PERFORMANCE WORK STATEMENT (PWS)
FOR
ROUTINE SUBSTATION MAINTENANCE
Solicitation FA4610-11-R-0037
30TH SPACE WING - VANDENBERG AFB
5 July 2012
Solicitation FA4610-11-R-0037 Attachment 1
SUBSTATION MAINTENANCE
TABLE OF CONTENTS
| 1 | DESCRIPTION OF SERVICES | 5 |
| 1.1 | Coordinating Maintenance | 5 |
| 1.2 | Routine/Additional Maintenance | 5 |
| 2 | SCOPE OF WORK | 6 |
| 2.1 | Maintenance Schedules | 6 |
| 2.2 | Monthly Walk-Down Inspection | 6 |
| 2.3 | Substation Transformer Maintenance | 7 |
| 2.4 | 69kV Circuit Breaker (SF6 and Vacuum) Maintenance | 8 |
| 2.5 | Vacuum Insulated 12kV Circuit Breaker Maintenance | 9 |
| 2.6 | 12kV Switchgear Maintenance | 10 |
| 2.7 | Air Disconnecting Switch Maintenance | 12 |
| 2.8 | Protective Relay Testing, Calibration, and Maintenance | 12 |
| 2.8.1 | Visual and Mechanical Inspections | 12 |
| 2.8.2 | Electrical Tests | 12 |
| 2.8.3 | Functional Operation | 13 |
| 2.9 | Other Relay or Control Device Testing, Calibration, and Maintenance | 13 |
| 2.10 | Insulator Maintenance | 14 |
| 2.11 | Fuses Maintenance | 14 |
| 2.12 | Grounding and Lightning Protection Systems Maintenance | 14 |
| 2.13 | Substation Structures and Fencing Maintenance | 15 |
| 2.14 | Buses, Wire and Connectors | 16 |
| 2.15 | Station Control Battery Maintenance | 16 |
| 2.15.1 | Battery Safety Guidelines | 16 |
| 2.15.2 | Visual Inspections | 17 |
| 2.15.3 | Mechanical and Miscellaneous Investigation: | 17 |
| 2.15.4 | Battery Test and Measurement: | 17 |
| 2.16 | Environmental Greenhouse Gas Compliance | 18 |
| 3 | DELIVERABLES | 19 |
| 3.1 | Monthly Reports | 19 |
| 3.2 | Annual Reports | 19 |
| 3.3 | Regulatory GHG Reports | 19 |
| 3.4 | Imminent Issues Reporting | 19 |
| 4 | REPAIRS | 20 |
| 5 | OPERATIONS | 21 |
| 5.1 | Switching Orders | 21 |
| 5.2 | Impact Assessment | 21 |
| 5.3 | Switching Execution | 21 |
| 5.4 | Advance Coordination | 21 |
| 5.5 | Lockdown Limitations | 21 |
| 6 | SERVICES SUMMARY (SS) | 22 |
| 7 | GOVERNMENT FURNISHED PROPERTY AND SERVICES | 23 |
| 7.1 | Utilities | 23 |
| 7.2 | Refuse/Recycle Collection | 23 |
| 7.3 | Security Forces and Fire Protection Services | 23 |
| 7.4 | Medical Response Services | 23 |
| 8 | GENERAL REQUIREMENTS | 24 |
| 8.1 | Quality Assurance | 24 |
| 8.2 | Contractor Quality Control Responsibilities | 24 |
| 8.3 | Contractor Personnel Requirements | 24 |
| 8.3.1 | Personnel performing work standards, certifications and training | 24 |
| 8.3.2 | Regulatory Compliance | 25 |
| 8.3.3 | Conflict of Interest | 25 |
| 8.4 | Security Compliance | 25 |
| 8.5 | Main Base Access Requirements | 25 |
| 8.6 | Base Access Process | 26 |
| 8.7 | Contractor Personnel Access Process | 26 |
| 8.8 | Security Requirements | 26 |
| 8.8.1 | OPSEC Security Training | 26 |
| 8.8.2 | Physical Security Training | 26 |
| 8.8.3 | Urgent Security Action | 27 |
| 8.8.4 | Personnel Background Checks | 27 |
| 8.8.4.1 | CES Security Point of Contact | 27 |
| 8.8.4.2 | NAC Processing Time | 27 |
| 8.8.5 | Contractor Personnel Restrictions | 27 |
| 8.8.6 | Contractor Vehicles | 27 |
| 8.9 | Government Liability. | 28 |
| 8.9.1 | Loss or Damage | 28 |
| 8.9.2 | Fines Assessed Against the Government | 28 |
| 9 | ACRONYMS | 29 |
10 REQUIRED REPORTS AND SUBMITTALS …………………………………………………………………………………………31
APPENDICES:
Appendix 1: Historical Data Appendix 2: Compliance and Reference Publications Appendix 3: Environmental Requirements Appendix 4: GHG Regulations Reference
DESCRIPTION OF SERVICES
The Contractor shall furnish all parts, labor material, equipment, transportation and supervision necessary to provide scheduled, preventive and predictive diagnostic maintenance services for nine (9) substations and one (1) 12kv switch yard (Switch Yard M) that are connected to the 69kV transmission and 12kV distribution systems respectively, located at Vandenberg Air Force Base (VAFB). The period of performance under this Contract is for a base year, four additional option years, and a 6month extension (at the end of the Contract). The option years and 6 month extension are exercisable at the sole discretion of the Government. The goal is to ensure high confidence levels in electrical service required for the entire installation. This Contract is primarily to perform routine maintenance and associated repairs on VAFB substations, as described in paragraphs 2.3 through 2.15 of this PWS. Other “repair” actions may be authorized IAW paragraph 4.
