Attachment_1-_MAHG101026C_Repair_Larcher_Paving_SPEC.pdf
PDF 120 KB Posted
- Attached to
- Repave Larcher Paving Federal contract opportunity
- Solicitation number
- FA3010-18-R-0022
About this file
Please see attached.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amend_1.pdf | ||
| MAHG101026C_Repair_Larcher_Paving_ADDENDUM1.pdf | ||
| Site_Visit_Sign_in.pdf | ||
| Attachment_6_-_Reference_List.pdf | ||
| Attachment_5_-_PPQ.pdf | ||
| Attachment_8_-_SF_1444.pdf | ||
| FA3010-18-R-0022.pdf | ||
| Attachment_4-MAHG101026C_Repair_Larcher_Paving_DWG.pdf | ||
| Attachment_3-_WDOL_Highway_Repair_Larcher_Paving.pdf | ||
| Attachment_2-MAHG101026C_Repair_Larcher_Paving_SOW.pdf | ||
| Attachment_7_-__Notice_of_Compliance.pdf | ||
| Synopsis.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MAHG 10-1026C REPAVE LARCHER BLVD
PAVEMENT MARKINGS
SECTION 32 17 23, Page 1
SECTION 32 17 23
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)
ASTM D 471 (1998) Rubber Property - Effect of Liquids
ASTM D 522 (1993) Mandrel Bend Test of Attached Organic
Coatings
ASTM D 711 (1998) No-Pick-Up Time of Traffic Paint
ASTM D 792 (1991) Density and Specific Gravity (Relative
Density) of Plastics by Displacement
ASTM D 823 (1995) Producing Films of Uniform Thickness of Paints, Varnishes, and Related Products on Test Panels.
ASTM D 2240 (1997) Rubber Property-Durometer Hardness
ASTM D 2621 (1995) Infrared Identification of Vehicle
Solids from Solvent Reducible Paints
ASTM D 2697 (1998) Volume Nonvolatile Matter in clear or
Pigmented Coatings
ASTM D 3335 (1999) Lead, Cadmium, and Cobalt in Paint by
Atomic Absorption Spectroscopy
ASTM D 3718 (1999) Low Concentrations of Chromium in paint by Atomic Absorption Spectroscopy
ASTM D 3924 (1996) Conditioning and Testing Paint, Varnish, Lacquers, and Related Materials
ASTM D 3960 (1998) Determining Volatile Organic Compound
(VOC) Content of Paints and Related Coatings
ASTM D 4280 (1996) Extended Life Type, Nonplowables, Prismatic, Raised, Retroflective Pavement Markers
ASTM D 4541 (1995) Pull-Off Strength of Coatings Using
Portable Adhesion Testers
ASTM E 28 (1996) Softening Point by Ring-and-Ball
Apparatus
SECTION 32 17 23, Page 2
ASTM G 53 (1996) Operating Light- and Water- Exposure Apparatus (Fluorescent UV Condensation Type) for Exposure of Nonmetallic Materials
U.S. GENERAL SERVICES ADMINISTRATION (GSA)
FS A-A-2886 (1997; Rev A)Paint, Traffic, Solvent Based
FED-STD-595 (1989; 1994; Rev. B) Colors used in
Government Procurement
FS TT-B-1325 (1993; 2000; Rev. C) Beads (Glass Spheres)
Retro-Reflective
FS TT-P-1952 (1994; 2000; Rev. D) Paint, Traffic and
Airfield Markings, Water Emulsion Base
INTERNATIONAL CONCRETE REPAIR INSTITUTE (ICRI)
ICRI Technical Guideline 03732 Selecting and Specifying Surface Preparation for Sealers, Coatings, and Membranes
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. When applicable, submit the following in accordance with the procedures in the Statement of Work:
SD-03 Product Data
Reflective media for roads and streets
Paints for roads and streets
Thermoplastic compounds and primer
SD-06 Test Reports
SD-07 Certificates
SD-08 Manufacturer's Instructions
SECTION 32 17 23, Page 3
Submit manufacturer's Material Safety Data Sheets.
1.3 DELIVERY AND STORAGE
Deliver paints, paint materials and thermoplastic compound materials in original sealed containers that plainly show the designated name, specification number, batch number, color, date of manufacture, manufacturer's directions, and name of manufacturer. Provide storage facilities at the job site for maintaining materials at temperatures recommended by the manufacturer.
