Attachment_9,_Addendum__1.pdf

PDF 47 KB Posted

Attached to
Repair Boilers Bldg 2001 Federal contract opportunity
Solicitation number
FA301017R0018
Issued by
Department of the Air Force Air Education and Training Command

About this file

Addendum #1

View the file

Other files for this federal contract opportunity

Other files attached to Repair Boilers Bldg 2001, newest first.
File Type Posted
FA301017R00180001.pdf PDF
FA3010-17-R-0018_-_Repair_boilers_BLDG_2001.pdf PDF
Attachment_6_-_SF_1444.pdf PDF
Attachment_4_-_PPQ.doc DOC document
Attachment_3_-_DWG.pdf PDF
Attachment_1_-_SoW.pdf PDF
Attachment_8_-_Wage_Determination.pdf PDF
Attachment_5_-_Reference_List.docx DOCX document
Attachment_2_-_Specifications.pdf PDF
Attachment_7_-__Notice_of_Compliance.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MAHG17-1008

JULY 26, 2017

ADDENDUM #1

The following are changes to the construction documents for the following project:

MAHG17-1008 REPLACE WATER HEATERS BLDG. 2001

KEESLER AFB, MISSISSIPPI

Any information found within these documents shall take precedent over the information contained within the original construction documents. It is the responsibility of the contractor to review the documents and to include any revised or additional information in their bid.

A. Changes to Statement of Work:

Section 1.1 SCOPE:

Add

1. Provide two (2) new 120V/1PH circuits from the breaker panel in the electrical room to the two new disconnect switches reusing the existing conduit. Replace existing breakers with new breakers rated for the supplied water heaters.

2. Replace existing disconnect switches that feed the existing water heaters with new disconnect switches. Provide new conductors from the new disconnect switches to the new water heaters.

Make all terminations, etc. to provide power to the new water heaters. All new conductors are to be rated for the supplied water heaters.

Section 1.3 COMPLETION TIME:

1. The completion date for this project is 120 calendar days from the notice to proceed.

Section 1.15 INTERRUPTION OF UTILITY SERVICE

Add

1. Interruptions to utility services shall be minimized. Necessary outages shall be coordinated with the PAE Applied Technologies LLC Contracting Officer a minimum of 3 weeks in advance of the planned outage. Utility outages will only be permitted on down Fridays and weekends.

B. Changes to Drawings:

1. Add to Note 2, Sheet M2.0 (Sheet 3 of 4), the following: Shutdown shall take place on down

Fridays and weekends only.

2. Append Note 11, Sheet M2.1 (Sheet 4 of 4) as follows:

Provide two (2) new 120V/1PH circuits from the breaker panel in the electrical room to the two new disconnect switches reusing the existing conduit. Replace existing breakers with new breakers rated for the supplied water heaters.

Replace existing disconnect switches that feed the existing water heaters with new disconnect switches. Provide new conductors from the new disconnect switches to the new water heaters.

Make all terminations, etc. to provide power to the new water heaters. All new conductors are to be rated for the supplied water heaters.

C. Changes to Specifications:

1. No change

End of Addendum #1