Attch 2 Submittal Schedule.xls

XLS spreadsheet 55 KB Posted

Attached to
MAF Security Office Renovations Federal contract opportunity
Solicitation number
FA4626-10-R-0016
Issued by
Department of the Air Force Global Strike Command

About this file

Attachment 2 (Material Submittal)

View the file

Other files for this federal contract opportunity

Other files attached to MAF Security Office Renovations, newest first.
File Type Posted
Site Visit List.pdf PDF
10-R-0016-AMD.zip ZIP file
Attch 3 Schedule of Drawings.pdf PDF
Attch 4 Drawings.zip ZIP file
Attch 1 Specifications.zip ZIP file
Attch 5 Wage determination MT5.docx DOCX document
Attch 5 Wage determination MT6.docx DOCX document
Attch 5 Wage determination MT3.docx DOCX document
Attch 6 Past Performance Survey.docx DOCX document
Attch 7 - Subcontractor Consent Form - 10R0027.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

SCHEDULE OF MATERIALS SUBMITTALSProject NumberProject Title:Solicitation/Contract No.
NZAS 09-2001Missile Alert Facility Security Office RenovationFA4626-10-R-0016
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACTOR/ADMINISTRATOR
Number of Copies Required
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIFICATION OF COMPLIANCESHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACTURER'S RECOMMENDATIONSMANUFACTURER'S WARRANTYCATALOG DATAOPERATING INSTRUCTIONSNOTIFICATIONOTHERREQUIRED SUBMISSION DATE (BY CONTRACTOR)DATE RECEIVED IN CONTRACTINGDATE TO MISSILE ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
APPROVEDDIS- APPROVED
ARCHITECTURAL SUBMITTALS
1SPECIAL PROCEDURES - 01 00 00 1.6.B / 3.14 (Quality Control Plan)410 days ANTP
2SPECIAL PROCEDURES - 01 00 00 3.3.A (Schedule of Materials Submittal)410 days ANTP
3SPECIAL PROCEDURES - 01 00 00 3.7.B (Construction Schedule)410 days ANTP
4SPECIAL PROCEDURES - 01 00 00 3.9.A (Work Notification)4Tues PTSW
5SPECIAL PROCEDURES - 01 00 00 3.17 (As-Built Field Drawings)4EWD
6SPECIAL PROCEDURES - 01 00 00 3.19.C (Storage Area Request)4Precon Conf
7SPECIAL PROCEDURES - 01 00 00 3.22.A (Work Clearance Request)4PTSW
8SPECIAL PROCEDURES - 01 00 00 3.27 (Temporary Security Office Trailer)4PT placing
9SPECIAL PROCEDURES - 01 00 00 3.30 (Pre-Final Inspection Request)4PTFI
10SPECIAL PROCEDURES - 01 00 00 Pg. 20-21 (Systems Checklist)4PTFI
11SPECIAL PROCEDURES - 01 00 00 End of Section (Materials Approval Submittal)4PSS
12MAF SECURITY - 01 10 01 3.1.A (EAL Data List)420 days PTSW
13ENVIRONMENTAL PROCEDURES - 01 10 05 3.6.A (AF Form 3952 - Chemical/Hazardous Material Request / Authorization)4ACA