1.1 Coordinating Maintenance
Contractor is advised and understands that VAFB mission priorities and constraints will require the Contractor to be flexible in the scheduling of work to be performed in substations and switch yard. For example, launch protocols prohibit any work to be performed at substations and switch yard 48 hours prior to and 48 hours after a launch. Additionally, year round range activities will restrict the Contractor’s ability to perform work in substations. During periods of heightened national security, work in substations may be restricted. The Contractor shall work closely with 30 Civil Engineering Squadron (30CES) to schedule substation work and shall have the ability to quickly adapt to new or revised schedules as dictated by the VAFB mission. The contractor agrees that these constraints shall not be the basis for any claim for equitable adjustment.
1.2 Routine/Additional Maintenance
The Contractor shall perform routine maintenance at each substation on the items listed in this Performance Work Statement (PWS) at a minimum of once per year unless specifically called out differently in this PWS or otherwise required to meet the performance standards in this Contract or as otherwise required to maintain the substations in proper operational mode?. Routine maintenance includes the provision of labor, materials, equipment, and tools required to perform the maintenance tasks described in paragraphs 2.3 through 2.15 inclusive of this PWS. More frequent maintenance for many of these items may be required to meet the performance standards in this Contract. It is the Contractor’s responsibility to determine the frequency of each maintenance action to meet the performance standards in this Contract. The Contractor may propose additional maintenance or repair actions which are not specified in this PWS to meet the standards in this Contract. The Contracting Officer along with 30CES will determine whether or not to implement the suggested additional maintenance or repairs.
SCOPE OF WORK
Contractor shall provide routine substation maintenance and associated repairs as specified in the following paragraphs:
Maintenance Schedules During the first 30 days of the Contract the Contractor shall mobilize to perform the required maintenance, coordinate the initial schedule for access to the nine (9) substations and one (1) switch yard, and develop and submit a comprehensive maintenance checklist or database for tracking the required maintenance at each substation and switch yard. The Contractor shall submit a final maintenance schedule to include a checklist or multiple checklists for each substation and switch yard that describes the tests to be performed and the proposed recurring frequency for those tests as described in paragraphs 2.3 through 2.15 inclusive of this PWS. This final maintenance schedule shall be submitted by the Contractor NLT 30 days after Contract award. The final maintenance schedule shall be reviewed by 30 CES/CEO and 30 CES/CEP within 15 calendar days of submittal. The final maintenance schedule will be considered approved within 15 days after submittal unless 30 CES/CEO responds otherwise. Once the final maintenance schedule is approved by 30CES/CEO and 30CES/CEP, it will be used for the remainder of the Contract, unless otherwise revised by mutual agreement of Contractor and Government.”
Monthly Walk-Down Inspection Contractor shall perform a monthly walk-down at each substation and switch yard. Contractor shall develop a walk-down inspection checklist of items to be recorded each month, which will require Government approval. . The initial walk-down checklist shall be submitted NLT 45 days after Contract award and monthly thereafter. The monthly inspection is to be performed when possible with other maintenance actions. The Contractor shall notify the Contracting Officer’s Representative (COR) of the date of the monthly walk-down inspection two weeks prior to the walk-down. The Contractor shall, if requested by the Government, be escorted by the COR or a technical representative of the Government during the walk-down inspection. Checklist shall include the following at a minimum.
1. Number of tap change operations at each LTC since last inspection.
2. Voltage and amperage readings on each of the 69kV and 12kV circuits.
3. Record all faults and trips at each circuit for the month from log book entries.
4. Visual inspection of components for signs of potential problems.
5. List any equipment that failed during the month.
6. SF6 readings for all 69kV breakers.
7. Basic transformer readings.
8. Rodent infestation evidence.
9. Any corrosion issues of note.
10. Verification that station is operating nominally.
11. Any other items deemed necessary.
Substation Transformer Maintenance Contractor shall maintain substation transformers using current technology and industry standard practices, methods and frequencies [annual and in accordance with (IAW) manufacturer’s recommendations] to optimize the equipment’s performance and useful life. The frequency of each of these maintenance actions needs to be identified on the Contractor’s checklist for each substation. This Section 2.3 applies to Substations A, B, C, D, E, F, K, N, and the Switching Station. Substation transformer maintenance for the Switching Station is anticipated to commence in Option Year 1 of this Contract for newly installed zig-zag grounding transformers. The substation transformer maintenance program shall include at the minimum the following:
1. Inspect physical and mechanical conditions IAW manufacturer’s instructions.
2. Verify settings and operation of all temperature devices IAW manufacturer’s instructions.
3. Verify cooling fans and pumps are correctly operating and that fan and pump motors have correct over-temperature protection.
4. Verify operation of liquid level indicators, pressure relief devices and fault pressure relays.
5. Test and correct all bolted connections resistance IAW methods, as described in paragraph 2.14 of this PWS.
6. Verify correct liquid levels in all tanks and bushings, and replenish liquids as necessary.
7. Verify that positive pressure is maintained on nitrogen blanketed transformers, and replenish nitrogen as necessary.
8. Inspect equipment grounding, and correct as necessary.
9. Verify the presence of transformer surge arrestors. Inspect for physical defects and perform insulation-resistance test IAW manufacturer’s instructions. Test resistance between the arrester ground terminal and the ground system should be less than 0.5 ohm.
10. Inspect transformer bushings for physical defects and perform recommended tests IAW manufacturer’s instructions. Clean and spray bushings with StaClean or Midsun 570 high voltage coating, as applicable to prevent flashovers.
