Attach_1_-_Specifications.pdf
PDF 115 KB Posted
- Attached to
- RED HORSE BOM Federal contract opportunity
- Solicitation number
- FA4661-18-Q-0007
About this file
Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 1._FA4661-18-Q-0007_-_Combo.docx | DOCX document | |
| Attach_3_-_Flexible_Base_Requirements.pdf | ||
| Attach_2_-_Breakout_Sheet.xlsm | XLSM spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MATERIAL PROCUREMENT STATEMENT OF WORK
Construct MSA Assembly Pad Dyess AFB, TX
Project Number: FNWZ050034
GENERAL REQUIREMENTS
1.00 General Scope
The material provider shall furnish all materials listed in the attached bill of materials and meeting listed specifications, necessary for the accomplishment of the project entitled “Construct MSA Assembly Pad”, Project No. FNWZ050034. The government’s POCs are Capt Justin Eshleman: 815-871-4163 or TSgt Chris Quintanilla: 406-403-5735. All deliveries specified above will be delivered to the following address: Cross Rd., Bldg 9119, Dyess AFB, TX 79607. Drivers must contact the government POC a minimum 1 hour prior to delivery.
1.01 Material Description
1.01.1 Notification of date and time of delivery/cancellation will be made as early as possible for all materials. A minimum of 24 hours prior to the required delivery date, a POC from the 819 RED HORSE squadron will contact the provider to coordinate the required quantities and date/time of deliveries.
1.01.1.1 Deliveries will be made to a secured location within the base, requiring escorts which will be provided by the base.
1.01.1.2 Deliveries must be able to support night operations with deliveries from 0400- 2200, Monday through Saturday.
1.01.2 Flexible Base Specifications (See Flexible Base Requirements Doc.):
1.01.2.1 The contractor will be required to provide a total of 15800 tons of base course material.
1.01.2.2 Flexible Base will be required; Grade 1 or a mix of Grade 1 and
Grade 2 with no more than 50% Grade 2 as specified in TxDOT S2471, Item 247. Please see attached specifications.
1.01.2.3 The contractor must provide gradation, plasticity, and proctor value for the material delivered.
1.01.2.4 Material delivery will start to the site on 1 Jan 18 and must be complete within fourteen (14) calendar days.
1.01.3 Concrete Specifications:
1.01.3.1 The contractor will be required to provide a total of 1250 CY of concrete.
1.01.3.2 Concrete shall have a minimum of 5,000 PSI compressive strength as determined by the 28 day compressive strength test.
1.01.3.3 Concrete shall have a minimum flexural strength of 650 PSI.
1.01.3.4 Polypropylene synthetic fiber with a denier less than 100 and a nominal fiber length of 50 mm 2 inches will be added to the concrete for added resistance to plastic shrinkage cracking.
Fibermesh 150 synthetic fiber (or equivalent – with approval) will be added at a rate of 1.5 lbs per cubic yard. Please see the attached data sheet for Fibermesh 150.
1.01.3.5 Water to cement ratio shall not exceed .45 at point of delivery.
1.01.3.6 Corrected air content shall be between 3.0% and 4.0% at point of delivery.
1.01.3.7 Tested slump shall be between 3 to 5 inches with a target of 4 inches at point of delivery.
1.01.3.8 Delivery will be specified at time of contract.
1.01.3.9 Delivery will be coordinated for 21 separate pours over an approximately 30 days.
1.01.3.10 The contractor must be able to provide 135 CY per day with the ability to support up to 270 CY a day.
1.01.3.11 Contractor will coordinate to ensure there is one truck on the job site at all times during active pours with one 10 yard truck every 15-30 minutes.
1.01.3.12 Non-Conforming Materials: Factors that indicate that there are non-conforming materials include (but not limited to) excessive compressive strength, inadequate compressive strength, excessive slump, concrete delivery records that indicate excessive time between mixing and placement, or excessive water was added to the mixture during delivery and placement. Any of these indicators alone are sufficient reason for the Contracting Officer to request additional sampling and testing. Investigations into non-conforming materials must be conducted at the Contractor's expense. The Contractor must be responsible for the investigation and must make written recommendations to adequately mitigate or remediate the non-conforming material. The Contracting Officer may accept, accept with reduced payment, require mitigation, or require removal and replacement of non-conforming material at no additional cost to the Government.