FA4484-15-R-0023-0002.pdf
PDF 829 KB Posted
- Attached to
- DOOR REMOVAL AND REPLACEMENT Federal contract opportunity
- Solicitation number
- FA4484-15-R-0023
About this file
FA4484-15-R-0023-0002 Amendment
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA4484-15-R-0023_B657_Questions.pdf | ||
| FA4484-15-R-0023-0001.pdf | ||
| J2_-_Past_Performance_Questionnaire.doc | DOC document | |
| J1_-_Wage_Determination.pdf | ||
| J3_-_Security_Forces_Appendix.doc | DOC document | |
| Request_for_Proposal.pdf | ||
| J4-_Submittal_Register.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4484-15-R-0023
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
STATEMENT OF WORK
STATEMENT OF WORK
FOR
Replace Doors in Building #657 (Rev 1)
AT
JOINT BASE MDL, LAKEHURST, NEW JERSEY
1. DESCRIPTION OF SERVICES. The contractor shall provide all personnel, equipment, tools, materials, supervision, and other items necessary to remove and replace interior doors in building #657 located at JB-MDL, Lakehurst, N.J.
2. TECHNICAL_REQUIREMENTS: The Contractor shall provide all the necessary labor, equipment, materials, transportation, and supervision to meet all of the following requirements:
• Remove all existing interior metal doors, frames and sidelights. Existing doors consists of: forty (40) metal half glass closet sliding doors, tracks and hardware located in classrooms, nine (9) metal classroom half glass doors and 16” wide side lights windows and metal frames located in corridor classroom entrances and one (1) metal office half glass door and 16” wide side lights windows and metal frame located in corridor, one (1) metal office half glass door and 8” wide side lights windows and metal frame located in corridor / dinette area, eight (8) half glass metal doors and metal door frames located in office, corridor, and dinette areas, two (2) metal bath room doors with metal door frames located in corridor and dinette areas and one (1) metal door with metal door frame located in closet in kitchen, two
(2) metal closet half glass pull doors and one (1) metal frame located in dinette area.
• Total number of doors to be removed is sixty-four (64) doors. Total numbers of door frames to be removed is twenty-three (23) door frames.
• Remove existing child finger protection guard and hardware on existing hinged doors. (total of nineteen
(19) finger protection guards)
• Provide and replace existing metal doors and frames with new fire rated solid wooden doors and new metal frames. New doors will consist of forty (40) new solid wooden half glass closet sliding doors and new tracks and hardware located in classrooms (new doors will be approximately 36” wide by 79 ½” high without frames), nine (9) new fire rated solid wooden classroom half glass doors and 16” wide side lights windows and new metal frames located in corridor classroom entrances and one (1) new fire rated wooden office half glass door and 16” wide side lights windows and metal frame located in corridor (new doors will be approximately 35 ½” wide by 79 ½” high – door frames will be approximately 58” wide by 81 ¾” high), one (1) new metal office half glass door and 8” wide side lights windows and metal frame located in corridor / dinette area (new door will be approximately 35 ½” wide by 79 ½” high – door frame will be approximately 50” wide by 81 ¾” high), eight (8) new single fire rated solid wooden half glass doors and new metal door frames located in office, corridor, and dinette areas (new doors will be approximately 36” wide by 79 ½” high – new door frames will be approximately 40” wide by 82” high), two (2) new fire rated solid wooden bath room doors with new metal door frames located in corridor and dinette areas and one (1) fire rated solid wooden door with metal door frame located in closet in kitchen (new doors will be approximately 35 ½” wide by 79 ½” high – new door frames will be approximately 40” wide by 79 ¾” high) and two (2) new fire rated solid wooden closet half glass pull doors and one (1) new metal frame located in dinette area. (new doors will be approximately 24” wide by 79 ½” high – new door frame will be approximately 52” wide by 81 ¾” high)
• New metals frames can be welded or “knock down” frames.
• Install new locksets, door closers and hardware to doors; adjust as needed for proper operation.
• New locksets shall be Grade 1 cylindrical locksets.
• New closers shall be LCN brand, model # 4041 or direct equivalent.
• New locksets shall be lever handle lockset style, stainless steel with 26D finish.
• All locksets shall accept BEST type lock cores. Existing cores shall be reused.
• All new hardware shall have a satin stainless steel 26 D finish.
• All old hardware, door knobs, locksets, kick plates, closers, and child finger protection guards shall be retained and turned over to Tech. P.O.C at the end of job.
• New doors shall be solid core birch veneer with a clear birch rotary white finish. All doors shall have a clear gloss polyurethane finish.
• New doors shall have a 1 hour fire rating. Blocking for door closers and locksets is required. Closet doors do not require to be fire rated.
• New classroom doors, room # ten, and kitchen door shall have new metal kick plates on interior side of doors.
• Mop plates shall be installed on the doors on the opposite side of the door of the kick plates.