1.4 WEATHER LIMITATIONS
Apply paint to clean, dry surfaces, and unless otherwise approved, only when air and pavement temperatures are above 40 degrees F and less than 95 degrees F for oil-based materials; above 50 degrees F and less than 110 degrees F for water-based materials. Maintain paint temperature within these same limits.
1.5 EQUIPMENT
Machines, tools, and equipment used in the performance of the work shall be approved by the Engineer and maintained in satisfactory operating condition.
Submit construction equipment list for approval by the Engineer.
1.5.1 Paint Applicator
Provide hand-operated push-type applicator machine of a type commonly used for application of paint to pavement surfaces. Paint applicator machine shall be acceptable for marking small street and parking areas. Applicator machine shall be equipped with the necessary paint tanks and spraying nozzles, and shall be capable of applying paint uniformly at coverage specified. Applicator for water-based markings shall be equipped with non-stick coated hoses; metal parts in contact with the paint material shall be constructed of grade 302, 304, 316, or equal stainless steel.
1.5.2 Reflective Media Dispenser
Attach dispenser for applying the reflective media to the paint dispenser and operate automatically and simultaneously with the paint applicator through the same control mechanism. Use dispenser capable of adjustment and designed to provide uniform flow of reflective media over the full width of the stripe at the rate of coverage specified herein at all operating speeds of the paint applicator to which it is attached.
1.5.3 Thermoplastic Application Equipment
Application equipment shall be mobile and maneuverable to the extent that straight lines can be followed and normal curves can be made in a true arc.
The equipment used for the placement of thermoplastic pavement markings shall be of two general types: mobile applicator and portable applicator.
1.5.3.1 Mobile Application Equipment
SECTION 32 17 23, Page 4
The mobile applicator shall be defined as a truck-mounted, self-contained pavement marking machine that is capable of hot applying thermoplastic by either the extrusion or spray method. The mobile unit shall be capable of operating continuously and of installing a minimum of 20,000 lineal feet of longitudinal markings in a 8-hour day. Equip the mobile unit with a melting kettle of such capacity as to hold a minimum of 6000 pounds of molten thermoplastic material. The kettle shall be capable of heating the thermoplastic composition to temperatures of 375 to 425 degrees F. The heating mechanism shall be by means of a thermostatically controlled heat transfer liquid. Heating of the composition by direct flame shall not be allowed. Oil and material temperature gages shall be visible at both ends of the kettle.
1.5.3.2 Portable Application Equipment
The portable applicator shall be defined as hand-operated equipment, specifically designed for placing special markings such as crosswalks, stopbars, legends, arrows, and short lengths of lane, edge and centerlines.
The portable applicator shall be capable of applying thermoplastic pavement markings by the extrusion method. It is intended that the portable applicator will be loaded with hot thermoplastic composition from the melting kettles on the mobile applicator. Equip the portable applicator with all the necessary components, including a materials storage reservoir, bead dispenser, extrusion shoe, and heating accessories, so as to be capable of holding the molten thermoplastic at a temperature of 375 to 425 degrees F, of extruding a line of 3 to 12 inches in width, and in thickness of not less than 0.125 inch nor more than 0.190 inch and of generally uniform cross section.
1.6 METHOD OF MEASUREMENT
The method of measurement for painted and preformed pavement markings shall be the square foot of painted area approved and accepted. The unit of measurement for raised reflective markings will be each.
1.7 BASIS OF PAYMENT
The measured quantity of painted and preformed pavement markings will be paid for at the respective contract unit prices, which will constitute full compensation for furnishing all materials, equipment, plant, and tools; and for all labor and other incidentals necessary to complete work required by this section of the specification.
PART 2 PRODUCTS
2.1 MATERIALS
Provide materials conforming to the requirements specified herein.
2.1.1 Paints for Roads and Streets
FS TT-P-1952, color as indicated.
2.1.2 Reflective Media for Roads and Streets
FS TT-B-1325, Type I, Gradation A.
