Attachment_1_-_Specifications.pdf

PDF 241 KB Posted

Attached to
Repair Floor at T-605 Federal contract opportunity
Solicitation number
FA448617Q0018
Issued by
Department of the Air Force United States Air Forces in Europe - Air Forces Africa

About this file

Attachment 1 - Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Repair Floor at T-605, newest first.
File Type Posted
Attachment_4_-_Site_Visit_Reservation.pdf PDF
Attachment_3_-_Submittal_Register.pdf PDF
FA448617Q0018.pdf PDF
Attachment_2_-_Project_Drawings.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Revision 1 – 14 August 2017

SPECIFICATIONS

FOR

REPAIR FLOOR, T-605

MQNA 17-1010

Portfolio Optimization Office, 65th Civil Engineer Squadron

July 2017

USAFE

Lajes Field, Azores, Portugal

65th Civil Engineer Squadron

APO AE 09720

MQNA17-1010 Repair Floor, T-605

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 73 03 SUPPLEMENTARY CONDITIONS FOR AZORES PROJECTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 14 00 WORK RESTRICTIONS

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.10 20 QUALITY CONTROL FOR MINOR CONSTRUCTION

01 78 00 CLOSEOUT SUBMITTALS

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 13 73 COMPRESSION JOINT SEALS FOR CONCRETE PAVEMENTS

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

DOCUMENT 00 73 03

SUPPLEMENTARY CONDITIONS FOR AZORES PROJECTS

08/08

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00.

SD-01 Preconstruction Submittals

AF Form 103; G

1.2 PHYSICAL DATA

Data referred to below is furnished for the Contractor's information.

However, it is expressly understood that the Government will not be responsible for interpretation or conclusion drawn therefrom by the Contractor.

a. The physical conditions indicated on the drawings and in the specifications are the result of site investigations.

b. Geographic Conditions

(1) The Azores are comprised of a group of nine small islands, politically an integral part of Portugal, lying in the North Atlantic, about 2,300 miles east of New York and about 980 miles west of Lisbon, Portugal. The islands have a total area of 1,581 square miles with a total population of about 360,000. The economic mainstays of the Azores are fishing and agriculture.

There is no heavy industry, and facilities for repairing machinery are limited.

(2) The climate is mild and the humidity high. Average annual temperature is 63 degrees F. Diuranal fluctuation in temperature is approximately 10 degrees. Highest recorded temperature, 80 degrees F, lowest recorded temperature, 40 degrees F. The yearly average rainfall is 44.80 inches; the monthly average rainfall and probability of rain is as follows:

Month Average (in.) Probability

January 6.00 65 percent

February 5.40 64 percent

March 5.00 61 percent

April 3.10 43 percent

DOCUMENT 00 73 03 Page 1

Month Average (in.) Probability

May 1.80 39 percent

June 1.80 33 percent

July 7.70 29 percent

August 1.80 35 percent

September 3.20 40 percent

October 5.20 55 percent

November 5.10 57 percent

December 5.30 58 percent

High winds occur from December through March. Average winds during this period are 11.6 knots. The recorded high winds are: November 90 knots, December 72 knots, January 90 knots, February 128 knots, March 106 knots, April 89 knots.

(3) Terceira Island measures roughly 11 by 18 miles, almost entirely bordered by high cliffs. The terrain is hilly and dominated by volcanic ranges, including two extinct craters. The airfield is located on the northeast side of the island. The total population of Terceira Island is approximately 60,000. The city of Angra do Heroismo, capitol of the district, has a population of about 30,000; and the nearest town to the airfield, Praia da Vitoria, has a population of about 11,000.

c. Transportation Facilities for Lajes Field. Lajes Field is defined as the U.S. Forces Azores operational area on Terceira Island.

(1) Railroads: There are no railroads on the island.

(2) Highways and Roads: The majority of the roads are paved. An asphalt highway links Praia da Vitoria and Angra do Heroismo. The use or construction of haul roads and bridges shall be subject to prior approval of the Contracting Officer.

(3) Ports: The island has two ports capable of handling deep draft ocean freighters, Praia da Vitoria and Angra do Heroismo.

(4) Air: Lajes Field is served by the commercial airline companies TAP, Azores Airlines, SATA and Ryanair. This Companies make trips to the mainland portugal and to other azorean islands multiple times a day, among other destinations including United States and Canada..