• Mop plates shall be installed on all closet doors on the classroom side of doors.
• Mop plates shall be installed on the sides of the doors that have linoleum / tile flooring.
• New doors shall have new continuous high frequency/heavy duty hinges.
• New installation shall include all new hardware (heavy duty closers, handles, locksets, tracks, rollers, etc.)
• All glass panels shall be shatter proof 1 hour fire rated safety glass.
• Provide and replace existing child finger protection guards and hardware with new child finger protection guards and hardware on nineteen (19) hinge doors located in classrooms, corridor, and office area.
• Door frames shall be painted. Color to match existing.
(NOTE: Paint colors are: Sherwin-Williams 6800 – Something Blue (walls) Sherwin- Williams 6601 – Butter Up (walls) and Sherwin-Williams 7606 – Blue Cruise (door jams). Finish shall semi-gloss for all frames, and doors shall have a clear gloss polyurethane finish.)
• All installations shall be according to manufacturer’s written instructions and assembly manuals.
• Work shall be done after operational hours of the Child Development Center.
• Weekend work is acceptable; all scheduling of weekend work must be done through Tech. POC.
Operating hours of the child development center are Monday through Friday 0630 to 1730.
• NOTE: At the site visit it was stated all work on the doors started at the beginning of the work day must be completed by the end of the work day. Completed means fully functional, maintainable and must be able to be secured in accordance with base child care standards.
2.1. Submittals:
See register
Any adjacent areas dissembled, damaged, or removed by the contractor during installation shall be properly repaired by the contractor at no expense to the Government. Any and all debris / trash generated by this project shall be removed and properly disposed of off base by the contractor. The contractor or his representative (QAP) shall be on site during duty hours or the hours of work being accomplished. The contractor shall coordinate the time that work will be accomplished with the points of contact listed below. The contractor shall be responsible for daily clean up at the work site and complete restoration of the area after completion of the work. All work shall be accomplished in accordance with all Federal, state, and local laws and regulations, applicable building codes and standards, NEC, NFPA, BOCA, & CABO, and OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA) codes.
3. SITE VISIT:
A site visit of the facility will be scheduled and Contractor attendance is highly recommended.
4. SPECIAL REQUIREMENTS:
The work site shall remain clean and clutter free since this area is an active employment site. All dumpsters or other containers for trash and debris shall be located in areas designated by the building manager and shall be subject to removal and / or relocation at the building manager’s request. These requirements shall not impact the performance period.
5. POINTS OF CONTACT:
SSgt Jillian Clamor at (609) 754 4996, jillian.clamor@us.af.mil A1C Mark Horton (609) 754 4791, mark.horton.2@us.af.mil
The Contractor Manager or an alternate shall be available within sixty (60) minutes notice during normal duty hours, 7:00am to 3:30pm, to meet with Government personnel to discuss any problems encountered at the work site.
Contractor will supply Government Quality Assurance Personnel (QAP) with phone number for contacting purposes.
6. BASE ENTRY:
The contractor shall obtain the necessary passes and /or identification for entry into Joint Base McGuire, Dix, Lakehurst for all employees prior to commencement of work. The Government reserves the right to refuse to issue an entrance pass to any employee for any reason deemed valid by the Government. The contractor shall be required to provide the Security Forces with vehicle registration(s), proof(s) of insurance, driver license(s), and a picture ID(s) to obtain a pass for entry onto the base. The Pass and Registration building is located on Rt. 547, Lakehurst, NJ.
7. SECURITY FORCE AND FIRE PROTECTION:
USE 911 TO REPORT ALL EMERGENCIES (POLICE, FIRE, EMS)
The Base Security Police Non-Emergency telephone number is 609-562-6001.
8. PERFORMANCE PERIOD:
All work shall be completed within a ONE HUNDRED AND TWENTY (120) calendar day period, excluding holidays.
9. INSPECTION / ACCEPTANCE OF PROJECT COMPLETION:
A final inspection will be scheduled upon completion of all work. Contact the Quality Assurance Evaluator two (2) days prior to completion for a site visit.
SECTION F - DELIVERIES OR PERFORMANCE
The following Delivery Schedule item for CLIN 0001 has been changed from:
DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC
90 dys. ADC 1 87 CES/CEOSS - F3A3Q5
ANDREW FAZIO
BLDG 191
LAKEHURST NJ 08733-1110
732-323-2860 FOB: Destination
F3A3Q5 mailto:jillian.clamor@us.af.mil mailto:mark.horton.2@us.af.mil
To:
DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC
120 dys. ADC 1 87 CES/CEOSS - F3A3Q5
ANDREW FAZIO
BLDG 191
LAKEHURST NJ 08733-1110
732-323-2860 FOB: Destination
F3A3Q5
(End of Summary of Changes)
| 8. PERFORMANCE PERIOD: |
| All work shall be completed within a ONE HUNDRED AND TWENTY (120) calendar day period, excluding holidays. |