SECTION 32 17 23, Page 5
2.1.3 Thermoplastic Compounds
The thermoplastic reflectorized pavement marking compound shall be extruded or sprayed in a molten state onto a primed pavement surface. Following a surface application of glass beads and upon cooling to normal pavement temperatures, the marking shall be an adherent reflectorized strip of the specified thickness and width that is capable of resisting deformation by traffic.
2.1.3.1 Composition Requirements
The binder component shall be formulated as a hydrocarbon resin. The pigment, beads and filler shall be uniformly dispersed in the binder resin.
The thermoplastic composition shall be free from all skins, dirt, and foreign objects and shall comply with the following requirements:
Percent by Weight Component White Yellow
Binder 17 min 17 min Titanium dioxide 10 min - Glass beads 20 min 20 min Calcium carbonate and inert fillers 49 min * Yellow pigments - *
*Amount and type of yellow pigment, calcium carbonate and inert fillers shall be at the option of the manufacturer, providing the other composition requirements of this specification are met.
2.1.3.2 Physical Properties
a. Drying time: When installed at 70 degrees F and in thicknesses between 1/8 and 3/16 inch, the composition shall be completely solid and shall show no damaging effect from traffic after curing 15 minutes.
b. Softening point: The composition shall have a softening point of not less than 194 degrees F when tested in accordance with ASTM E 28.
c. Specific gravity: The specific gravity of the composition shall be between 1.9 and 2.2 as determined in accordance with ASTM D 792.
2.1.3.3 Primer
a. Asphalt concrete primer: The primer for asphalt concrete pavements shall be a thermosetting adhesive with a solids content of pigment reinforced synthetic rubber and synthetic plastic resin dissolved or dispersed in a volatile organic solvent. The solids content shall not be less than 10 percent by weight at 70 degrees F and 60 percent relative humidity. A wet film thickness of 0.005 inch, plus or minus 0.001 inch, shall dry to a tack-free condition in less than 5 minutes.
b. Portland cement concrete primer: The primer for portland cement concrete pavements shall be an epoxy resin primer. The primer
SECTION 32 17 23, Page 6 shall be of the type recommended by the manufacturer of the thermoplastic composition.
2.1.4 Raised Pavement Markers
Either metallic or nonmetallic markers of the button or prismatic reflector type may be used. Markers shall be of permanent colors as specified for pavement marking, and shall retain the color and brightness under the action of traffic. Button markers shall have a diameter of not less than 4 inches.
Button markers shall have rounded surfaces presenting a smooth contour to traffic and shall not project more than 3/4 inch above level of pavement.
Pavement markers and adhesive epoxy shall conform to ASTM D 4280
PART 3 EXECUTION
3.1 SURFACE PREPARATION
Allow new pavement surfaces to cure for a period of not less than 30 days before application of marking materials. Thoroughly clean surfaces to be marked before application of the paint. Remove dust, dirt, and other granular surface deposits by sweeping, blowing with compressed air, rinsing with water, or a combination of these methods as required. Remove rubber deposits, existing paint markings, residual curing compounds, and other coatings adhering to the pavement by water blasting or approved chemical. For Portland Cement Concrete pavement, grinding, light shot blasting, and light scarification, to a resulting profile equal to ICRI Technical Guideline 03732 CSP 2, CSP 3, and CSP 4, respectively, can be used in addition to water blasting, to either remove existing coatings or for surface preparation on most pavements: shot blasting shall not be used on airfield pavements due to the potential of Foreign Object Damage (FOD) to aircraft. Scrub affected areas, where oil or grease is present on old pavements to be marked, with several applications of trisodium phosphate solution or other approved detergent or degreaser and rinse thoroughly after each application. After cleaning oil-soaked areas, seal with shellac or primer recommended by the manufacturer to prevent bleeding through the new paint. Do not commence painting in any area until pavement surfaces are dry and clean.
3.2 APPLICATION
3.2.1 Rate of Application
3.2.1.1 Reflective Markings
Apply paint evenly to the pavement area to be coated at a rate of 105 plus or minus 5 square feet per gallon. Apply glass spheres uniformly to the wet paint on airfield pavement at a rate of 10 pounds of glass spheres per gallon and on road and street pavement at a rate of 6 plus or minus 0.5 pounds of glass spheres per gallon.
3.2.1.2 Nonreflective Markings
Apply paint evenly to the pavement surface to be coated at a rate of 105 plus or minus 5 square feet per gallon.