11. Perform insulation-resistance tests, winding-to-winding and each winding-to-ground.
12. Calculate polarization index, according to IEEE Standard No. 43-2000.
13. Perform turns ratio tests at all tap positions.
14. Perform insulation power factor/dissipation factor tests on windings IAW equipment manufacturer’s instructions.
15. Perform power factor/dissipation factor tests or hot color watts loss tests on bushings IAW equipment manufacturer’s instructions.
16. Perform excitation current tests IAW equipment manufacturer’s instructions.
17. Cycle no-load tap changer and return to as-found position.
18. Perform core insulation resistance to tank ground test.
19. Perform a visual inspection on LTC IAW manufacturer’s instructions.
20. Perform specific inspections and mechanical tests on LTC and associated components, as recommended by manufacturer’s instructions, including replenishment of necessary oil.
21. Replace LTC’s filtration system oil filter breathers, as necessary.
22. Inspect LTC cabinet, and replace missing and burned out lights with non-filament bulbs, as necessary.
23. Remove a sample of insulating liquid IAW with ASTM D-923-07. Sample shall be tested for the listed parameters IAW the referenced specification or standard:
a. Dielectric Breakdown Voltage: ASTM D877 and/or ASTM 1816.
b. Acid Neutralization Number: ANSI/ASTM D974.
c. Interfacial Tension: ANSI/ASTM D971 or ANSI/ASTM D2285.
d. Color: ANSI/ASTM D1500.
e. Visual Condition: ASTM D1524.
f. Moisture in Insulating Liquids: ASTM D1553 (Required on 25kVor higher voltages and on all silicone filled units).
g. Dissipation Factor/Power Factor: ASTM D924.
h. Dissolved Gas Analysis (DGA): ANSI/IEEE C57.10.4.
i. Oxidation Inhibitor: ASTM D2668.
j. Particle Profile and Microscopic Evaluation: ASTM D6786.
k. Furanic Compounds in Electrical Insulating Liquids: ASTM D5837.
l. Polychlorinated Biphenyls in Insulating Liquids – ASTM D4059, if applicable.
69kV Circuit Breaker (SF6 and Vacuum) Maintenance Contractor shall maintain 69kV substation circuit breakers using current technology and industry standard practices, methods and frequencies (annual, 3 year, and 6 year inspections), as necessary to optimize the equipment’s performance and useful life. This Section 2.4 applies to Substations B, C, D, E, F, K, N, and the Switching Station It is anticipated that 69kV SF6 circuit breakers at Substation D will soon be replaced with 69kV vacuum circuit breakers. However, maintenance of the existing 69kV SF6 circuit breakers at Substation D will continue in the Base Year of this Contract. Maintenance of the new 69kV vacuum circuit breakers at Substation D is anticipated to commence in Option Year 1 of this Contract. All other substations noted above are expected to have maintenance performed on 69kV SF6 circuit breakers for the entire duration of this Contract. The substation circuit breaker maintenance program shall, at a minimum, include the following:
1. Document equipment nameplate data on the substation checklist.
2. Inspect physical and mechanical condition IAW manufacturer’s instructions.
3. Lubricate IAW manufacturer’s recommended procedures and lubricants.
4. Inspect anchorage, alignment, required clearances and grounding.
5. Inspect and adjust mechanism IAW manufacturer’s published instructions.
6. Inspect air compressor IAW manufacturer’s instructions, as applicable.
7. Inspect hydraulic system IAW manufacturer’s instructions.
8. Test for gas leaks, and repair as necessary IAW manufacturer’s instructions, including replenishment of SF6 gas. Contractor shall be responsible to provide 30CES reports on a monthly and annual basis of amounts of SF6 gas refilled.
9. Verify correct operation of all air and SF6 gas pressure alarms and cutouts IAW manufacturer’s instructions, as applicable.
10. Test SF6 gas for moisture and nitrogen content, as applicable.
11. Record as-found and as-left counter operations.
12. Perform operation and timing tests IAW manufacturer’s instructions.
13. Verify operation of all heaters.
14. Perform a contact-resistance test. Values should not exceed the manufacturer’s recommendations.
15. Test and correct all bolted connections resistance IAW methods, as described in paragraph 2.14.
16. Perform insulation-resistance test on each pole, phase to phase, and phase -to-ground with breaker closed and across each open pole for a minute. Apply voltage IAW manufacturer’s instructions.
17. Perform power factor/dissipation factor tests on breaker and bushings IAW manufacturer’s instructions.
18. Perform over-potential tests on each phase IAW manufacturer’s instructions.
19. Perform minimum pick-up voltage tests on trip and close coils.
20. Trip circuit breaker by operation of each protective device.
21. Inspect breaker control cabinet, and replace burned out indicating lights with LED bulbs, as necessary. Replace missing or burned out cabinet lights with non-filament bulbs, as necessary.
Vacuum Insulated 12kV Circuit Breaker Maintenance Contractor shall maintain 12kV substation circuit breakers using current technology and industry standard practices, methods, and frequencies, as necessary to optimize the equipment’s performance and useful life. This Section 2.5 applies to Substations A, B, C, D, E, F, K, N and Switch Yard M. The 12kV circuit breakers’ maintenance program shall include at a minimum the following:
1. Document equipment nameplate data.
2. Inspect physical and mechanical conditions IAW manufacturer’s instructions.
3. Lubricate as needed with manufacturer’s recommended lubricants.
4. Inspect anchorage, alignment, required clearances, and grounding IAW manufacturer’s instructions.
5. Perform all mechanical operational tests on both the circuit breaker and its operating mechanism IAW manufacturer’s instructions.
