Q and A.pdf
PDF 53 KB Posted
- Attached to
- Erosion Control/Xeriscape around Kearney Blvd Federal contract opportunity
- Solicitation number
- FA303020Q0024
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment FA303020Q00240001 SF 30.pdf | ||
| Q and A.pdf | ||
| AF3000 - Material Submittal - Fillable.pdf | ||
| AF 3064 - Progress Schedule.xlsx | XLSX spreadsheet | |
| FOUO (PII) BAL Working Copy (Initial Request) APR 2020.docx | DOCX document | |
| Erosion_Xeriscaping Sustainability Guidance Form.pdf | ||
| GAFB_Erosion_Trouble_Areas_Updated.pdf | ||
| SOW Erosion Control.pdf | ||
| AF Form 3065.docx | DOCX document | |
| Solicitation - FA303020Q0024.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q: Can we use a River Gravel size of 2” to 6” instead of 3” to 5”?
A: Yes.
Q: Can Low profile metal edging be used?
A: Yes, as long as the finished product can be mowed over, instead of edge trimmed.
Q: The SOW is asking for removal of 6 inches of soil, replaced with river rock with a concrete block border around it. There are specs for each but is this the basic requirements of the SOW?
A: Yes. The removal of soil and addition of stone/rock is needed.