3.2.1.3 Thermoplastic Compound
SECTION 32 17 23, Page 7
After surface preparation has been completed, prime the asphalt or concrete pavement surface with spray equipment. Allow primer materials to "set-up" prior to applying the thermoplastic composition. Apply asphalt concrete primer to all asphalt concrete pavements at a wet film thickness of 0.005 inch, plus or minus 0.001 inch 265 to 400 square feet per gallon. Apply portland cement concrete primer to all concrete pavements (including concrete bridge decks) at a wet film thickness of between 0.04 to 0.05 inch 320 to 400 square feet per gallon. After the primer has "set-up", apply the thermoplastic at temperatures no lower than 375 degrees F nor higher than 425 degrees F at the point of deposition. Immediately after installation of the marking, apply drop-on reflective glass spheres mechanically at the rate of one pound per 20 square feet such that the spheres are held by and imbedded in the surface of the molten material. Apply all extruded thermoplastic markings at the specified width and at a thickness of not less than 0.125 inch nor more than 0.190 inch. Apply all sprayed thermoplastic markings at the specified width and the thickness designated in the contract plans. If the plans do not specify a thickness, apply centerline markings at a wet thickness of 0.090 inch, plus or minus 0.005 inch, and edgeline markings at a wet thickness of 0.060 inch, plus or minus 0.005 inch.
3.2.2 Painting
Apply paint pneumatically with approved equipment at rate of coverage specified herein. Provide guidelines and templates as necessary to control paint application. Take special precautions in marking numbers, letters, and symbols. Manually paint numbers, letters, and symbols. Sharply outline all edges of markings. The maximum drying time requirements of the paint specifications will be strictly enforced, to prevent undue softening of bitumen, and pickup, displacement, or discoloration by tires of traffic.
Discontinue painting operations if there is a deficiency in drying of the markings until cause of the slow drying is determined and corrected.
3.2.3 Reflective Media
Application of reflective media shall immediately follow the application of paint. Accomplish drop-on application of the glass spheres to ensure even distribution at the specified rate of coverage. Should there be malfunction of either paint applicator or reflective media dispenser, discontinue operations until deficiency is corrected.
3.2.4 Thermoplastic Compound
Place thermoplastic pavement markings upon dry pavement. At the time of installation the pavement surface temperature shall be a minimum of 40 degrees F and rising. Thermoplastics, as placed, shall be free from dirt or tint. Apply all centerline, skipline, edgeline, and other longitudinal type markings with a mobile applicator. Place all special markings, crosswalks, stop bars, legends, arrows, and similar patterns with a portable applicator, using the extrusion method.
3.2.5 Raised Pavement Markers
Prefabricated markers shall be aligned carefully at the required spacing or as directed and permanently fixed in place by means of epoxy adhesives. To ensure good bond, areas where markers will be set shall be thoroughly cleaned by water blasting and use of compressed air prior to applying adhesive.
SECTION 32 17 23, Page 8
3.3 FIELD TESTING AND INSPECTION
3.3.1 Sampling and Testing
At the discretion of the Engineer, samples may be requested from the Contractor for testing by the Government for verification.
3.3.2 Inspection
Examine material at the job site to determine that it is the material referenced in the report of test results or certificate of compliance. A certificate of compliance shall be accompanied by test results substantiating conformance to the specified requirements.
3.3.2.1 Surface Preparations and Application Procedures
Surface preparations and application procedures will be examined by the Engineer to determine conformance with the requirements specified. Approve each separate operation prior to initiation of subsequent operations.
3.4 TRAFFIC CONTROL AND PROTECTION
Place warning signs near the beginning of the work site and well ahead of the work site for alerting approaching traffic from both directions. Place small markers along newly painted lines to control traffic and prevent damage to newly painted surfaces. Mark painting equipment with large warning signs indicating slow-moving painting equipment in operation. Do not use foil-backed material for temporary pavement marking because of its potential to conduct electricity during accidents involving downed power lines.