14ENVIRONMENTAL PROCEDURES - 01 10 05 3.7.A (EPCRA Section 313 Form R - List of Hazardous Substances)4ACA
15ENVIRONMENTAL PROCEDURES - 01 10 05 3.9 (Hazardous Waste Manifest)445 days SRO
16ENVIRONMENTAL PROCEDURES - 01 10 05 3.10.E (Solid Waste Disposal Documents)420 days SRO
17ENVIRONMENTAL PROCEDURES - 01 10 05 3.10.F (Non-Hazardous Solid Waste Diversion Report)410 days PTFA
18ENVIRONMENTAL PROCEDURES - 01 10 05 Pg 13 (Waste Management Plan)4PTSW
19MINOR DEMOLITION FOR REMODELING - 02 41 19 1.2B (Demolition Schedule)420 days ANTP
20MINOR DEMOLITION FOR REMODELING - 02 41 19 1.2C4PTSW
21MINOR DEMOLITION FOR REMODELING - 02 41 19 1.3B (Project Record Documents)4AFI
22METAL FABRICATIONS - 05 50 00 1.3B420 days AFI
23FINISH CARPENTRY - 06 20 00 1.3B420 days AFI
24ARCHITECTURAL WOOD CASEWORK - 06 41 00 1.3B420 days AFI
25ARCHITECTURAL WOOD CASEWORK - 06 41 00 1.3C420 days AFI
26SOLID SURFACING FABRICATIONS - 06 61 16 1.3B420 days AFI
27SOLID SURFACING FABRICATIONS - 06 61 16 1.3C420 days AFI
28SOLID SURFACING FABRICATIONS - 06 61 16 1.4B4At FI
29FOAMED-IN-PLACE INSULATION - 07 21 19 1.3B420 days PTSW
30FOAMED-IN-PLACE INSULATION - 07 21 19 1.3C4PTSW
31FOAMED-IN-PLACE INSULATION - 07 21 19 1.3D420 days PTSW
32BULLET RESISTANT PANELS - 07 42 45 1.4B430 days PTSW
33BULLET RESISTANT PANELS - 07 42 45 1.4C (Test Reports)430 days PTSW
34BULLET RESISTANT PANELS - 07 42 45 1.4D210 days PTSW
35BULLET RESISTANT PANELS - 07 42 45 1.4E4PTSW
36BULLET RESISTANT PANELS - 07 42 45 1.4F430 days PTSW
37JOINT SEALERS - 07 90 00 - 1.3B420 days PTSW
38JOINT SEALERS - 07 90 00 - 1.3C4PTSW
39JOINT SEALERS - 07 90 00 - 1.3D4PTSW
40STANDARD STEEL FRAMES - 08 12 14 1.3B420 day AFI
41STANDARD STEEL FRAMES - 08 12 14 1.3C420 days PTSW
42STANDARD STEEL FRAMES - 08 12 14 1.3D4PTSW
43STANDARD STEEL FRAMES - 08 12 14 1.3E420 days PTSW
44FLUSH WOOD DOORS - 08 14 16 1.3B420 days AFI
45FLUSH WOOD DOORS - 08 14 16 1.3C420 days PTSW
46FLUSH WOOD DOORS - 08 14 16 1.3C1210 days PTSW
47FLUSH WOOD DOORS - 08 14 16 1.3D4PTSW
48FLUSH WOOD DOORS - 08 14 16 1.3E420 days PTSW
49DOOR HARDWARE - 08 71 00 1.4B420 days AFI
50DOOR HARDWARE - 08 71 00 1.4C (Hardware Schedule)420 days PTSW
51DOOR HARDWARE - 08 71 00 1.4D4PTSW
52DOOR HARDWARE - 08 71 00 1.5A4At FI
53DOOR HARDWARE - 08 71 00 1.5B (Keys)4At FI
54GLAZING - 08 80 00 1.3B420 days PTSW
55GLAZING - 08 80 00 1.3C420 days PTSW
56GYPSUM BOARD ASSEMBLIES - 09 21 16 1.3B420 days PTSW
57ACOUSTICAL PANEL CEILINGS - 09 51 13 1.3B420 days AFI
58ACOUSTICAL PANEL CEILINGS - 09 51 13 1.3C420 days PTSW
59ACOUSTICAL PANEL CEILINGS - 09 51 13 1.3D210 days PTSW
60ACOUSTICAL PANEL CEILINGS - 09 51 13 1.3E210 days PTSW