6. Visually inspect critical distances, such as contact gap, as recommended by manufacturer, and report on findings.
7. Test and correct all bolted connections resistance IAW methods, as described in paragraph 2.14of this PWS.
8. Perform timing tests IAW manufacturer’s instructions.
9. Record as-found and as-left operation counter readings.
10. Perform minimum pick-up voltage tests on trip and close coils.
11. Verify trip, close, trip-free, and anti-pump functions.
12. Trip circuit breaker by operation of each protective device.
13. Perform a contact resistance test across each pole, and HIPOT across open contacts.
14. Perform insulation-resistance tests pole-to-pole, pole-to-ground with the switch closed, and across each open pole IAW manufacturer’s instructions.
15. Perform a vacuum bottle integrity (over-potential) test across each vacuum bottle with breaker in the open position. Test voltage should be IAW manufacturer’s recommendations.
16. Perform dissipation factor/power factor tests on each pole with the breaker open, and each pole with the breaker closed.
17. Perform power factor or dissipation tests on each bushing IAW manufacturer’s instructions. Use conductive straps and hot collar procedures, if bushing is not equipped with a power factor tap.
18. Perform an over-potential test on each phase IAW manufacturer’s instructions.
12kV Switchgear Maintenance Contractor shall maintain the 12kV switchgear including the buses, station power transformers, automatic transfer switches, ancillary equipment, control power transformers, metering, and instrumentation using current technology and industry standard practices, methods and frequencies as necessary to optimize the equipment’s performance and useful life. This Section 2.6 applies to Substations A, B, C, D, E, F, K, N, and Switch Yard M.
1. Document make and manufacturer of equipment on inspection checklist.
2. Inspect physical and mechanical conditions IAW manufacturer’s instructions.
3. Inspect anchorage, alignment, grounding, and required area clearances.
4. Verify that fuse and/or circuit breaker sizes and types correspond to drawings.
5. Verify that current and voltage transformer ratios correspond to drawings.
6. Test and correct all bolted connections resistance IAW methods, as described in paragraph 2.14.
7. Confirm correct operation and sequencing of electrical and mechanical interlock systems.
a. Attempt closure on locked-open devices, and attempt to open locked-closed devices.
b. Make key exchange with devices operated in off-normal positions.
8. Inspect and lubricate IAW manufacturer’s instructions.
a. Verify appropriate lubrication on moving current-carrying parts.
b. Verify appropriate lubrication on moving and sliding surfaces.
9. Inspect insulators for evidence of physical damage or contaminated surfaces.
10. Verify correct barrier and shutter installation and operation.
11. Exercise all active components.
12. Inspect mechanical indicating devices for correct operation.
13. Verify that filters are in place, and/or vents are clear.
14. Perform visual and mechanical inspections of instrument transformers IAW manufacturer’s instructions.
15. Inspect control power transformers IAW manufacturer’s instructions.
a. Inspect for physical damage, cracked insulation, broken leads, tightening of connections, defective wiring, and overall general condition.
b. Verify that primary and secondary fuse or circuit breaker ratings match drawings.
c. Verify correct functioning of draw-out disconnecting and grounding contacts and interlocks.
16. Perform electrical tests on instrument transformers IAW manufacturer’s instructions.
17. Perform ground-resistance tests IAW manufacturer’s instructions.
18. Perform resistance measurements through bolted electrical connections with a low-resistance ohmmeter, if applicable.
19. Perform insulation-resistance tests on each bus section, phase-to-phase and phase-to-ground, for one minute IAW manufacturer’s instructions.
20. Perform an over-potential test on each bus section, each phase-to-ground with phases not under test grounded, IAW manufacturer’s instructions.
21. Perform insulation-resistance tests on control wiring with respect to ground. Applied potential shall be 500 volts DC for 300 volt rated cable and 1,000 volts DC for 600 volt rated cable. Test duration shall be one minute. For units with solid-state components or control devices that cannot tolerate the applied voltage, follow manufacturer’s recommendation.
22. Perform current-injection tests on the entire current circuit in each section of switchgear IAW manufacturer’s instructions.
a. Perform current tests by secondary injection with magnitudes, such that a minimum current of 1.0 ampere flows in the secondary circuit. Verify correct magnitude of current at each device in the circuit.
b. Perform current tests by primary injection with magnitudes, such that a minimum of 1.0 ampere flows in the secondary circuit. Verify correct magnitude of current at each device in the circuit.
23. Determine accuracy of all meters, and calibrate watt-hour meters IAW manufacturer’s instructions. Verify multipliers.
24. Perform phasing checks on double-ended or dual-source switchgear to insure correct bus phasing from each source.
25. Inspect and test Control Power Transformers IAW manufacturer’s instructions.
a. Perform insulation-resistance tests. Perform measurements from winding-to-winding and each winding-to-ground IAW manufacturer’s instructions.
b. Perform secondary wiring integrity tests. Disconnect transformer at secondary terminals, and connect secondary wiring to a rated secondary voltage source. Verify correct potential at all devices.
c. Verify correct secondary voltage by energizing primary winding with system voltage. Measure secondary voltage with the secondary wiring disconnected.
d. Verify correct function of control transfer relays located in switchgear with multiple control power sources.
26. Inspect and test Voltage Transformers IAW manufacturer’s instructions.
a. Perform insulation-resistance tests. Perform measurements from winding-to-winding and each winding-to-ground IAW manufacturer’ instructions.
b. Perform secondary wiring integrity tests. Verify correct potential at all devices.
c. Verify secondary voltages by energizing primary winding with system voltage.
27. Verify operation of cubicle switchgear/switchboard space heaters.
Air Disconnecting Switch Maintenance Contractor shall maintain the air disconnect switches using current technology and industry standard practices, methods and frequencies, as necessary to optimize the equipment’s performance and useful life. Substation air disconnect switches may be the single knife blade type operated by hot stick or the gang operated knife blade type either operated by crank handle or swing handle in mechanical linkages. This Section 2.7 applies to Substations A, B, C, D, E, F, K, N, and the Switching Station. The substation air disconnect switch maintenance program shall include at a minimum the following:
1. Perform an operation check.
2. Inspect, clean, and lubricate control rods, contacts, receivers, target plates, or any other hardware present IAW manufacturer’s instructions.