-- End of Section --
SUBMITTAL PROCEDURES
SECTION 013300, Page 1
SECTION 01 33 00
PART 1 GENERAL
1.1 SUBMITTAL IDENTIFICATION
Submittals required are identified by SD numbers as follows:
SD-01 Data
SD-04 Drawings
SD-06 Instructions
SD-07 Schedules
SD-08 Statements
SD-09 Reports
SD-13 Certificates
SD-14 Samples
SD-18 Records
SD-19 Operation and Maintenance Manuals
1.2 SUBMITTAL CLASSIFICATION
Submittals are classified as follows:
1.2.1 Contracting Officer Approved
Approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Within the terms of the Contract Clause entitled "Specifications and Drawings for Construction," they are considered to be "shop drawings."
1.2.2 Information Only
All submittals not requiring approval will be for information only. They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.
1.3 APPROVED SUBMITTALS
The Contracting Officer's approval of submittals shall not be construed as a complete check, but will indicate only that the general method of construction, materials, detailing and other information are satisfactory.
Approval will not relieve the Contractor of the responsibility for any error which may exist. After submittals have been approved by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment http://www.ccb.org/UFGS/ufgstoc.htm
SECTION 013300, Page 2 will be considered unless accompanied by an explanation of why a substitution is necessary.
1.4 DISAPPROVED SUBMITTALS
The Contractor shall make all corrections required by the Contracting Officer and promptly furnish a corrected submittal in the form and number of copies specified for the initial submittal. If the Contractor considers any correction indicated on the submittals to constitute a change to the contract, a notice in accordance with the Contract Clause "Changes" shall be given promptly to the Contracting Officer.
PART 2 PRODUCTS (NOT APPLICABLE)
PART 3 EXECUTION
3.1 GENERAL
The Contractor shall make submittals in two copies. The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Units of weights and measures used on all submittals shall be the same as those used in the contract drawings. Each submittal shall be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Prior to submittal, all items shall be checked and approved by the Contractor's Quality Control (CQC) System Manager and each item shall be stamped, signed, and dated by the CQC System Manager indicating action taken.
Proposed deviations from the contract requirements shall be clearly identified. Submittals shall include items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list);
certifications; warranties; and other such required submittals. Submittals requiring Contracting Officer approval shall be scheduled and made prior to the acquisition of the material or equipment covered thereby. Samples remaining upon completion of the work shall be picked up and disposed of in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.
3.2 SUBMITTAL REGISTER
The Contractor shall provide a list of items of equipment and materials for which submittals are required by the specifications. The Contracting Officer may require additional submittals throughout the duration of the contract.
The approved submittal register will become the scheduling document and will be used to control submittals throughout the life of the contract. The submittal register and the progress schedules shall be coordinated.
3.3 SCHEDULING
Submittals covering component items forming a system or items that are interrelated shall be scheduled to be coordinated and submitted concurrently.
Certifications to be submitted with the pertinent drawings shall be so scheduled. Adequate time (a minimum of 20 calendar days exclusive of mailing time) shall be allowed and shown on the register for review and approval. No delay damages or time extensions will be allowed for time lost in late submittals.
SECTION 013300, Page 3
3.4 DEVIATIONS
For submittals which include proposed deviations requested by the Contractor, the Contractor shall set forth in writing the reason for any deviations and annotate such deviations on the submittal.
3.5 CONTROL OF SUBMITTALS
The Contractor shall carefully control his procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."
3.6 APPROVED SUBMITTALS
Upon completion of review of submittals requiring Contracting Officer approval, the submittals will be identified as having received approval by being so stamped and dated. One copy of the submittal will be retained by the Contracting Officer, and the other copy of the submittal will be returned to the Contractor.
3.7 INFORMATION ONLY SUBMITTALS
Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals. The Contracting Officer reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work.
COLD-MILLING OF BITUMINOUS PAVEMENT
SECTION 02961, Page 1
SECTION 02961
03/98
\PART 1 GENERAL
1.1 REFERENCE
The publication listed below forms a part of this specification to the extent referenced. The publication is referred to in the text by the basic designation only.
AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM)
ASTM C 136 (2001) Sieve Analysis of Fine and Coarse
Aggregates
1.2 COORDINATION
Work performed under this section shall be coordinated with, and approved by the Contracting Officer. A minimum of seven days notice is required prior to start of milling work to minimize impact on activity operations.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
3.1 SURFACE PREPARATION
Clean the pavement surface of excessive dirt, clay or other foreign matter with power brooms and hand brooms immediately prior to the milling operation.