61ACOUSTICAL PANEL CEILINGS - 09 51 13 1.3F4PTSW
62FLUID-APPLIED FLOORING - 09 67 00 1.3B430 days PTSW
63FLUID-APPLIED FLOORING - 09 67 00 1.3C220 days PTSW
64FLUID-APPLIED FLOORING - 09 67 00 1.3D430 days PTSW
65FLUID-APPLIED FLOORING - 09 67 00 1.3E4PTSW
66FLUID-APPLIED FLOORING - 09 67 00 1.4B4At FI
67PAINTING AND COATING - 09 90 00 1.4B420 days PTSW
68PAINTING AND COATING - 09 90 00 1.5B4At FI
69FOOD SERVICE EQUIPMENT - 11 40 00 1.3B430 days PTSW
70FOOD SERVICE EQUIPMENT - 11 40 00 1.3C430 days PTSW
71FOOD SERVICE EQUIPMENT - 11 40 00 1.4B4At FI
72MONITOR MOUNTS - 11 52 15 1.3B430 days PTSW
73MONITOR MOUNTS - 11 52 15 1.4B420 days AFI
74WINDOW SHADES - 12 21 15 1.2B420 days AFI
75WINDOW SHADES - 12 21 15 1.2C420 days PTSW
76WINDOW SHADES - 12 21 15 1.2D210 days PTSW
MECHANICAL SUBMITTALS
77Pipe materials, fittings and accessories - 22 11 00 1.3 and 22 13 00 1.3420 days PTSW
78Plumbing fixture, WC-1, including flush valve and faucet - 22 40 00 1.3420 days PTSW
79Refrigerant pipe insulation - 23 07 00 1.3420 days PTSW
80Refrigerant pipe - 23 23 00 1.4420 days PTSW
81Exhaust fan EF-1 - 23 34 00 1.3B430 days PTSW
82Heat pump EVAP-1/CU-1 23 81 43 1.4430 days PTSW
83PROJECT RECORD DRWINGS - 22 05-00 1.12420 days AFI
84OPERATION AND MAINTENANCE DATA - 22 05 00 1.13410 days PTFI
85Potable water certificate - 22 11 00 3.44AFI
ELECTRICAL SUBMITTALS
86GENERAL PROVISIONS FOR ELECTRICAL WORK 26 05 00 - 2.01A420 days PTSW
87GENERAL PROVISIONS FOR ELECTRICAL WORK 26 05 00 - 2.01A (Installation layout drawings)420 days AFI
88GENERAL PROVISIONS FOR ELECTRICAL WORK 26 05 00 - 2.01B420 days PTSW
89GENERAL PROVISIONS FOR ELECTRICAL WORK 26 05 00 - 2.02 (Project Record Documents)410 days AFI
90GROUNDING & BONDING FOR ELECTRICAL SYSTEMS 26 05 26 - 1.05B420 days PTSW
91GROUNDING & BONDING FOR ELECTRICAL SYSTEMS 26 05 26 - 1.05C (Test Reports)420 days PTSW
92GROUNDING & BONDING FOR ELECTRICAL SYSTEMS 26 05 26 - 1.05D420 days PTSW
93GROUNDING & BONDING FOR ELECTRICAL SYSTEMS 16060 - 1.06B (Project Record Documents)4EWD
94HANGERS & SUPPORTS 26 05 29 - 1.03B420 days PTSW
95HANGERS & SUPPORTS 26 05 29 - 1.03C4PTSW
96ELECTRICAL IDENTIFICATION - 26 05 29 - 1.03B420 days PTSW
97ELECTRICAL IDENTIFICATION - 26 05 29 - 1.03C410 days AFI
98LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS & CABLES 26 05 19 - 1.03B420 days PTSW
99LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS & CABLES 26 05 19 - 1.03C (Test Reports)420 days PTSW
100LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS & CABLES 26 05 19 - 1.03D4PTSW
101LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS & CABLES 26 05 19 - 1.03E (Project Record Documents)4EWD
