Attachment_3_Pricing_Schedule.PDF

PDF 274 KB Posted

Attached to
Wastewater Piping Federal contract opportunity
Solicitation number
FA4819-18-Q-7003
Issued by
Department of the Air Force Air Combat Command

About this file

Pricing Schedule

View the file

Other files for this federal contract opportunity

Other files attached to Wastewater Piping, newest first.
File Type Posted
Q&A_MFR.pdf PDF
FA4819-18-Q-7003-0001.pdf PDF
Attachment_2_SOW_Appendix_A.pdf PDF
FA4819-18-Q-7003.pdf PDF
Attachment_4_Wage_Determination.pdf PDF
Attachment_1_Statement_of_Work_(SOW).pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

325TH FIGHTER WING (ACC)

TYNDALL AIR FORCE BASE FLORIDA

XLWU 18-1012

REPAIR WASTEWATER PIPING, B1690 DFAC

SOW APPENDIX B:

PRICING SCHEDULE

PRICING SCHEDULE XLWU 18-1012 - Repair Wastewater Piping, B1690

1/26/2018

Note: Provide additional pages as needed Pricing Schedule

SUB TOT POP Construction (Base) 60 Days

LINE ITEM UNIT QUANTITY UNIT COST TOTAL Notes

001 Professional Services / Permitting JOB -$

002 Material Testing JOB -$

003 -$

004 -$

SUB TOT

LINE ITEM UNIT QUANTITY UNIT COST TOTAL Notes

001 Mobilization/Demobilization JOB -$

002 Equipment Rental MONTH -$

003 Super Intendence DAY -$

004 -$

005 -$

006 -$

007 -$

SUB TOT

LINE ITEM UNIT QUANTITY UNIT COST TOTAL Notes

001 Tile SF -$

002 Concrete SF -$

003 Walls CY -$

004 Excavate Soils CY -$

005 Wastewater System LF -$

006 Demolition & Waste Disposal CY -$

007 -$

008 -$

009 -$

010 -$

2.3.1 (b.) AND 2.3.1 (c.) GENERAL CONDITIONS

DESCRIPTION

A mobilization cost will be given in order to get the contractor set up on Tyndall AFB. This shall include, but may not be limited to the fees associated in moving equipment, material, and personnel to this area.

2.3.1 TASK 1

2.3.1 (a.) PROFESSIONAL SERVICES

DESCRIPTION

Line item shall account for all costs associated with any required permitting & professional services necessary to complete the contracted work.

Line item shall account for all costs associated with the 3rd party material testing services required by the contract documents.

All costs associated with removal of remaining wall materials to expose wastewater elements defined in the Contract Documents.

All costs associated with removal of sub-slab soil and materials to expose wastewater system defined in the Contract Documents.

All costs associated with legal disposal of demolition/construction material off site.

All costs associated with equipment rental to accomplish the work. Contractor to provide itemized list of equipment and associated cost.

All costs associated with removal of the wastewater system defined in the Contract Documents.

All costs associated with providing oversite during the performance of on site activities; layout, demolition, construction.

2.3.1 (b.) DEMOLITION

DESCRIPTION

All costs associated with removal of the floor and wall tile in the trenching area of work.

All costs associated with sawcutting and removal of the concrete slab & walls to permit access for repair as defined in the Contract Documents.

1/26/2018

Note: Provide additional pages as needed Pricing Schedule

SUB TOT

LINE ITEM UNIT QUANTITY UNIT COST TOTAL Notes

001 Wastewater Pipe LF -$

002 Drains EA -$

003 Cleanouts EA -$

004 Vent Stack Tie-Ins EA -$

005 Back Fill Excavation CY -$

006 Concrete CY -$

007 Walls, Floors, Tile SF -$

008 Final Clean Up EA -$

009 -$

010 -$

011 -$

012 -$

SUB TOT

LINE ITEM % TOTAL Notes

001 Overhead -$

002 Profit -$

003 Bond -$

PROJECT SUBTOTAL =

2.3.1 OVERHEAD, PROFIT, BOND

DESCRIPTION

Overhead Costs

Profit

Actual Bond

PROJECT TOTAL ESTIMATE =

2.3.1 (c.) CONSTRUCTION

DESCRIPTION

All costs associated with providing and installing new wastewater system pipe as defined in the Contract Documents. Line item shall include items such as: DWV PVC S40 pipe, connection hardware, joints, reducers , and other components within the repair areas.

All costs associated with providing and installing new clean-outs as defined in the Contract Documents.

All costs associated with providing and installing new Tie-In harware as defined in the Contract Documents.

All costs associated with backfilling, compaction, and restoration of the capillary water barrier as defined in the Contract Documents.

All costs associated with installing new reinforced concrete slab in the repair area as defined in the Contract Documents.

Line item shall inclued any other masonry related items such as patching.

All costs associated with restoring the walls and floors as defined in the Contract Documents. Line item shall include patching, finishing, base and tile as needed for restoration.

All costs associated with final clean up efforts to restore the facility to pre-construction clean conditions.

All costs associated with providing and installing new drains and floor sinks, and traps as defined in the Contract Documents.

1/22/2018

Note: Provide additional pages as needed Pricing Schedule

2.3.1 EQUIPMENT RENTAL ( ITEMIZED LIST )

UNIT QUANTITY QUANTITY UNIT COST TOTAL

ex. MONTH 1 1 2,180.00 2,180.00$

1 -$

2 -$

3 -$

4 -$

5 -$

6 -$

7 -$

8 -$

9 -$

10 -$

11 -$

12 -$

13 -$

14 -$

15 -$

16 -$

17 -$

18 -$

19 -$

20 -$

OTHER PROJECT NOTES FOR BID

UNIT QUANTITY QUANTITY UNIT COST TOTAL

ex. MONTH 1 1 2,180.00 2,180.00$

1 -$

2 -$

3 -$

4 -$

5 -$

6 -$

7 -$

8 -$

9 -$

10 -$

11 -$

12 -$

13 -$

14 -$

15 -$

16 -$

17 -$

18 -$

19 -$

20 -$

SUB TOT

DESCRIPTION

(Example) 40' Straight Boom Manlift (Sunbelt Rentals)

2.3.1 TASK 1 - EAST & WEST WALLS

SUB TOT

RENTAL DESCRIPTION

(Example) 40' Straight Boom Manlift (Sunbelt Rentals)

BID SCHED TASK 1 E&W Walls
BID SCHED TASK 2 Stair
BID SCHED TASK 3 F&R Fascia
BID SCHED TASK 4 F&R Veneer
BID.pdf
BID SCHED TASK 1 E&W Walls
T1
BID SCHED TASK 2 Stair
T2
BID SCHED TASK 3 F&R Fascia
T3
BID SCHED TASK 4 F&R Veneer
T4
Bid1.pdf
BID T1
T1
Pricing.pdf
BID T1
T1
BID T2
T2
BID T3
T3
BID T4
T4
BID T5
T5
BID T6
T6
BID T7
T7
PRICING.pdf
BID T1
T1
PRICING.pdf
BID T1
T1

File details come from the government source that posted it.