Attachment 10 - Q and A_ 24 July 2020.pdf

PDF 229 KB Posted

Attached to
Repair 900 Block Parking Lots Federal contract opportunity
Solicitation number
FA301020R0031
Issued by
Department of the Air Force Air Education and Training Command

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA301020R0031

Repair Parking Lots, 900 Block

Questions & Answers 24 July 2020

Q1: How often can billing be submitted on this project?

A: Progress payments will be made in accordance with FAR clause 52.232-5, as included in the solicitation.

Q2: What is the procedure to submit an invoice and what documentation is required?

A: Invoicing will be accomplished in accordance with DFARS clause 252.232-7006, as included in the solicitation.

Q3: What is the procedure to use water from on-base fire hydrants?

A: The hydrant usage request process will be covered after award with the successful Offeror during the pre-construction meeting.

Q4: How is a “concrete surface crack” repaired?

A: Concrete surface cracks have been removed from this requirement. Note 4 on the Drawings

(Attachment 3) and the SOW (Attachment 1) have been updated to remove this requirement.

Q5: What is the procedure for an unforeseen site condition? Example: (a) Tree stump in parking area.

(b) Asphalt not 2” thick.

A: Differing site conditions discovered after contract award will be handled in accordance with

FAR clause 52.236-2, as included by reference in the solicitation.

Q6: Have any cores been done to areas being milled?

A: The Drawings have been updated to provide locations and information regarding cores which have been accomplished. Please see “Attachment 3 – DWG_Repair 900 Block_Rev2_3 Oct 2019” as included with Amendment 002 of this solicitation.

Q7: Will the contractor coordinate with CM on schedule or ALCON?

A: The schedule will be coordinated in accordance with paragraph 3.2.4 of the Statement of

Work (Attachment 1), as included with the solicitation.

Q8: How long will the submittal review process take?

A: Submittals will be reviewed and processed in accordance with paragraphs 3.2.5 and 3.3 of the Statement of Work (Attachment 1), as included with the solicitation.

Q9: How long will the inspection process take?

A: The pre-final (if needed) and final inspection process will be covered after award with the successful Offeror during the pre-construction meeting.

Q10: How long after inspection until the contractor receives a punch list?

A: The pre-final (if needed) and final inspection process will be covered after award with the successful Offeror during the pre-construction meeting.

Q11: Can the job supervisor monitor multiple projects or remain on-site during on-going work?

A: Site supervision will be accomplished in accordance with paragraph 3.6 of the Statement of

Work (Attachment 1) and FAR clause 52.236-6, as included with the solicitation.

Q12: How long will it take to get 30-day passes?

A: Pass requests will be processed in accordance with paragraph 3.12 of the Statement of Work

(Attachment 1), as included in this solicitation. Any additional information which may impact base access passes will be provided by Security Forces after contract award with the successful Offeror during the pre-construction meeting.

Q13: What is the appropriate asphalt mix?

A: See Statement of Work (SOW) paragraph 3.2.4 and Specifications paragraph 2.3 and 3.3.