1.3 LEGAL HOLIDAYS

For information purpose, the base acknowledges the following United States and Portuguese holidays:

DOCUMENT 00 73 03 Page 2

*New Year's Day 01 January

Mardi Gras Variable

Good Friday Variable

Day of Liberty 25 April

Day of the Worker 01 May

Holy Spirit Monday Variable

Corpus Christi Variable

Day of Portugal 10 June

Praia da Vitoria Day 11 August

Assumption Day 15 August

Founding of the Republic 05 October

All Saint's Day 01 November

Restoration of Independence 01 December

Immaculate Conception 08 December

*Christmas Day 25 December

*Martin Luther King's Birthday Third Monday in January

*President's Day Third Monday in February

*Memorial Day Last Monday in May

*Independence Day 04 July

*Labor Day First Monday in September

*Columbus Day Second Monday in October

*Veteran's Day 11 November

*Thanksgiving Day Fourth Thursday in November

(*) NOTE: Any of the above holidays falling on a Saturday will be observed on the proceeding Friday. Holidays falling on a Sunday will be observed on the following Monday.

1.4 SPECIAL CONSIDERATIONS

a. Contractor(s) must use and regard the most current and valid "Lajes Field Facilities Excellence Standards (LFFES)" for construction projects on Lajes Field, Azores. A copy of this standard will be

DOCUMENT 00 73 03 Page 3 provided to the contractor(s) by the CO upon request by each contractor. All project staging areas, construction sites, and storage areas shall be securely fenced around the entire perimeter of the job site. Fencing shall be completely secured at top and bottom to prevent pedestrian access. Fences shall be screened with opaque screening material to prevent visibility of the fenced area (min 2 m in height) in areas where material storage, contractor work trailers, trash container and any debris that maybe collected as result of construction. Fences and screens shall be adequately staked and/or anchored to prevent blowing over during high wind conditions. Submit photos or samples of the screening material for approval prior to installation.

b. The contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The contractor shall only remove trees when specifically authorized by 65 CES Environmental Management function to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound. The contractor shall return all areas disturbed during construction to its original condition.

c. The contractor shall request approval for laydown area and placing an office trailer at any project location. Any office trailer shall be no more than 10' x 32' in size, provided with a skirt on all sides, in like new condition, and painted Cream Beige or an equivalent color of similar tone approved by CO, if it is not obscured and hidden by the opaque fencing material. Office trailers in need of painting and / or repairs or, that are in an unsightly condition will not be allowed at the project site. A nameplate shall be displayed on the exterior of all trailers which lists the name of the contractor's company, contractor's point(s) of contact (POC) and telephone number where he/she can be reached, contract number, and title, and the date trailer was placed at the job site.

d. All contractor employees shall obey all traffic laws on installation.

The contractor shall park all vehicles only in legally designated locations, or within the fence line of the construction site.

e. The contractor shall perform normal housekeeping functions inside and outside contractor job sites. Such functions include grounds maintenance, sweeping, mopping, dusting, disposal of accumulated waste materials and rubbish and other operations necessary to present a neat appearance at all times. All rubbish and waste materials shall be removed daily and shall be placed in contractor furnished containers.

During construction, the contractor shall maintain all areas in a neat and orderly manner. The contractor shall clean the construction site and/or structure of all construction trash, trash generated by employees, debris, demolished building materials, combustible waste material, and/or dust daily or more frequently as necessary for safe operations. During the laying of asphalt roads, streets and/or parking surfaces, areas soiled by residual asphalt shall be cleaned daily. The contractor shall treat with lime entrances and exits to asphalt work site at their own expense. The contractor shall ensure all light or moderate weight debris at the construction site is properly secured in

DOCUMENT 00 73 03 Page 4 waste receptacles so that it does not blow to another area or onto the airfield. At the end of each project all equipment, rubble and rubbish shall be completely removed from the base by the contractor, leaving the area in a safe, clean and orderly manner to the satisfaction of the

CO.

f. Trucks loaded with loose material that can create a dust, debris or falling hazard shall be secured and covered. Fasten a suitable cover, such as tarpaulin, over the load before his/her vehicles and such spillage shall be cleaned up immediately. For the duration of entering surrounding streets. The contractor is solely responsible for spillage from this contract and on a daily basis, the contractor shall remove from all base roads and/or streets asphalt, mud, soil, rocks, trash, and debris that result from their construction business on the particular day affected. In the case of asphalt, roads will be cleaned operation on base. All roads and/or streets affected shall be cleaned before close of and/or treated with lime immediately.