3. Lubricate mechanical linkages IAW manufacturer’s instructions.
4. Inspect switching platforms for bonding continuity and stability, and correct as necessary.
Protective Relay Testing, Calibration, and Maintenance Contractor shall maintain, test, and calibrate protective relays using current technology and industry standard practices, methods and frequencies, as necessary to optimize the equipment’s performance and useful life. This Section 2.8 applies to Substations A, B, C, D, E, F, K, N, Switch Yard M, and the Switching Station. The protective relay testing, calibration, and maintenance shall include at a minimum the following:
Visual and Mechanical Inspections
1. Document equipment’s nameplate and data.
2. Inspect relays and cases for physical damage.
3. Tighten case connections, and inspect cover for correct gasket seal.
4. Clean cover glass.
5. Inspect shorting hardware, connection paddles, and/or knife switches.
6. Remove any foreign material from the case.
7. Verify target reset.
8. Verify relay settings IAW VAFB-supplied coordination study data, and reset as necessary.
Electrical Tests
1. Perform insulation-resistance tests on each circuit frame. From the manufacturer’s instructions, determine allowable procedures required for this test, as it pertains to solid-state and micro-processor based relays.
2. Inspect targets and indicators.
3. Determine pick-up and drop-out of electro-mechanical targets.
4. Verify operation of all panel indicator lamps, and replace as necessary.
5. Set contrast for liquid crystal display readouts.
Functional Operation
1. Device 50 Instantaneous Over-Current Relay.
a. Measure and record pick-up.
b. Measure and record drop-out.
2. Device 51 Time Over-Current Relay.
a. Measure and record minimum pick-up.
b. Measure and record time delays at two points on the time-current curve.
3. Device 79 Reclosing Relay.
a. Measure and record time delay for each programmed reclosing interval.
b. Verify lockout for unsuccessful reclosing.
c. Measure and record reset time.
d. Measure and record close pulse duration.
e. Verify instantaneous over-current lockout.
4. Device 87 Differential Relay.
a. Measure and record operating unit pick-up.
b. Measure and record the operation of each restraint unit.
c. Measure and record slope.
d. Measure and record harmonic restraint.
e. Measure and record instantaneous pick-up.
f. Plot operating characteristics for each restraint.
Other Relay or Control Device Testing, Calibration, and Maintenance Contractor shall maintain, test, and calibrate other relay devices necessary to ensure proper substation operation. At a minimum, the listed devices shall be maintained IAW manufacturer’s instructions. This Section 2.9 applies to Substations A, B, C, D, E, F, K, N, Switch Yard M, and the Switching Station. The Contractor shall identify other unlisted devices for inclusion in the final maintenance schedule as per Section 0. This CLIN shall be all inclusive within Section 2.8 of this PWS and billed within CLIN X007.
1. Device 25 Synchronization Check.
2. Device 67 Directional Over-Current Relay.
3. Device 85 Communications/Pilot Wire Relay.
4. Device 86 Lockout Relay.
5. Controls and indicators.
Contractor shall verify that all power circuit breaker controls operate correctly, to include:
a. Interposing relays, as part of a Supervisory Control and Data Acquisition System (SCADA) or remote control system.
b. Device 43 Remote/local switches, and indicating lamps.
c. Trip/close switches, including close-inhibit and trip-free operation.
d. Breaker position indicating lamps.
e. Alarm indications to local and/or SCADA displays.
Insulator Maintenance Contractor shall maintain insulators using current technology and industry standard practices, methods and frequencies, as necessary. This Section 2.10 applies to Substations A, B, C, D, E, F, K, N, and the Switching Station. The insulator maintenance program shall include at a minimum the following:
1. Perform Corona Detection, and report findings.
2. Inspect for cracks or other defects, and report findings.
3. Clean and spray insulators with StaClean or Midsun 570 high voltage insulator coating, as applicable to prevent flashovers.
4. Perform insulation tests, as necessary to verify proper insulation value.
5. Perform yearly insulator pressure washing with de-ionized water for Substations A, B, C, D, E, F, and the Switching Station. For Substations K and N, perform insulator pressure washing every 6 months. The risk of flashover is very high when an energized, highly contaminated insulator, regardless of its glaze-type, is washed. For that reason, always pressure wash all substation insulators de-energized.
Fuse Maintenance Contractor shall maintain fuses using current technology and industry standard practices, methods and frequency, as necessary to optimize the equipment’s performance and useful life. This Section 2.11 applies to Substations A, B, C, D, E, F, K, N, Switch Yard M, and the Switching Station. The fuse maintenance program shall include at a minimum the following:
1. Visual inspection for corrosion, and repair/replace as necessary.
2. Clean contact surfaces.
3. Visually inspect fuse table to ensure proper fuses are installed.
4. Replace fuses that show visible signs of deterioration.
Grounding and Lightning Protection Systems Maintenance Contractor shall maintain, inspect and test substation grounding systems and lightning protection systems IAW AFI 32-1065, Grounding Systems. Continuity tests, ground resistance measurement/tests, and visual inspection checklists shall be contained within the recurring substation maintenance report or monthly walk-down checklist report, as appropriate. This Section 2.12 applies to Substations A, B, C, D, E, F, K, N, Switch Yard M, and the Switching Station.
