Header_Repair.doc

DOC document 26 KB Posted

Attached to
Remove, Manufacure and Replace two header water pipe Federal contract opportunity
Solicitation number
FA4626-16-Q-0013
Issued by
Department of the Air Force Global Strike Command

About this file

Updated Statement of Work

View the file

Other files for this federal contract opportunity

Other files attached to Remove, Manufacure and Replace two header water pipe, newest first.
File Type Posted
Q__A.docx DOCX document
Circulation_Pump_Header.pptx PPTX presentation
Q_ _A.docx DOCX document
COMBO.docx DOCX document
Distribution_Pump_Header.pptx PPTX presentation
SOW.pdf PDF
COMBO.docx DOCX document
WD.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Distribution Header Repair

GENERAL

1.1 SUMMARY OF WORK:

1.1.1 The contractor shall provide all labor, equipment and materials to replace 2 header sections of the 16” High Temperature Hot Water distribution pipe. The pipe headers consist of (9) 10”, (2) 12”, (2) 3” and (1) 6” pipe branches; (7) 16” x 10” tees (2) 16” x 12” tees; (2) 10” , (2) 3”, and (1) 6” weld o-lets; (2) ½” and (1) ¾” thread o-lets; (2) 2” weld o-lets with pipe drain and (4) 2” gate valves

1.1.2 Contractor shall replace pipe hangers as needed

1.1.3 Contractor shall insulate all piping with non-asbestos insulation.

1.1.4 Contractor shall dispose of all materials removed during repair.

1.1.5 Contractor shall provide all documentation and inspections required by State and Federal requirements.

1.2 Specifications:

Process:

High Temperature Hot Water

Temperature:

500 Degrees F.

Pressure:

500 PSI

Material:

Black Iron Schedule 40 (1/2” wall thickness)

Size:

16” pipe headers

1.3 Execution:

1.3.1 Remove and dispose of all piping, insulation and materials being replaced

1.3.2 Manufacture (2) 16” pipe headers with (9) 10”, (2) 12”, (2) 3” and (1) 6” pipe branches; (7) 16” x 10” and (2) 16” x 12” tees; (2) 10” , (2) 3”, and (1) 6” weld o-lets; (2) ½” and (1) ¾” thread o-lets; (2) 2” weld o-lets with pipe drain and (4) 2” gate valves

1.3.3 Install replacement headers to meet all State and Federal requirements

1.3.4 Insulate all piping with non-asbestos insulation

1.3.5 Hydrostatic test and file all required documentation for repair required by Federal and State requirements

1.4 Government Support:

1.4.1 The government will be responsible for removal of all auxiliary equipment that would impede the execution of the contract. Testing requirements will be assisted by the government.

1.5 Period of Performance

1.5.1 Period of performance will be between June- August of Central Heating Plant maintenance overhaul.