g. Grassy areas disturbed by any type of construction work including storage, equipment staging, and material delivery areas shall be sodded or seeded as required on each delivery order. Contractor shall be responsible for the successful growth and maintenance of all new grass areas under this contract for a period of thirty (30) calendar days, or three mowings, after final acceptance of the work. All grass, shrubbery, and ornamental plants fenced by the construction site shall be maintained to base standards by the contractor.

h. All contractor owned items such as, but not limited to, stakes, traffic/safety cones, barriers, warning tape, erosion control fences that are erected during construction, shall be removed entirely after completion of project and prior to Government acceptance of the project site. The contractor, at his own expense, shall return to the site to remove any items left at or near the project site after this time period.

i. The contractor shall coordinate the exact location of each item of work with the inspector, such as drainage systems, drop inlets, repairs, and so forth. Once a week, the contractor shall layout and stake the proposed work in the field, and then review the layout with the inspector, who shall make recommendations as to adjustments needed.

Prior to doing any work, the contractor shall receive approval from the inspector, who will coordinate with the CO, engineer, and environmental flight as required.

1.5 CONDUCT OF CONTRACTOR PERSONNEL

The Contractor shall report to the Contracting Officer, immediately upon receipt or discovery of any information, whether or not verified, relating to physical security incidents, misconduct, crimes, and misdemeanors, including but not limited to murder, arson, larceny of any weapon, ammunition, or explosives, larceny of other property, robbery, burglary, narcotics and dangerous drugs, destruction of Government property, fraud, malfeasance, sabotage, subversions, disaffections, treasons, or espionage. The Contractor shall recognize and comply with the rules and regulations promulgated by the foreign country where the work is performed to the extent required by pertinent international agreements.

DOCUMENT 00 73 03 Page 5

1.6 TURN-IN OF U.S. GOVERNMENT-OWNED MATERIAL AND EQUIPMENT

Property, material, or equipment removed during the course of repairs, alterations, or renovation of any building or other structure remains the property of the U.S. Government and shall be disposed of as follows:

a. Material other than scrap shall be turned over to the Government.

b. The Contracting Officer will designate the time and place and prepare the necessary forms for receiving the materials.

c. The items designated as scrap by the Contracting Officer shall be disposed of as directed.

1.7 INVESTIGATION OF DAMAGE OR INJURY

The U.S. Government will have the right to conduct an investigation, or participate in the Contractor's investigation, of any damage or injury to U.S. Government property, equipment, or personnel.

1.8 PROCESSING OF CONTRACTOR'S PERSONNEL AND PROPERTY

The Contractor shall process Contractor personnel and property through the Contracting Officer prior to commencement and at the completion of work under this contract. This processing shall include such things as registering and deregistering vehicles, arranging for the issuance and turn-in of identification and passes, and clearing liabilities incurred such as clubs, billeting, and loans.

1.9 VISAS--DIPLOMATIC CLEARANCES

The Contractor shall ensure that his employees obtain the required diplomatic clearances (visas) of sufficient duration to cover the performance period of the contract. (Sixty-day visitor visas are available at Portuguese Immigration at Lajes Field.)

1.10 SPECIAL REQUIREMENTS FOR OUTDOOR SIGNS

In accordance with USFORAZINST 5710.2D outdoor signs displayed on local military facilities are mandatory to be in both Portuguese and English languages. Identical size lettering shall be used for both languages, with Portuguese on top. The same requirement applies to project signs and safety and warning signs as used by the Contractor.

1.11 WRITTEN CORRESPONDENCE

Written correspondence from the Contractor to the Contracting Officer shall be in English language, including but not limited to Contractor's invoice, Contractor's Monthly Estimate for Voucher, Contractor's schedules, samples and submittals, reports, and as-built drawing markups.

1.12 PORTUGUESE EQUIVALENT

Where equipment, materials, or installations are to be in accordance with American standards, the equivalent Portuguese standard may be used subject to the approval of the Contracting Officer. The Contractor shall be responsible for proving the equivalency of the Portuguese standard.

DOCUMENT 00 73 03 Page 6

1.13 SOURCE REQUIREMENTS CLAUSE (01 MAY 86)

The requirements of this clause are material conditions of this contract.

The Contractor shall, in the performance of this contract, use Portuguese sources to the maximum extent feasible for the goods and services required to perform the contract including labor, materials, supplies, services, equipment, and subcontracts provided such goods and services meet the contract specifications and standards, will be available at the required locale within the required time limits and are equal or lower in cost than those from other sources. The Contractor shall demonstrate compliance with this requirement.