102CONDUIT 26 05 32 - 1.03B420 days PTSW
103CONDUIT 26 05 32 - 1.03C (Project Record Documents)4PTSW
104BOXES 26 05 33 - 1.03B420 days PTSW
105BOXES 26 05 33 - 1.03C (Project Record Documents)4EWD
106WIRING DEVICES 26 27 26 - 1.03B420 days PTSW
107WIRING DEVICES 26 27 26 - 1.03C4PTSW
108EQUIPMENT WIRING CONNECTIONS 26 05 03 - 1.03B420 days PTSW
109EQUIPMENT WIRING CONNECTIONS 26 05 03 - 1.03C4PTSW
110EQUIPMENT WIRING CONNECTIONS 26 05 03 - 1.04B (Project Record Documents)4EWD
111ENCLOSED SWITCHES 26 05 03 - 1.03B420 days PTSW
112ENCLOSED SWITCHES 26 05 03 - 1.03C (Project Record Documents)4EWD
113ENCLOSED SWITCHES 26 05 03 - 1.03D420 days AFI
114ENCLOSED SWITCHES 26 05 03 - 1.03E (Operation and Maintenance Manuals)420 days AFI
115INTERIOR LUMINAIRES 26 51 00 - 1.03B420 days AFI
116INTERIOR LUMINAIRES 26 51 00 - 1.03C420 days PTSW
117INTERIOR LUMINAIRES 26 51 00 - 1.03D4PTSW
118INTERIOR LUMINAIRES 26 51 00 - 1.03E (Operation and Maintenance Data)4AFI
119STRUCTURED TELECOMMUNICATIONS CABLING & ENCLOSURES 27 13 43 - 1.03B420 days PTSW
120STRUCTURED TELECOMMUNICATIONS CABLING & ENCLOSURES 27 13 43 - 1.03C420 days PTSW
121STRUCTURED TELECOMMUNICATIONS CABLING & ENCLOSURES 27 13 43 - 1.03D (MANUFACTURER'S QUALIFICATIONS)420 days PTSW
122STRUCTURED TELECOMMUNICATIONS CABLING & ENCLOSURES 26 13 43 - 1.03E (INSTALLER QUALIFICATIONS)420 days PTSW
123STRUCTURED TELECOMMUNICATIONS CABLING & ENCLOSURES 26 13 43 - 1.03F (TEST PLAN)430 days PTFI
124STRUCTURED TELECOMMUNICATIONS CABLING & ENCLOSURES 26 13 43 - 1.03G (Field Test Reports)420 days AFI
125STRUCTURED TELECOMMUNICATIONS CABLING & ENCLOSURES 26 13 43 - 1.03H (PROJECT RECORD DOCUMENTS)4EWD
126STRUCTURED TELECOMMUNICATIONS CABLING & ENCLOSURES 26 13 43 - 1.03I (Operation and Maintenance Data)420 days AFI
Schedule of Abbreviations:
AWC= After Work CompletedBMF=Before Material Delivery
PTSW= Prior to Starting WorkSN=Advance Notification
AFA= After Final AcceptanceSRO=After Each Occurrence
PTO= Prior to OutagePTFI=Prior to Final Inspection
PTNT= Prior to Notice to ProceedPTFP=Prior to Final Payment
ANTP= After Notice to ProceedPTCW=Prior to Completing Work
EWD= Each work day AF Form 3000 not requiredAFI=After Final Inspection
PTFA= Prior to Final AcceptancePT=Prior To
ACA= After Contract AwardPSS=Per Submittal Schedule

&L&"Times New Roman,Regular"&12Attachment 2&C&"Times New Roman,Regular"&12PROJECT TITLE&R&"Times New Roman,Regular"&12FA4626-xx-R-xxxx &L&"Times New Roman,Regular"&12AF Form 66 02:

&F-&D&C&"Times New Roman,Regular"&12 SS-&P

REQUIRED TECHNICAL SUBMITTALS