Question_from_Refuse_site_visit_II.doc
DOC document 27 KB Posted
- Attached to
- Refuse Collection and Disposal Services Federal contract opportunity
- Solicitation number
- FA4419-13-T-0102
About this file
Questions from Refuse site visit II
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Clarification_from_Question_from_Refuse_site_visit_II.doc | DOC document | |
| FA4419-13-T-0102-0001.pdf | ||
| Comments_from_Refuse_site_visit.doc | DOC document | |
| Wage_Determination.pdf | ||
| Solicitation_FA4419_13_T_0102.pdf | ||
| Signed_PWS_Refuse_1.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question:
Which size dumpster was required for this job, and how often would the dumpster be emptied and what specific materials would be going into the dumpster?
Answer:
The dumpster size is listed as 2 cubic yard capacity in the PWS. The frequency for food and other high use dumpsters is specifically listed in the PWS. The other dumpsters are listed as at least once weekly, but if the dumpster reaches 80% of capacity it will need to be dumped. This may, on occasion, mean that a dumpster may have to be dumped twice in one week. The scheduling of the dumpsters that are not listed as specific days is up to the contractor.