The requirement to use Portuguese sources to the maximum extent feasible does not apply when not in accordance with requirements, standards, or specifications specifically set forth elsewhere in this contract.

Consistent with the foregoing, the Contractor shall submit a four-part written "Report of Sources" to the Contracting Officer as follows:

PART I . The Contractor shall prepare a listing indicating for each category of expenditures anticipated under the contract the U.S. dollar value estimated to be paid to Portuguese sources and the U.S. dollar value estimated to be paid to other sources. The categories shall include as a minimum those shown in the following sample format:

REPORT OF SOURCES

Category $ to Portuguese Sources

$ to Other Sources

Transportation

Direct Hire Labor

Construction Materials

Equipment

Purchases

Rentals

Supplies

Services

Subcontracts

Other

Total: (Sum must equal contract price)

NOTES:

DOCUMENT 00 73 03 Page 7

REPORT OF SOURCES

Category $ to Portuguese Sources

$ to Other Sources

(1) Items that are included in subcontracts, such as labor and materials, should be reported only as subcontracts and shall not be included with other categories.

(2) Overhead and profit must be prorated among the categories.

PART II . The Contractor shall prepare a list of subcontracts indicating the purpose of the subcontract, the name of the subcontractor, and whether Portuguese or other source.

PART III . The Contractor shall prepare a list of each item or subcontract not procured from a Portuguese source, indicating the reason for not procuring the item or subcontract from a Portuguese source.

PART IV . The Contractor shall indicate the approximate percentage of the total contract price that he will pay collectively to Portuguese sources.

The initial four-part "Report of Sources" shall be submitted by the Contractor to the Contracting Officer not later than 30 calendar days after contract award. In addition, the Contractor shall submit an updated report in the same four-part format every 30 calendar days thereafter. If no changes have occurred since the last report, the Contractor may submit a negative report by letter.

1.14 SECURITY REQUIREMENTS

a. The contractor shall comply with security regulations imposed by the Installation Commander and/or the agency occupying the space where the work is to be performed, including adhering to, or, obtaining any security clearances.

b. Closure of Openings: The contractor shall close every fence opening resulting from work in order to prevent outside intrusion at the end of each workday. The Closure(s) shall remain in place when contractor is not actively engaged in working on the site(s), including each and every day, night, weekends, and holidays, to reduce wind and weather intrusion. The closure(s) shall be constructed of mesh wire anchored in place to stud framing, if necessary, or similar construction as approved by a government representative through the CO.

c. Contractor Access to Air Force Installations: The contractor shall obtain temporary installation passes for all contractor/subcontractor personnel who visit or perform work on the Air Force Installations cited in the contract. The contractor shall obtain passes through the 65th Contracting Flight. Contractor personnel are required to wear or prominently display contractor furnished badges while visiting or performing work on the installation.

d. Work Performed in Secured Areas: Projects in secured areas may require a local agency check of contractor personnel and all sub-contractors prior to commencement of work. If a check is required, the contractor should allocate time in the work schedule to accomplish this check. The contractor shall price work performed in secured areas according to

DOCUMENT 00 73 03 Page 8 standard work hour rates unless prior approval to use non-standard work hour rates is obtained from the CO.

e. Escort in Restricted Areas: Contractor personnel must be escorted at all times in a controlled/restricted area by a government escort.

Escorts for secured areas will be scheduled by the contractor at least ten (10) calendar days prior to starting work. The government will provide an escort as quickly as possible, but the contractor should expect delays due to the sensitive nature of secured areas.

f. Unauthorized Reconnaissance: The contractor shall inform all personnel working under his/her jurisdiction (including subcontractor and visiting supplier personnel) that access to areas outside the immediate work area (excluding cafeterias and rest rooms near the work site, direct haul and access routes, contracting and points of supply and storage) is strictly prohibited. Circulation of the above personnel shall be limited to official business only. Persons engaged in unauthorized reconnaissance of other contractor or government activity will be referred to the CO for disposition. Infractions involving possible compromise of national security will be turned over to the Office of Special Investigation (OSI) for disposition.

1.15 CONSTRUCTION SITE MAINTENANCE

a. The contractor shall maintain each site in a neat and orderly manner.

