Airfield site visit.pptx
PPTX presentation 848 KB Posted
- Attached to
- Dyess Airfield Pavements Requirement Federal contract opportunity
- Solicitation number
- FA4661-12-R-0010
About this file
Pre-Proposal Site Visit PowerPoint Slides 21 March 2012
View the file
Other files for this federal contract opportunity
Show all 23
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Airfield Pavements Pre-Proposal Site Visit
Welcome to Dyess AFB
PLEASE SIGN IN
Airfield Pavements Requirement
Pre-Proposal Site Visit 21 March 2012
Overview Sign-in Introductions Airfield Overview Site Visit
Introductions Lt. Col John Del Barrio –7 CONS/Commander Mr. Ronald Miller – Director of Business Operations & Contracting Officer Mr. Anthony Rogiano – Team Leader Mr. Barry Mines – Chief, Technical Support Mr. John Ford – Project Engineer Mr. Steve Verette – Inspector TSgt DeMuro – Airfield OPS
Current Airfield Facts Awarded Dollars: $12,000,000
Award Actions:
Awarded in 2009 (two option years) 14 Task Orders Fills Airfield Pavements Requirements
Airfield Projects
New Airfield Solicitation # FA4661-12-R-0010
Indefinite Delivery-Requirements Contract Competition restricted to Total Small Business One award from the aforementioned set-aside
NAICS Code 237310
Contract performance is one base period plus two 12 month option periods
No minimum, max is $35,000,000
Notice to Proceed issued / performance period stated in each task order
Proposals Proposals due NLT 9 April 2012, 2 PM CST
Faxed or electronic proposals are NOT authorized and will not be accepted
Use delivery confirmation or hand carry to 7 CONS/LGCA (Clarion Miller)
Registration in the Central Contractor Registration (CCR) database is mandatory
Evaluation Lowest Price Technically Acceptable; evaluated factors to obtain “Best Value” will be past performance, technical, and price
Technical: “Acceptable or Unacceptable” based on factors in Section M of solicitation
Past Performance: “Acceptable or Unacceptable” based on factors in Section M of solicitation
Price: Will be the final evaluation factor if contractor is determined to be “acceptable” for Technical and Past Performance
Questions
All questions must be submitted to the 7 CONS no later than 26 March 2012 @ 2:00 PM, CST
Specify page, section and paragraph number
Late inquiries/questions will NOT be accepted
Answers to the questions will be posted in FBO on or about 30 March 2012
NO PICTURES ON THE FLIGHTLINE