RFQ Notice ID# FA301622U0286

Amendment #1

8 September 2022

1. The purpose of this Amendment is to provide the government’s response to questions submitted by contractors.

2. Contractor questions and government responses are below.

Contractor Question 1: Is there a loading dock present for each location the equipment will be delivered?

Government Response: Yes, loading docks are available at both locations.

Contractor Question 2: Are the doorways big enough for the machines to go through?

Government Response: Yes, each facility has double doors and the machines will fit through the

Doorways.

Contractor Question 3: Are the present machines in place Insinger brands? If not, what brand are they.

Government Response: Bldg 9110 has a Hobart Model UW50, Bldg 6592 has Champion Brand Models: LD20PTELEL and ED12PTELEL

3. Please acknowledge receipt of this amendment with your quote as follows:

Amendment #1, FA301622U0286, Dated 8 September 2022

SUBJECT: Contractor Acknowledgement

TO: 502 CONS/JBKAB

I acknowledge receipt of this Amendment.

Authorized Signature

Date