All supplies and equipment on the project site shall be stored to preclude mechanical and climatic damage. All grass, weeds, etc. shall be cut as necessary to prevent any fire/safety hazards and shall be no higher than 5 cm at any one time or as directed by the CO. All trash, debris, paper etc. shall be picked up immediately and placed in proper containers.

b. Contractor Parking: The contractor shall inform his employees, suppliers, and subcontractors that their vehicles shall not be parked on grass, in Fire Lanes or other restricted areas, parking spaces marked as "Handicapped" or "Government", at any time. In addition, vehicles may not be driven over grass surfaces, unless indicated during a site visit or pre-performance conference. Any damage done to lawns, shrubs, sidewalks etc. shall be repaired or replaced by the contractor at no additional cost to the government.

c. Trucking: Loose debris on trucks leaving the site shall be loaded in a manner that will prevent dropping of materials on streets and conform to local ordinances and laws. Fasten suitable cover, such as a tarpaulin, over the load before entering surrounding streets. The contractor shall be responsible for immediately cleaning up any materials that fall from trucks.

d. Fencing of Construction Site: Fences will be used to isolate construction sites as per instructions by the CO and per recommendations of the Lajes Facility Excellence Standards.

e. Barricades

(1) The contractor shall barricade access to all construction sites.

Barricading shall be used to isolate areas from access. The barricades shall be maintained in good condition, and be installed such that people approaching from the predominant direction can clearly read the warning. Barricades on streets shall have

DOCUMENT 00 73 03 Page 9 battery powered flashers for night use. Construction fencing shall be used to isolate exterior areas from pedestrian access, and shall be maintained in good condition. Cones shall only be used to temporarily block pedestrian traffic. Extended pedestrian blockages or road traffic shall use rigid barrels/barricades. All barricades, barrels, cones, etc., are included in the contractor's supplied equipment/supplies and therefore shall not be a direct cost to any contract unless the CO deems the individual contract requirements so extensive as to warrant payment.

(2) All projects involving excavation shall be secured with flashing lights on all sides and have construction fencing completely surrounding the site at a minimum of five (5) feet from the hole.

1.16 DRAWING REQUIREMENTS

a. Existing Condition Drawings and As-built Drawings (including utilities):

(1) Existing condition drawings showing existing underground utilities are available upon request. The contractor shall avail himself of the drawings. Any utility line shown on the record drawings (or made known to the contractor) and damaged during construction work shall be repaired immediately by the contractor at no additional cost to the government.

(2) The government does not guarantee the accuracy or adequacy of existing record drawings. It is the contractor's responsibility to verify all existing conditions prior to starting work.

(3) During the progress of the job, the contractor shall keep a careful record at the job site of all work accomplished from the layouts shown on the drawings. The contractor shall provide documents (drawings or sketches) to describe all of the work accomplished, and enter changes and corrections on contract or record drawings promptly and submit to the CO.

b. As-built Work Element in Progress Schedule:

(1) As-builts shall be in the form of one (1) CD-ROM with all documents and drawings as .pdf-files and shall be turned over to the CO within twenty-one (21) calendar days of final inspection.

(2) The as-builts shall be professionally drafted in AutoCAD and the contractor shall use conventional drafting techniques, nomenclature, symbols, lettering, noting, and dimensioning.

Resolution of reproducible as-builts shall be legible.

(3) Computer-Aided Design and Drafting (CADD) drawings shall comply with the most current version of Department of Defense (DOD) Technical Report arcGIS.

(4) The as-built drawings shall indicate, in addition to all changes and corrections, the actual as-built condition. In order that the location of sub-surface utility lines and appurtenances may be determined in the event the surface openings or indicators become covered over or obscured, utility record drawings shall show by offset dimensions to two permanently fixed surfaced features, the end of each run including each change in direction. Valve, splice boxes, and similar appurtenances shall be located by dimensioning

DOCUMENT 00 73 03 Page 10 along the utility run from a reference point. The average depth below the surface of each run shall also be recorded.

1.17 PERMITS

a. Welding Permit: No welding shall be started without first obtaining a permit issued by the 65 CES/CEF, Fire Prevention and Emergency Service Office. Contractor shall request the welding permit not less than five

(5) working days before the welding work starts.

b. Work Clearance Requests:

(1) In order to avoid damaging any underground utilities, such as sewer, water, gas, electrical, telephone, cable TV, and possibly others, the contractor must obtain digging permits. The contractor shall process, obtain and maintain a Work Clearance Request (AF Form 103) required, prior to beginning construction.

(2) The contractor is responsible for obtaining a Work Clearance Request for each contract right after Notice to Proceed (NTP) is issued. The contractor must fill out the request form (AF Form

103) with pertinent information and attach a plan showing the location of the respective work (contract drawings with areas highlighted is acceptable).

