Amd_0004_Q As_22May13.doc
DOC document 41 KB Posted
- Attached to
- Waste Water Treatment Plant Services Federal contract opportunity
- Solicitation number
- FA4801-13-R-0005
About this file
The purpose of this amendment is to post additional answers to questions received on 20 21 May 13 which does not affect pricing.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| WWTP_Conformed_thru_P00042.doc | DOC document | |
| Atch_1_WWTP_PWS_wAppendices_16_Jan_13_(2).doc | DOC document | |
| FA4801-13-R-0005_Amd_0003.doc | DOC document | |
| Signed_Site_Visit_Minutes_2_May_13.pdf | ||
| WWTP_Ktr_Q As_14May13.doc | DOC document | |
| Amd_0002_Update_FAR_clauses.doc | DOC document | |
| Amd_0001 _Response_Date_for_Q's.doc | DOC document | |
| Atch_3 _4-pg_Base_access....pdf | ||
| Atch_2 _WD_05-2511_Rev_16_06-13-2012.doc | DOC document | |
| Atch_4 _Special_Event_Request_1_July_2012_for_SV.docx | DOCX document | |
| WWTP_Sol_SF1449_Released.doc | DOC document |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
CONTINUATION OF BLOCK 14
FA4801-13-R-0005 WWTP Additional Questions and Answers
Project Solutions, Inc.
Q. 1. If there is a dispute between the Federal Environmental Protection Agency (EPA) and the New Mexico Environmental Department (NMED), will that affect the new contractor and operations at the plant?
A. If a dispute arises between the EPA and NMED this would be a contractual issue that can be resolved on a case-by-case basis. Historically, there has been no disputes between EPA and NMED. As indicated in the Performance Work Statement, paragraph 4.11.2, "In the event environmental laws/regulations change during the term of this contract, the contractor is required to comply as such laws/regulations come into effect. If there is an increase or decrease in cost as a result of the change, the contractor shall inform the CO pursuant to requirements of FAR 52.212-4(c) and negotiate a modification to the contract." The contractor shall abide by the current NPDES permit until a new one is issued.
Q. 2. Chlorine and sulfur dioxide amounts seemed very low for the size of this operation and for year-long chlorination.
A. The plant uses approximately 10 pounds per day (300 pounds per year) of chlorine and sulfur dioxide historically as reported to the NMED and EPA.
National O&M, Inc.
Q. 1. The reported annual chemical usage for chlorine gas and sulfur dioxide is low by a factor of 10 times. Please confirm annual usage.
A. The plant uses approximately 10 pounds per day (300 pounds per year) of chlorine and sulfur dioxide historically as reported to the NMED and EPA.
End Continuation of Block 14