Attach_1_-_SOW_(15_Nov_13)-.pdf

PDF 121 KB Posted

Attached to
FA2823-15-R-4009* Construct RIG Facility, Site C-3, Eglin AFB Federal contract opportunity
Solicitation number
FA2823-15-R-4001
Issued by
Department of the Air Force Materiel Command Test Center

About this file

Statement of Work

View the file

Other files for this federal contract opportunity

Other files attached to FA2823-15-R-4009* Construct RIG Facility, Site C-3, Eglin AFB, newest first.
File Type Posted
Interested_Vendor_List.pdf PDF
RFI_Responses_for_RIG-19_March_2015_with_Pictures.pdf PDF
Interested_Vendor_List.pdf PDF
FA2823-15-R-4009-03_Amendment_3_CONFORM.pdf.doc.pdf PDF
FA2823-15-R-4009-03_Amendment_3.pdf.doc.pdf PDF
FA2823-15-R-4009-02_Amendment_2.pdf PDF
FA2823-15-R-4009-01_Amendment.pdf PDF
FA2823-15-R-4009-SOLICITATION.pdf PDF
ATTACHMENT_E_-_Drawings_ _Specs.pdf PDF
121174_SPEC_CONSTRUCT_RIG_FACILITY.pdf PDF
Attach_2 3_-_Drawings_ _Specs.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1

CONSTRUCT RIG FACILITY

SITE C-3

FTFA 12 1174

SPEC. # 13AF

DRAWING # 13AF

Statement of Work

Eglin Air Force Base

Florida

15 November 2013

Attachment 1

STATEMENT OF WORK

FTFA121174, CONSTRUCT RIG FACILITY SITE C-3

1.1 GENERAL INTENTION

It is the declared and acknowledged intention and meaning to provide and secure the construction for the Construct Rig Facility Site C-3 FTFA 12-1174, Eglin Air Force Base, Florida.

1.2 GENERAL DESCRIPTION

In general, the work consists of the following:

Construct new conditioned concrete masonry building with metal roof, interior galvanized metal stud walls with gypsum board painted finish, acoustical and gypsum board ceilings, floor and wall finishes, toilet facilities, server room, training room, workroom, offices and storage. Miscellaneous specialties include signage, fire extinguishers, shelving, etc). Support utilities include lighting, security, plumbing and HVAC systems.

The above general description of work does not in any way limit the responsibility of the Contractor to perform all work and furnish all labor, materials, and equipment complete in accordance with the plans and specifications.

1.3 NOTICE OF CHANGE TO DRAWING AND SPECIFICATIONS

In the Drawings and Specifications, references to “Option 1” are to be changed to read “Additive 2”.

1.4 ADDITIVES

ADDITIVE 1: Use integrally colored split face cmu in lieu of painted smooth face cmu.

ADDITIVE 2: Construction of building with larger square footage in lieu of smaller building called for in Base Bid.

1.5 LOCATION

The work shall be located at Site C-3, Eglin Air Force Base, Florida. The exact location of the facility is indicated on the drawings.

1.6 PERIOD OF PERFROMANCE

The Period of Performance will be 300 calendar days.