(3) Contractor shall submit to CO two (2) signed copies of the form (AF Form 103).

(4) Also, as a part of the work request process, the contractor shall be required to mark all locations of excavation work on site with white spray paint or stakes with flagging. Existing utilities will be marked in the field by the respective agency in proposed construction areas. The contractor is required to maintain these markings (or reference points) so that the pertinent agency does not have to duplicate their work.

1.18 PROGRESS REPORTS

The reports mentioned in FAR clause 52.236-15, "Schedules for Construction Contracts" shall be accomplished on AF Form 3064, Contracts Progress Schedule, and AF Form 3065, Contract Progress Report.

1.19 MATERIAL SUBMITTAL AND APPROVAL FORM

In accordance with FAR clause 52.236-5 "Materials and Workmanship," all material requiring approval shall be submitted by the contractor to the CO for approval on an AF Form 3000 within ten (10) calendar days after NTP (or as other-wise established by the CO).

1.20 COORDINATION WITH GOVERNMENT ACTIVITIES

a. If it becomes necessary to interrupt work activities due to construction, permission to do so must be requested in writing to the CO twenty-one (21) calendar days in advance.

b. The contractor shall request street closings, both partial and/or total, twenty-one (21) calendar days prior to the closing.

c. Work in conjunction with this contract which requires utility outages

DOCUMENT 00 73 03 Page 11 which will affect (as determined by the CO) normal activities in the building, construction area, or other work areas, shall be performed by the contractor at a time other than regular work periods of the organization occupying the facility or area.

d. Temporary construction for facilities used by the contractor for preventing interruption of normal work activity or loss of utilities shall be subject to approval of 65 CES/CEN through the CO.

e. Utility Outages:

(1) The contractor shall coordinate all utility outages with the using agency through the CO or his representative prior to the outage.

Services shall not be interrupted until receipt of approval of proposed hours and dates from the 65 CES/CEN through the CO. All work shall be arranged to ensure that the outage will be of minimum duration. The contractor will provide notice to the CO, in writing, not less than twenty-one (21) working calendar days prior to the required outage or as determined by the CO. No response to the outage/interruption request shall be considered as disapproval for the outage/interruption. In the event a scheduled utility outage is canceled by the Government, notification shall be given to the contractor at least 24 hours in advance of the time for the outage to start and the contractor waives his right to any claim for equitable adjustment or increased cost of performance under this contract as a result of this cancellation. Once a utility outage is arranged and work begun, work must go on continuously until the affected utilities are restored to the affected facility.

(2) The contractor's Interruption and Outage Requests shall include specific location of interruption/outage, hours and dates of interruption/outage, services affected by the interruption/outage.

(3) Water Mains. Operation of valves on water mains will be by government personnel only. Where shut-off of water lines interrupts service to fire hydrants or fire sprinkler systems, the contractor shall contact the CO and arrange his operations to have sufficient personnel available to restore service without delay in the event of an emergency as determined by the 65 CES/CEF Fire Prevention Office.

(4) Fire Protection System. Where interruption of electrical power affects a fire protection system service, the contractor shall notify the CO twenty-one (21) working calendar days before making such interruptions and shall restore service prior to leaving the job site each day.

1.21 REMOVAL AND REPLACEMENT RESPONSIBILITY

The contractor shall be responsible for the replacement or repair of all existing finished surfaces, utilities, equipment, landscapes, grounds, and structures or parts thereof that he/she has damaged, removed, or cut into in order to perform work specified. Removed items to be reinstalled shall be stored by the contractor, free from damage, until reinstalled at no additional cost to the Government.

1.22 WARRANTY SERVICE REQUIREMENTS

a. The contractor shall furnish, as a minimum, one (1) primary name and

DOCUMENT 00 73 03 Page 12 telephone number of an individual on his/her management staff, available twenty four (24) hours per day, seven (7) days per week, for the life of this contract to respond to warranty situations. In the event the primary individual is unavailable, the contractor shall furnish an alternate individual and shall notify the CO of the alternate individual's telephone number.

b. Following notification by the CO or, the COR, the contractor shall respond to a warranty service requirement identified by the CO, or the COR, in accordance with the "Warranty Service Priority List" of this program. This list prioritizes warranty work into the following categories:

Emergency: Perform on site inspection to evaluate situation, determine course of action, initiate work within 2 hours and work continuously to completion.

Urgent: Perform on site inspection to evaluate situation, determine course of action, initiate work within 24 hours and work continuously to completion.