Visual/physical inspection shall be performed to ensure:
1. Corrosion or vibration has not weakened any part of the system.
2. Down conductors, roof conductors, and ground terminals are intact. Repair/replace, as necessary.
3. Braided bonding wires are not excessively frayed (cross-sectional area reduced by half). Repair/replace, as necessary.
4. Ground wires on lighting protection masts are not damaged by lawn mowers or other equipment. Repair/replace, as necessary.
5. Conductors and system components are securely fastened to mounting surfaces. Relocate connections, as necessary to better protect against accidental displacement.
6. Surge suppression (over-voltage) devices are in good condition.
7. The system is in good repair.
8. There are no loose connections that might cause high resistance joints. Repair/replace and tighten, as necessary.
9. The system neutral is grounded at the service entrance, including the connection to the grounding electrode. Repair/replace, as necessary.
10. Separately derived systems are properly grounded.
11. Flashover protection is installed on insulating fittings on underground metallic pipelines entering the facility.
12. Grounding systems within the facility are bonded together at ground level or below. Repair/replace, as necessary.
The following tests shall be performed on the grounding and lightning protection systems, as applicable:
1. A point-to-point resistance test, referred to as DC Continuity Testing, to ensure the integrity of the grounding grid. The DC Continuity Test requires lead cables from various points around the facility back to a reference location.
2. A resistance-to-ground test of the grounding electrodes using a clamp-on induced frequency ground resistance meter.
2.13 Substation Structures and Fencing Maintenance
Contractor shall perform annual inspection and maintenance of structures and fences. Contractor shall visually inspect, and document by photograph any corrosion, and other structural issues that should be addressed. Fencing shall be checked for structural integrity, proper signage, locks, functional gates, and ground corrosion. This Section 2.13 applies to Substations A, B, C, D, E, F, K, N, Switch Yard M, and the Switching Station. Inspection results shall be contained within the recurring substation maintenance report or monthly walk-down checklist report, as appropriate. Inspection results shall include the following at a minimum:
1. Any missing signage.
2. Any building envelope or roof leaks.
3. Any indicators of rodent/pest infestation, or infiltration.
4. Any degraded fencing, gates, doors, walls, or other barriers to unauthorized entry.
5. Recommended corrosion control.
6. Performance of weed abatement, or other vegetation removal inside and along the fence line of substation yards.
7. Grounding systems of structures, fences, and gates are bonded together at ground level or below. Repair/replace, as necessary.
8. Inspect and troubleshoot switch house lighting and general yard lighting. Replace defective photocells, ballasts, burned out bulbs and other associated components, as necessary.
9. Inspect substation sump pump for proper operation, and recommend repairs, as necessary.
2.14 Buses, Wire and Connectors Maintenance
Contractor shall maintain the substation conductors, buses, jumpers and related connectors using current technology and industry standard practices, methods and frequencies, as necessary to optimize the equipment’s performance and useful life. This Section 2.14 applies to Substations A, B, C, D, E, F, K, N, Switch Yard M, and the Switching Station. The maintenance program shall include at a minimum the inspection and correction of all bolted electrical connections for high resistance using one of the following methods:
1. Use of low-resistance ohmmeter.
2. Verify tightness of accessible bolted electrical connections by use of a calibrated torque wrench IAW manufacturer’s instructions.
3. Perform thermo-graphic survey that provides a report, which includes the following:
a. Description of equipment to be tested.
b. Discrepancies noted.
c. Temperature difference between the area of concern and the reference area.
d. Probable cause of temperature difference.
e. Identify load conditions at the time of inspection.
f. Provide photographs of the deficient area.
g. Recommended action.
2.15 Station Control Battery Maintenance
Contractor shall maintain the substation control batteries, inverters, rectifiers, panels, and related system components and hardware using current technology and industry standard practices, methods and frequencies, as necessary to optimize the equipment’s performance and useful life. This Section 2.15 applies to Substations A, B, C, D, E, F, K, N, Switch Yard M, and the Switching Station. The maintenance program shall include at a minimum the following:
2.15.1 Battery Safety Guidelines
Maintenance personnel shall be trained to perform the tasks properly. Training shall include using Personal Protective Equipment (PPE), handling the electrolyte safely, using the proper tools, and following the battery manufacturer’s service and maintenance instructions.
1. The room or compartment in which operating lead-acid batteries are located shall be ventilated adequately.
2. Appropriate safety equipment shall be worn, including goggles, gloves, and aprons by persons working with the batteries. Eyewash and quick drench facilities shall be provided near the batteries.
3. Open flames, sparks, hotplates, and other ignition sources shall be kept away from storage batteries, gas ventilation paths, and places where hydrogen can accumulate.
4. Metal objects shall not be placed on battery cells. Insulated tools shall be used to protect against shorting of cells.
5. When electrolyte is being prepared, PPE shall include a full face shield.
2.15.2 Visual Inspections
1. Battery housings shall be checked for cracks and structural damage.
2. The charger shall be checked for proper operation. Interconnection cables, cell connectors, and other conductors shall be examined for wear, contamination, corrosion, and discoloration. Racks shall be checked for corrosion, cleanliness, and structural integrity.
3. A check shall be made for spilled electrolyte. Bicarbonate of Soda solutions shall be used to neutralize lead-acid battery spills.
4. Seismic protection, DC circuit over-current protection, alarm circuits, grounding connections, cable clamps, and all other installed protective systems and devices shall be inspected and corrected, as required.
5. Eyewash and quick drench facilities shall be inspected and corrected, as required.
2.15.3 Mechanical and Miscellaneous Investigation:
1. Terminal connectors, battery posts and cable ends shall be checked, and all corrosion and dirt removed. Battery posts shall be cleaned IAW the manufacturer’s recommendations.
