Submittals
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Response_to_Questions__1.pdf | ||
| RHS_Snow_Barn.pdf | ||
| 100__DESIGN_MALMSTROM_AFB_SNOW_BARN.pdf | ||
| Clarification.docx | DOCX document | |
| Attach_6_Drawings.pdf | ||
| Attach_1_Specifications.pdf | ||
| Attach_5_Schedule_of_Drawings.pdf | ||
| Attach_2_Wage_Determination.docx | DOCX document | |
| Attach_3_Base_Entry.pdf | ||
| FA4626-16-T-0005.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| SCHEDULE OF MATERIALS SUBMITTALS | Project Number | Project Title: | Solicitation/Contract No. | ||||||||||||||||||
| NZAS 02-14041 | Snow Barn Fire Protection | FA4626-16-T-0005 | |||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACTOR/ADMINISTRATOR | ||||||||||||||||||||
| Number of Copies Required | |||||||||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MANUFACTURER'S RECOMMENDATIONS | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | TEST REPORTS | OTHER | REQUIRED SUBMISSION DATE (BY CONTRACTOR) | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | |
| APPROVED | DIS- APPROVED | ||||||||||||||||||||
| DIVISION 01 - GENERAL REQUIREMENTS | |||||||||||||||||||||
| 1 | 01 00 00 General Requirements - 3.5 B. As-Built Field Data | 2 | 3d - PFI | ||||||||||||||||||
| 2 | 01 00 00 General Requirements - 3.5 F. As-Built Field Data | 1 | 30 d - AFI | AutoCAD CD | |||||||||||||||||
| 3 | 01 00 00 General Requirements - 3.7 A. O&M Instructions | 1 | 2 | 1d - ATT | 1 hardcopy, 2 CD's - see individual sections as well | ||||||||||||||||
| 4 | 01 00 00 General Requirements - 3.8 A. Contractor Furnished Equipment Data | 10d - BD | Equipment List & Guarantees | ||||||||||||||||||
| 5 | 01 00 00 General Requirements - 3.11 A. Start of Work notification | X | 5 d - PTE | ||||||||||||||||||
| 6 | 01 00 00 General Requirements - 3.12 A. Notice of Pre-Final and Final Inspections | X | 14d - PTE | Red line “As-Built” dwgs shall be provided by the Contractor at final inspection. | |||||||||||||||||
| 7 | 01 00 00 General Requirements - 3.14 A. Utility Outages | X | 14 d - PSW | ||||||||||||||||||
| 8 | 01 00 00 General Requirements - 3.18 B. QC Submittals | 3 | 10d - ANP | Quality Control Plan | |||||||||||||||||
| 9 | 01 00 00 General Requirements - 3.20 A. 1354 checklist | 1 | 10d - PFI | Checklist to be delivered to the contractor at Pre-Construction conference | |||||||||||||||||
| 10 | 01 00 10 Security - 1.1 A. Identification of Employees | 14d - PSW | EAL | ||||||||||||||||||
| 11 | 01 36 00 2.3 Environmental Permits | X | 5d - PSW | ||||||||||||||||||
| DIVISION 21 - FIRE SUPPRESSION | |||||||||||||||||||||
| 12 | 21 13 13 Wet Pipe Sprinkler System - 1.4A Submittal Data | 3 | 3 | 15 d ANP | |||||||||||||||||
| 13 | DIVISION 28 - ELECTRONIC SAFETY AND SECURITY | ||||||||||||||||||||
| 14 | 28 31 76 - Interior Addressable Fire Alarm System - 1.4 A/B Submittals (substitute products) | 3 | 3 | 20d - PSW | |||||||||||||||||
| 15 | 28 31 76 - Interior Addressable Fire Alarm System - 1.4C | 4 | 20d - PSW | ||||||||||||||||||
| 16 | 28 31 76 - Interior Addressable Fire Alarm System - 1.4D | 3 | 20d - PSW | List of address names and descriptions | |||||||||||||||||
| 17 | 28 31 76 - Interior Addressable Fire Alarm System - 1.4F Record Drawings and O&Ms | 3 | 20d - PSW | ||||||||||||||||||
| 18 | 28 31 76 - Interior Addressable Fire Alarm System - 1.4G | 3 | 14d - PSW | NICET Technician Certificates, Contractor and Instllater State licenses | |||||||||||||||||
| 19 | 28 31 76 - Interior Addressable Fire Alarm System - 1.4I | 3 | 14d - PSW | Manufacturer's certification/contractor authorization | |||||||||||||||||
| 20 | 28 31 76 - Interior Addressable Fire Alarm System - 1.4J | 3 | 3 | 7d - PT | Red line As-Builts, System Device address list, Prelim Test Reports | ||||||||||||||||
| 21 | 28 31 76 - Interior Addressable Fire Alarm System - 1.4K | 3 | 3 | 3 | 7d - AFI | Spare Parts list, O&M manuals, Completed Gov trng, Warranty letter | |||||||||||||||
| D - Days | PSW - Prior to Start Work | PFI - Prior to Final Inspection | |||||||||||||||||||
| AFI - After Final Inspection | BBCW - Before Beginning Concrete Work | PPC - Prior to Project Completion | |||||||||||||||||||
| ANP - After Notice to Proceed | BD - Before Delivery | PT - Prior to Testing | |||||||||||||||||||
| ATT - After Test is Taken | PBC - Prior to Beginning Construction | PTW - Prior to Event | |||||||||||||||||||
| PRI - Prior to Final Inspection | SRO - After Each Occurrence |