Routine: All other work to be initiated within 48 hours and work continuously to completion.

c. The "Warranty Service Priority List" is as follows:

Emergency: Emergency deemed as any damage on the active runway.

Urgent: All repairs on the airfield taxiways and/or parking aprons.

Routine: All other areas.

d. Should parts be required to complete the work and the parts are not immediately available the contractor shall have a maximum of 12 hours after arrival at the job site to provide the CO with firm, written proposals for emergency alternatives and temporary repairs for government participation with the contractor to provide emergency relief until the required parts are available on site for the contractor to perform permanent warranty repair. The contractor's proposals shall include a firm date and time that the required parts shall be available on site to complete the permanent warranty repair.

The CO will evaluate the proposed alternatives and select the alternative considered to be in the best interest of the government to reduce the impact of the emergency condition. Alternatives considered by the CO will include the alternative for the contractor to "do nothing" while waiting until the required parts are available to perform permanent warranty repair. Negotiating a proposal, which will require government participation and the expenditure of government funds, shall constitute a separate procurement action by the government.

1.23 CONTRACTOR PERSONNEL

Contract Manager: The contractor shall provide a contract manager and at least one alternate. The contract manager and alternate shall have full authority to act for the contractor in all contractual matters. The contract manager or alternate shall be available during standard work hours. The contract manager and alternate shall be able to read, speak and write English fluently.

DOCUMENT 00 73 03 Page 13

1.24 GOVERNMENT PERSONNEL

Personnel from 65 CES/CEN are designated as the representative of the CO for the purpose of technical surveillance of workmanship and inspection of materials for work being performed under this contract. This designation in no way authorizes anyone other than the CO to commit the Government to changes in the terms of the contract. No oral statement of any person and no written statement of anyone other than the CO shall modify or other-wise affect the terms or meaning of this contract. All requests by the contractor for interpretations, modifications, or changes shall be made in writing to the CO. The Government shall not be liable for any costs incurred by the government or any action taken by the contractor, which are not in conformance with this statement.

1.25 E-MAIL CAPABILITY

The contractor shall have e-mail capability, via Internet or other means.

This will allow the CO and 65 CES/CEN to communicate with contractor via e-mail.

1.26 GOVERNMENT LIABILITY

The Government shall not be liable for any loss or damage to the contractor's property, including stock, or for expenses incidental to such loss or damage. The contractor shall file a report with the Base Security Forces immediately as is practicable to report loss.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Document --

DOCUMENT 00 73 03 Page 14

SECTION 01 11 00

SUMMARY OF WORK

08/15

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only.

SD-01 Preconstruction Submittals

Manufacturer's product instalation instructions; G

Initial DD form 1354; G

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes the repair of building T-605 floor, by providing a new epoxy floor system and new floor markings. The area of the floor to be repaired is defined in the project drawings.

The work will consist on:

- Remove all existing floor markings and paint (Area 1 and 2 in the project drawings);

- Repair all existing holes and cracks in the floor (the floor shall be smooth and flat);

- Apply primer coat SIKAFLOOR 156 (see attached product data sheet), or equivalent, in accordance with the manufacturer's product instalation instructions;

- Apply first coat SIKAFLOOR 264 plus 4% of SIKA anti slip agent (see attached product data sheets), or equivalent, in accordance with the manufacturer's product instalation instructions;

- Apply second coat SIKAFLOOR 264 (see attached product data sheet), or equivalent, in accordance with the manufacturer's product instalation instructions;

- Remove all existing joint sealants (see specifications section 32.13.73

- Compression joint seals for concrete pavements);

- Saw-cutting the concrete floor for new joint seals aplication (see specifications section 32.13.73 - Compression joint seals for concrete pavements);

- Apply new compression joint seals system in accordance with specifications section 32.13.73 - Compression joint seals for concrete pavements;

- Paint safety/operational markings in the floor, according to project drawings;

1.2.2 Location

The work is located in building T-605, Lajes Field, Terceira Island, Azores, Portugal. The exact location will be shown by the Contracting Officer.

SECTION 01 11 00 Page 1

1.2.3 Period of Performance

Contractor is required to complete project within 90 calendar days including material acquisition.

1.3 OCCUPANCY OF PREMISES

Building will be occupied during performance of work under this Contract.

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways. 1.4 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.5 INITIAL DD FORM 1354

Initial "DD Form 1354 - Transfer and Acceptance of DoD Real Property" with cost estimate breakout for all the planned assets 15 calendar days after notice to proceed.