2. Lead-acid battery surfaces shall be cleaned with water and sodium bicarbonate to avoid leakage currents caused by electrolyte on the battery. Cleaners, soaps, or solvents shall not be used to clean battery covers, since damage can result.
3. The inter-cell connectors (links) shall be checked annually, and tightened to manufacturer’s recommended values.
4. Alarm relays, lights, and horns shall be checked for proper operation.
5. Ventilation openings shall be checked to verify they are clear of obstructions.
2.15.4 Battery Test and Measurement:
1. Full battery tests, which include a capacity test, shall be performed IAW manufacturer’s instructions.
2. A sample (e.g. 25 percent) of inter-cell connectors and terminal connection resistances shall be measured quarterly, IAW manufacturer’s instructions.
3. Batteries shall be examined under load with an infrared scanning device. The abnormal temperature of a cell; a poor connection at the battery post; and a deteriorated link, strap, or conductor are some of the problems that can be readily identified by thermo-graphic surveys.
4. Contractor shall annotate all battery readings on AFTO Form 430 or equivalent.
2.16 Environmental Greenhouse Gas Compliance
Contractor shall comply with federal, state and local Greenhouse Gas (GHG) regulations applicable to GHG found in electrical switchgear and electrical transmission and distribution systems under the control (contract obligation) of the Contractor. These regulations include, but are not limited to Title 17, California Code of Regulations (CCR), Subarticle 3.1, Regulation for Reducing Sulfur Hexafluoride Emissions from Gas Insulated Switchgear § 95350 through 95359. This Section 2.16 applies to Substations B, C, D (if applicable), E, F, K, N, and the Switching Station.
At a minimum, the Contractor shall be responsible for the sulfur hexafluoride (SF6) equipment and gas container inventorying, recordkeeping, emissions and emissions rate calculations, and annual report preparations for all VAFB substations.
The Contractor is responsible for SF6 switchgear at VAFB substations. The Contractor shall coordinate and report all GHG, and specifically SF6, regulatory compliance activities and/or actions with the Contract environmental technical representative, the Contract electrical technical representative, and Contracting Officer, as required. The Contractor shall support scheduled and unscheduled visits/inspections by regulators. The Contractor shall notify the responsible VAFB Government officials should an unannounced regulator be present at Contractor facilities or while the Contractor is performing activities/services at a VAFB substation. The Contractor shall not contact environmental regulators without prior coordination and approval from the responsible VAFB Government representative.
3 DELIVERABLES
3.1 Monthly Reports
The Contractor shall submit monthly data as follows:
1. The dates and time the Contractor was performing maintenance on each substation during the month, including the names of the employees performing the maintenance.
2. The dates and time the Contractor was performing “repairs” on each substation during the month, including the names of the employees performing the “repairs”.
3. Completed Monthly Walk-Down checklists for each substation IAW Section 2.2 of this PWS.
4. A written report of defects, deficiencies, anomalies, and issues identified at substations that could impact electrical substation or grid performance.
Monthly reports shall be delivered to the COR NLT one work week after the end of each contract month (no reports are due on Federal holidays, Saturdays or Sundays).
3.2 Annual Reports
The Contractor shall submit an annual summary report for each substation that documents the following:
1. All maintenance performed IAW the maintenance schedule, including all checklists for specific equipment.
2. The frequency of maintenance.
3. All issues identified and corrected by VAFB or the Contractor, including all measured and recorded data as identified in Sections 2.3 through 2.16 inclusive of this PWS. This report shall highlight and prioritize any identified, but uncorrected deficiencies. This report shall be delivered to the COR NLT 1 November of each contract year.
3.3 Regulatory GHG Reports
The Contractor shall maintain all records as required by the applicable regulations and shall deliver those records to 30 CES, as the owner of the GHG (SF6) gas insulated switchgear (GIS). Required, annual reports shall be prepared by the Contractor, and delivered to the VAFB responsible official(s) NLT two work weeks in advance of a regulatory compliance submission date. As owner of regulated GIS, 30 CES/CEAN will certify and send required reports to the applicable regulatory agency.
3.4 Imminent Issues Reporting
Contractor shall provide written notice of imminent issues to the VAFB DCC at 606-1856 upon discovery, if they are an emergency or within 24 hours if they need correction within one week. This report can be via e-mail or letter. Imminent issues are defined as issues that could impact the VAFB grid in a negative fashion or potential degradations of VAFB infrastructure that need immediate attention.
4. REPAIRS
In the course of performing maintenance, the Contractor (or a Government representative) will likely encounter additional repairs (not specified in this PWS) that are necessary for the safety and reliability of VAFB substations. Repairs are defined as repairs for labor and materials under $50,000. The Contractor or the Government may identify a repair. If the Contractor identifies the repair, the Government will determine if the work can be performed in-house. If the repair cannot be performed by the Government, the following processes will be used to execute the repairs. Any repair effort greater than $50,000 shall be procure via a separate contract vehicle.
Firm-Fixed Price Proposal.
Upon identification of a repair, the Contractor shall provide the Government with a firm-fixed price proposal within five (5) workdays after identification, to include a breakdown of the number of labor hours for each labor category required along with a list of the materials/parts needed for the repair. Labor rates shall be those established at Contract award. Repairs $5,000 or less only require written approval from an individual listed on the authorized personnel directory, i.e. COR. Repairs greater than $5,000 requires written approval from the Contracting Officer prior to performing work.
The Contractor shall bill the Government through Wide-Area Work Flow for these services on CLIN 0015 The estimated value of the CLIN will be determined upon award.
5. OPERATIONS
Contractor shall operate substation equipment only when necessary to perform maintenance and repairs, and only when the following conditions have been satisfied:
5.1 Switching Orders
Contractor shall communicate plans to perform switching to the Government Program Manager (PM) by means of a switching order submitted at least five days in advance of the desired switching.
