.1110718663