PART 2 PRODUCTS

- See SIKAFLOOR 254 (or equivelent product) product Data Sheet.

- See SIKAFLOOR 156 (or equivelent product) product Data Sheet.

- See SIKAFLOOR anti slip agent product (or equivelent product) Data Sheet.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 2

SECTION 01 14 00

WORK RESTRICTIONS

11/11

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel; G

1.2 CONTRACTOR ACCESS AND USE OF PREMISES

1.2.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.

1.2.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.2.1.2 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

1.2.2 Working Hours

Regular working hours must consist of an 8 hour period , between 8 a.m.

and 5:00 p.m., Monday through Friday, excluding Government holidays.

1.2.3 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 21 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a

SECTION 01 14 00 Page 1 manner approved by the Contracting Officer.

1.2.4 Occupied Buildings

The Contractor shall be working around existing buildings which are occupied.

The existing buildings and their contents must be kept secure at all times.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 14 00 Page 2

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

08/15

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-04 Samples

Color Boards; G

1.2 COLOR BOARDS FOR AIR FORCE PROJECTS

Submit five sets of color boards within 15 calendar days after Contract Award. Each set of boards must include samples of colors and finishes of floors and floors markings. Present the samples on 8 by 10-1/2 inches boards (modules) with a maximum spread of 24 by 31-1/2 inches for foldouts. Design modules to fit in a standard loose-leaf, three-ring binder. If more space is needed, more than one board per set may be submitted. Certify that the color samples have been reviewed in detail, and that the color samples are in strict accordance with contract drawings and specifications, except as may be otherwise explicitly stated.

Submittal of color samples does not relieve the Contractor of the responsibility to submit samples required elsewhere herein.

1.3 SUPERVISION

1.3.1 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.

1.4 PRECONSTRUCTION

After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work must also attend.

1.5 PARTNERING

To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key

SECTION 01 30 00 Page 1 personnel from the Supported Command, the End User (who will occupy the facility), the Government Design and Construction team and Subject Matter Experts, the Installation, the Contractor and Subcontractors, and the Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.

The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.

1.5.1 Informal Partnering

The Contracting Officer will organize the Partnering Sessions with key personnel of the project team, including Contractor personnel and Government personnel.

The Initial Partnering session should be a part of the Pre-Construction Meeting. Partnering sessions will be held at a location agreed to by the Contracting Officer and the Contractor (typically a conference room provided by the office or the Contractor). The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by the Contracting Officer. The Partners will determine the frequency of the follow-on sessions, at no more than 3 to six month intervals.

1.6 ELECTRONIC MAIL (E-MAIL) ADDRESS

Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use e-mail to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats. Multiple e-mail addresses are not allowed.

It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this e-mail address.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 30 00 Page 2

SECTION 01 33 00

SUBMITTAL PROCEDURES

05/11

PART 1 GENERAL

1.1 DEFINITIONS

1.1.1 Submittal Descriptions (SD)

Submittals requirements are specified in the technical sections.

Submittals are identified by Submittal Description (SD) numbers and titles as follows:

SD-01 Preconstruction Submittals

Submittals which are required prior to

Certificates of insurance

Surety bonds

List of proposed Subcontractors

List of proposed products

Construction progress schedule

Network Analysis Schedule (NAS)

Submittal register

Schedule of prices or Earned Value Report

Health and safety plan

Work plan

Quality Control(QC) plan

Environmental protection plan

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

Samples of warranty language when the contract requires extended product warranties.

SD-04 Samples

Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by

SECTION 01 33 00 Page 1 which the work can be judged.

Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.

Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.

Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports.

Daily logs and checklists.

Final acceptance test and operational test procedure.

SD-11 Closeout Submittals

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).

Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.

1.1.2 Approving Authority

Office or designated person authorized to approve submittal.

1.1.3 Work

As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.

SECTION 01 33 00 Page 2

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. Submit the following in accordance with this section.

SD-01 Preconstruction Submittals

Submittal Register; G

SD-11 Closeout Submittals

Interim DD Form 1354; G

1.3 SUBMITTAL CLASSIFICATION

Submittals are classified as follows:

1.3.1 Government Approved (G)

Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are considered to be "shop drawings."

1.4 PREPARATION

1.4.1 Electronic File Format

Provide submittals in electronic format, with the exception of material samples required for SD-04 Samples items. Compile the submittal file as a single, complete document, to include the Transmittal Form described within.

This is the start of the file's text. The full file is on GovTribe.