5.2 Impact Assessment
Contractor shall articulate the resulting electrical impact of any switching order by determining which circuits will lose power and which circuits could potentially be back-fed by other energized components.
5.3 Switching Execution
Contractor shall participate in clearing crews from the line prior to any switching operations. To perform this successfully, the Contractor shall be accompanied by a 30 CES electrician equipped with a narrow-band radio tuned to the electrical channel.
5.4 Advance Coordination
Contractor shall allow at least ten business days to secure approval for any electrical outage to a facility customer.
5.5 Lockdown Limitations
To comply with the 30th Space Wing launch configuration policy, the Contractor shall not schedule or perform switching within 48 hours prior to a scheduled space launch, nor within 48 hours after lift-off of a scheduled space launch.
6. SERVICES SUMMARY (SS)
The SS identifies the key performance objectives for the services and the associated performance thresholds that must be attained by the Contractor, and over which the Government will exercise surveillance. The omission of any PWS or Contract requirement from the SS shall not be construed as a waiver by the Government to enforce the performance of that requirement by Contractor or a waiver of any rights or remedies by the Government against Contractor for non performance of that requirement.
Table 1 Key Performance Objectives
| Performance Objective |
| PWS Reference |
| Performance Threshold |
| 1 |
| Completion of monthly inspections |
| Paragraph 2.2 |
| Zero late report submittal(s) per month. |
| 2 |
| Completion of required maintenance and testing |
| Paragraph 2.2-2.15 |
| Zero late report submittals after completion of maintenance. |
| 3 |
| Green House Gas Report Submittals |
| 3.3 |
| Zero late submittal(s) per month and annually. |
7. GOVERNMENT-FURNISHED PROPERTY AND SERVICES
No property or services shall be provided under this Contract, except as noted below. All other items needed to fulfill the requirements of this Contract are the sole responsibility of the Contractor.
7.1 Utilities
The Government will provide electricity and water to support the maintenance requirements of this Contract.
7.2 Refuse/Recycle Collection
The Contractor shall be allowed to use Government-furnished trash/recycle VAFB containers , and dispose of waste at VAFB facilities.
7.3 Security Forces and Fire Protection Services
The Government will provide security force responses and fire suppression services within the confines of VAFB. For emergency services call 606-3911 (LE Desk).
7.4 Medical Response Services
The Government will provide initial medical treatment for life-threatening emergencies. It shall be the responsibility of the Contractor or Contractor employee to seek continued medical treatment, if needed. The Contractor or employee shall reimburse the Government for all Government-provided medical services. The emergency phone number is 606-3911 (LE Desk).
8. GENERAL REQUIREMENTS
8.1 Quality Assurance
The Government will monitor the Contractor’s performance by performing scheduled and unscheduled surveillance. The Government will increase or decrease its surveillance as performance dictates. The Government will also monitor, and investigate customer complaints for the purpose of ensuring whether or not the Contractor is providing quality service. The Contracting Officer or his/her designated representative may schedule progress meetings as required.
8.2 Contractor Quality Control Responsibilities
The Contractor shall provide a Quality Control Plan to the Contracting Officer for acceptance, no later than ten (10) calendar days after Contract start date. Any modifications to the Quality Control Plan must be submitted to the Contracting Officer for acceptance. The plan shall address how the Contractor will ensure all requirements of the PWS are to be met. The plan must contain, at a minimum, the items listed below:
1. A description of the Contractor’s inspection system which should cover, at a minimum, all requirements listed in the Services Summary. Description shall include specifics as to the areas to be inspected on a scheduled and unscheduled basis, frequency of inspections, and the title and organizational placement of the inspectors.
2. A description of the methods to be used for identifying and preventing defects in the quality of service performed.
3. A description of records utilized to document inspections, and corrective actions taken.
4. A description of control procedures for any Government-furnished keys/locksets.
The Contractor’s inspection records shall be kept throughout the Contract performance period and for the period after Contract completion until final settlement of any claims under this Contract. Upon request, the Contractor shall immediately make these records available to the Government for review/inspection.
The Contractor shall also maintain a system which will accept, acknowledge, and forward customer complaints to appropriate parties, and provide a tracking system to ensure resolution of complaints.
8.3 Contractor Personnel Requirements
8.3.1 Personnel performing work standards, certifications and training Contractor personnel shall present a neat appearance and be easily recognizable. This may be accomplished by wearing distinctive clothing bearing the name of the company or by wearing appropriate badges that contain the company name and employee name.
Personnel performing maintenance must have at least five years of substation maintenance experience, and must possess documentation of completion of specific substation maintenance training for each major component upon which the technician is assigned to perform maintenance. Additionally, contractor personnel must possess documentation of completion of training on NFPA 70 safety requirements. Training records must be available for review by Government after award, and upon request.
Contractor shall have on staff a degreed Electrical Engineer with a Professional License as an Electrical Engineer registered in the state of California, and a minimum of five years of substation maintenance experience. A copy of the license and proof of substation maintenance experience must be available for review by Government after award, and upon request.
8.3.2 Regulatory Compliance
Contractor personnel shall comply, and ensure that subContractor personnel comply with current federal, state, local, Department of Defense (DoD), and Air Force regulations, plans, and policies, including all applicable parts of the Air Force Occupational Safety and Health Standard (AFOSH) and United States Department of Labor Occupational Safety and Health Administration (OSHA).
8.3.3 Conflict of Interest
The Contractor shall not employ any person who is an employee of the United States Government if the employment of that person would create a conflict of interest, nor shall the Contractor employ any person who is an employee of the Department of the Air Force, either…