Paint_Booth_Q&A.docx

DOCX document 13 KB Posted

Attached to
307th Paint Booth Federal contract opportunity
Solicitation number
FA4608-17-Q-0032
Issued by
Department of the Air Force Global Strike Command

About this file

Q&A

View the file

Other files for this federal contract opportunity

Other files attached to 307th Paint Booth, newest first.
File Type Posted
Paint_Booth_Pics.pdf PDF
STATEMENT_OF_WORK_-_Paint_Booth_-_6826_updated.docx DOCX document
17-Q-0032_Request_for_Quotation.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Paint Booth Q&A Q. Is the government removing the old paint booth? (Sorry we see on pricing page we Remove) Will government dispose of old equipment etc. removed?

A. Removal and disposal will be entirely on the contractor.

Q. Is the Building CMU, or pre-engineered steel? what about Roof, is it Flat or Pitched if pitched what is the slope? 3:12, etc. ?

A. Building is pre-engineered steel building but interior walls are cinder block with metal exterior walls. Roof is flat for 14 ft., then slopes at 2 inches every 14 feet after. To the best I could measure. See exterior building pictures attached.

Q. Height from floor to the Roof?

A. 18 ft. 4 inches at highest point. 18 ft. 2 inches at interior wall on front side of paint booth area.

Q. Existing Floor is it concrete?

A. Yes. Floor is concrete.

Q. Will all utilities be brought within 10' of the Booth?

A. Electrical connections are provided on adjacent wall of the booth within 10

ft. A hole may need to be drilled to connect. Civil Engineering confirmed.