Cost Estimate Worksheet

View the file

Other files for this federal contract opportunity

Other files attached to Construct Additional Parking near Bldg 1627, newest first.
File Type Posted
FA4803-18-B-0008-P00001_Corrections_to_Solicitation.pdf PDF
FA480318B0008_Parking1627_rel.pdf PDF
Attch3_DD1354_draft.pdf PDF
Attch1_SOW_180702.pdf PDF
Attch6_Base_Pass_Request.pdf PDF
Attch5_WDSC180054_180105.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Roof Repair, B710

Project: CONSTR Additional Parking near B1627Project Engineer: Matt Wenger
Location: B1601, B1604, B1605, B1606 and B1627Department: CEOER
Contractor: TBD
Address: Shaw AFB, SC
PR No.: VLSB 18-0042
For Official Use Only
Line No.ItemUnit of MeasureQuantityMaterial CostsLabor CostsDirect CostLine Total
Unit CostTotalLabor Hours per UnitLabor-HoursAvg. Rate ($/hr)Total
Additional Parking near B1627
1Sidewalk demoSY$0.00
2Dumpster rental / dump feeEA$0.00
3Clearing and grubbingAC$0.00
4Storm systemLF$0.00
5subgrade prepSF$0.00
6Base prepSY$0.00
7AsphaltTON$0.00
8Overhead lightingEA$0.00
9Lighting utilityLF$0.00
10Curb and gutterLF$0.00
11Parking lot - stripingStall$0.00
12General conditions / supervisionWK$0.00
$0.00$0.00$0.00$0.00
Base Bid
Total Material Cost:$0.00
Total Labor Cost:$0.00
Direct Cost:$0.00
Total Line Item Cost:$0.00
Overhead:$0.00
Subtotal:$0.00$0.00
Profit:$0.00
Subtotal:$0.00
Bond:$0.00
Total Contract Price:$0.00

Roof Repair, B710 (2)

Project: Repair Roof, Operations Group B710Project Engineer: Shep Sublette
Location: Shaw AFBDepartment: CEOER
Contractor:
Address:
PR No.: VLSB 14-0011
For Official Use Only
Line No.ItemUnit of MeasureQuantityMaterial CostsLabor CostsDirect CostLine Total
Unit CostTotalLabor Hours per UnitLabor-HoursAvg. Rate ($/hr)Total
BUILDING 0710
1Demo roof materialSF21,124$0.000.061605$32.30$51,841.50$51,841.50
2Abate ACMSF1,500$0.05$75.000.0690$32.30$2,907.00$2,982.00
3Install Standing Seam Metal RoofSF21,124$8.60$181,666.400.367605$32.30$245,629.87$427,296.27
4Install R-30 InsulationSF21,124$2.70$57,034.800.03634$32.30$20,469.16$77,503.96
5Site CleanupEA1240$25.00$6,000.00$6,000.00
6SupervisionEA11000$55.00$55,000.00$55,000.00
$238,776.20$381,847.53$0.00$620,623.73
Base Bid
Total Material Cost:$238,776.20
Total Labor Cost:$381,847.53
Direct Cost:$0.00
Total Line Item Cost:$620,623.73
Overhead:10%$62,062.37
Subtotal:$0.00$682,686.10
Profit:10%$68,268.61
Subtotal:$750,954.71
Bond:2%$15,019.09
Total Contract Price:$765,973.81