3.2 COLD-MILLING OPERATION
Remove old pavement by cold milling. Ensure that only bituminous pavement is removed and the base course is not disturbed. Make sufficient passes so that the designated area is milled to the grades and cross sections indicated.
The milling shall proceed with care so as not to damage the pavement below the designated grade. Repair or replace damaged manholes, valve boxes, utility lines, or pavement that is torn, cracked, gouged, rutted, broken or undercut. Protect runway lighting system. Repair or replace any component damaged by milling operations. The milled material shall be removed from the pavement and loaded into trucks.
3.3 FIELD QUALITY CONTROL
3.3.1 Grade-Conforming Tests
Test the finished milled surface of the pavement for conformance with the plan-grade requirements and test for acceptance by running lines of levels at intervals of 25 feet longitudinally and 25 feet transversely to determine the elevation of the completed pavement. The finished milled-pavement surfaces shall vary not more than 0.02 feet from the established plan grade line and elevation. Correct variations from the designated gradeline and elevation in
SECTION 02961, Page 2 excess of the plan-grade requirements, as directed. Remove and replace deficient low areas. Skin patching for correcting low areas is not permitted. Correct low areas by removing sufficient material to allow at least 1 inch of asphalt concrete to be placed.
3.4 REMOVAL OF MILLED MATERIAL
Material that is removed shall be transported to central plant for hot-mix or cold-mix recycling and shall become the property of the contractor and removed from the site.
| Spec_32 17 23, PAVEMENT MARKINGS 10-1026C |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 SUBMITTALS |
| 1.3 DELIVERY AND STORAGE |
| 1.4 WEATHER LIMITATIONS |
| 1.5 EQUIPMENT |
| 1.5.1 Paint Applicator |
| 1.5.2 Reflective Media Dispenser |
| 1.5.3 Thermoplastic Application Equipment |
| 1.5.3.1 Mobile Application Equipment |
| 1.5.3.2 Portable Application Equipment |
| 1.6 Method of Measurement |
| 1.7 Basis of payment |
| PART 2 PRODUCTS |
| 2.1 MATERIALS |
| 2.1.1 Paints for Roads and Streets |
| 2.1.2 Reflective Media for Roads and Streets |
| 2.1.3 Thermoplastic Compounds |
| 2.1.3.1 Composition Requirements |
| 2.1.3.2 Physical Properties |
| 2.1.3.3 Primer |
2.1.4 Raised Pavement Markers
| PART 3 EXECUTION |
| 3.1 SURFACE PREPARATION |
| 3.2 APPLICATION |
| 3.2.1 Rate of Application |
| 3.2.1.1 Reflective Markings |
| 3.2.1.2 Nonreflective Markings |
| 3.2.1.3 Thermoplastic Compound |
| 3.2.2 Painting |
| 3.2.3 Reflective Media |
| 3.2.4 Thermoplastic Compound |
| 3.2.5 Raised Pavement Markers |
| 3.3 FIELD TESTING AND INSPECTION |
| 3.3.1 Sampling and Testing |
| 3.3.2 Inspection |
| 3.3.2.1 Surface Preparations and Application Procedures |
3.4 TRAFFIC CONTROL AND PROTECTION
| Spec_01300 SUBMITTAL PROCEDURES 10-1026C |
| PART 1 GENERAL |
| 1.1 SUBMITTAL IDENTIFICATION |
| 1.2 SUBMITTAL CLASSIFICATION |
| 1.2.1 Contracting Officer Approved |
| 1.2.2 Information Only |
| 1.3 APPROVED SUBMITTALS |
| 1.4 DISAPPROVED SUBMITTALS |
| PART 2 PRODUCTS (Not Applicable) |
| PART 3 EXECUTION |
| 3.1 GENERAL |
| 3.2 SUBMITTAL REGISTER |
| 3.3 SCHEDULING |
| 3.4 Deviations |
| 3.5 CONTROL OF SUBMITTALS |
| 3.6 APPROVED SUBMITTALS |
| 3.7 INFORMATION ONLY SUBMITTALS |
Spec_02961 COLD MILLING OF BITUMINOUS PAVEMENT 10-1026C