Questions_and_Answers_1.pdf

PDF 54 KB Posted

Attached to
Install Overhead Hoist, Bldg 90700 Federal contract opportunity
Solicitation number
FA4417-16-R-0009
Issued by
Department of the Air Force Special Operations Command

View the file

Other files for this federal contract opportunity

Other files attached to Install Overhead Hoist, Bldg 90700, newest first.
File Type Posted
Site_Visit_Sign_In-MFR.pdf PDF
FA4417-16-R-0009_Amendment_1.pdf PDF
Financial_Reference_Sheet.pdf PDF
Past_Present_Performance_Questionnaire.pdf PDF
WD_FL160029.pdf PDF
FTEV_14-1183_Specifications.pdf PDF
FTEV_14-1183_Drawings.pdf PDF
FA4417-16-R-0009.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION NO. FA4417-16-R-0009

INSTALL OVERHEAD HOIST

BUILDING 90700

QUESTIONS & ANSWERS

23 March 16

1. Are existing hangar drawings available? Existing drawings are needed to do an analysis on the trussed frames to ensure that additional loads would not cause any problems.

Answer: The A/E Design Team has determined and documented that, if attached per the Structural Plans provided, the crane loading will have no adverse effect on the structure.

Contractor’s structural design responsibilities shall begin with the method of attachment and all components below the point of connection.

2. Will there be any lead abatement performed on this project?

Answer: Existing structural components within the hangar bay have been historically found, and should be assumed to still contain lead concentrations exceeding 1.0 mg/cm2 within the paint system. The presence of lead at this level may result in airborne lead concentrations being generated during construction activities that may exceed the Permissible Exposure Limit (PEL) identified in OSHA Lead Construction Standard (29

CFR 1926.62).

Contractor shall adhere to all federal and state requirements concerning management of lead containing materials including, but not necessarily limited to the requirements stipulated in Specification Section 01 56 00 ENVIRONMENTAL PROTECTION and OSHA Lead Construction Standard (29 CFR 1926.62).

3. Will the Hanger remain empty during this contract period, or will we need to consider any down time due to a plane being inside during our scheduled work day?

Answer: The hangar will not be empty during the whole contract period. Per general notes on drawing sheet T-1, contractor will need to closely coordinate planned hangar access dates. Aircraft maintenance will be performed on the west side of the hangar most of the performance period while new crane is being installed on the east side. Welding operations will need to be conducted during times when there is no plane in the hangar. This could be at night or on weekends.

-END QUESTIONS & ANSWERS -