FA3010-17-R-0008_Addendum_1.pdf

PDF 94 KB Posted

Attached to
Pre-engineered Office Installation Federal contract opportunity
Solicitation number
FA301017R0008
Issued by
Department of the Air Force Air Education and Training Command

About this file

Please see the attached addendum.

View the file

Other files for this federal contract opportunity

Other files attached to Pre-engineered Office Installation, newest first.
File Type Posted
Amendment_5.pdf PDF
Amendment_4.pdf PDF
MAHG169000_Provide_Pre-Engineered_Offices_B4301_Revised_sheets__25_May.pdf PDF
Amendment_3.pdf PDF
Attachment_2_-_MAHG169000_Construct_Offices_Fab_Shop_B4301_DWG_Add1.pdf PDF
FA301017R00080002.pdf PDF
FA3010-17-R-0008-0001.pdf PDF
0008_Answers.docx DOCX document
Pre-Bid_Site_Visit_Sign-In_0008.pdf PDF
Attachment_2,_Drawings.pdf PDF
Attachment_7,_Wage_Determination.pdf PDF
Attachment_3,_PPQ.doc DOC document
FA3010-17-R-0008.pdf PDF
Attachment_6,_Notice_of_Compliance.pdf PDF
Attachment_5,_SF_1444.pdf PDF
Attachment_4,_Reference_List.docx DOCX document
Attachment_1,_Specifications.pdf PDF
Attachment_8,_SOW.pdf PDF
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AD1- 1 ADDENDUM 1

ADDENDUM NO. 1

May 03, 2017

RE: MAHG 169000 CONSTRUCT OFFICES FAB SHOP B4331

Keesler Air Force Base Biloxi, Mississippi

This Addendum consists of 1 page, 0 Specification Sections and 0 Drawing Sheets.

CHANGES TO PROJECT STATEMENT OF WORK (SOW):

1. SOW SECTIONS A.1.a, B.1.a, C.2.a, D.2.a, E.2.a:

Add the following to the Scope of Work (SOW) for all fire suppression additions and or modifications:

Prior to any work on existing fire suppression system Contractor must have a licensed Fire Protection Engineer (FPE) survey the existing fire suppression system to include flow calculations. FPE is to provide digital (AutoCAD and PDF formats) and hard copy drawings of existing fire suppression system. At conclusion of project the contractor is responsible for providing digital (AutoCAD and PDF formats) and hard copy as-built drawings of the modified fire suppression system as well as any related calculations. Government will provide local water system pressures to Contractor. Fire suppression system is to be designed according to UFC 3-600-01 and all other relevant codes.

2. SOW SECTION F.4:

Contractor is to provide 2 layers of pressure treated ¾” plywood glued and screwed together that is 6” larger on all sides than actual equipment. Contractor is to provide elastomeric isolation pads on all corners of equipment.

QUESTIONS AND ANSWERS:

1. Drawing Page A1.0, general note 10 says to provide new fire suppression for new enclosures.

Can the gov. provide a fire suppression specification section and FP drawings?

ANSWER 1: SEE CHANGES TO PROJECT STATEMENT OF WORK NO. 1 ABOVE.

2. Can a basis of design be provided for the pre-engineered office spaces, and /or specifications and elevations?

ANSWER 2: Please see Statement of Work “Provide and Install New” sections for pre-engineered office systems information.

3. Drawing Page M1.0 says that OAU-1 is to be installed on the roof of one of the office spaces, and placed on a 6” pad. Instead of a 6” concrete pad on top of the pre-engineered ceiling, should OAU-1 be mounted on a roof curb, and can a detail be provided?

ANSWER 3: NO a roof curb is not necessary we are not penetrating the metal deck of the office space. The pad in question is a housekeeping pad. SEE CHANGES TO PROJECT

STATEMENT OF WORK NO. 2 ABOVE.

END OF ADDENDUM 1