FA2823-11-R-0023 Replace HVAC Navy Dorms.doc
DOC document 341 KB Posted
- Attached to
- Replace HVAC Navy Dorms Federal contract opportunity
- Solicitation number
- FA2823-11-R-0023
About this file
Solicitation FA2823-11-R-0023 Replace HVAC Navy Dorms
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Q and A 26 August 11.docx | DOCX document | |
| Q and A 25 August 2011.pdf | ||
| Drawings dated 11 June 2011.pdf | ||
| Specifications dated 11 June 2011.pdf | ||
| https //www.fbo.gov/index s opportunity mode form id e219ff23e2c5dc97fcfbfffa09f60a69 tab core _cview 0 | — | |
| Drawings FTFA 09-1120.pdf | ||
| Specifications FTFA 09-1120.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section B - Supplies or Services and Prices
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1 |
| Lump Sum |
FTFA 09-1120, Replace HVAC in Navy Dorms
FFP
FTFA 09-1120, Replace HVAC in Navy Dorms on Eglin AFB, FL. Furnish all labor, equipment and materials to replace HVAC systems in accordance with the Specifications dated 11 June 2011 and the Drawings dated 11 June 2011. Funds provided by NAVY “Contemplated”. THIS CLIN IS SUBJECT TO THE STATUTORY COST LIMITATION CITED IN DFARS 252.236-7006 OF $5,000,000.
FOB: Destination
PURCHASE REQUEST NUMBER: F1T2BR1154A001
SIGNAL CODE: A
NET AMT
CLAUSES INCORPORATED BY FULL TEXT
A201. LINE ITEMS
THE FOLLOWING CONTRACT LINE ITEMS ARE FIRM FIXED PRICE: CLIN 0001
Section C - Descriptions and Specifications
CLAUSES INCORPORATED BY FULL TEXT
| C-1 |
| SPECIFICATIONS, STANDARDS AND DRAWINGS (IAW FAR 11.201) |
Specifications, standards or drawings (as applicable) are furnished/listed below:
ITEM NR SPECIFICATIONS, STANDARDS AND/OR ATTACHMENTS
SPECIFICATIONS
SEE ATTACHMENT 1
DRAWINGS
SEE ATTACHMENT 2
Section E - Inspection and Acceptance
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
| CLIN |
| INSPECT AT |
| INSPECT BY |
| ACCEPT AT |
| ACCEPT BY |
| 0001 |
| N/A |
| N/A |
| N/A |
| Government |
CLAUSES INCORPORATED BY REFERENCE
| 52.246-12 |
| Inspection of Construction |
| AUG 1996 |
Section F - Deliveries or Performance
DELIVERY INFORMATION
| CLIN |
| DELIVERY DATE |
| QUANTITY |
| SHIP TO ADDRESS |
| UIC |
| 0001 |
| 450 dys. ADC |
| 1 |
| 96 CEG/CEP - F1T2BR |
MARK NELSON
501 DE LEON ST BLDG 696 STE
1 RM 49
EGLIN AFB FL 32542
850-883-1361
FOB: Destination
F1T2BR
CLAUSES INCORPORATED BY REFERENCE
| 52.247-34 |
| F.O.B. Destination |
| NOV 1991 |
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 (ten) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 450 (four hundred fifty) calendar days after the receipt of Notice to Proceed.
** The time stated for completion shall include final cleanup of the premises.
(End of clause)
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $285.42 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
Section H - Special Contract Requirements
CLAUSES INCORPORATED BY FULL TEXT
| H-025 |
| INCORPORATION OF SECTION K |
| OCT 1998 |
Section K of the solicitation is hereby incorporated by reference.
| H-800 |
| IMPLEMENTATION OF WARRANTY–CONSTRUCTION |
| JAN 2000 |
(a) Any manufacturer’s warranties which extend beyond or in addition to the normal one year warranty required by FAR 52.246-21 shall be furnished to the government in their entirety, including the names of vendors responsible for servicing these warranties.
(b) Prior to final acceptance of the work covered by this contract, the contractor shall furnish in writing to the Contracting Officer a list of all items of equipment furnished. This list will be accompanied by the applicable warranty documentation. This list shall include;
(i) Nomenclature of the item, type and serial number where applicable, and name and address of the manufacturer.
(ii) Cost
(iii) Period of warranty
(iv) Name, address and telephone number of the subcontractor or supplier
(v) Name, address and telephone number of the servicing agency that will be responsible for the warranty service.
CLAUSES INCORPORATED BY FULL TEXT
| H-801 |
| MEDICAL INFORMATION |
| JAN 2000 |
The name of the Contractor’s physician(s) and preferred hospital (for use in the event of industrial injury of employees) shall be posted by the Contractor at the site of the work in a prominent place where it can easily be seen by the workers. This information shall also be furnished to the Director of Base Medical Services, 96 MDG/SG, Eglin AFB FL 32542-5300.
| H-803 |
| INSPECTION AND SURVEILLANCE |
| JAN 2000 |
The Director, Civil Engineering, Eglin Air Force Base, Florida, is designated as the representative of the Contracting Officer for the purpose of surveillance and inspection of performance of work under this contract. This designation does not include authority to direct or authorize the Contractor to make changes in the scope or terms of the contract without the written authority of the Contracting Officer. Contractor shall notify Construction Management Branch, 96 CEG/CEPDR, Mr. Mark Nelson, office telephone (850) 883-1361 at least 24 hours in advance of the date work will commence under this contract; contractor shall also notify that office at earliest possible time of anticipated absence(s) from the job site.
| H-807 |
| ON-BASE PERFORMANCE |
| JAN 2000 |
(a) Work on this project shall be accomplished during normal hours, which are 7:00 AM to 3:30 PM, Monday through Friday, except legal holidays. Any work desired to be accomplished during other than the normal hours will require prior approval of the Contracting Officer. The Contractor must submit a written request to the Contracting Officer.
(b) The Contractor’s performance may be interrupted from time to time because of high priority mission schedules. For each calendar day and/or portion of a calendar day that the contractor is removed from the job site, the contract schedule will be adjusted by one (1) calendar day.
(c) If building remains occupied throughout construction, special provisions apply as follows: ______NONE__________________________________________________________________________________________________________________________________________________________________________
CLAUSES INCORPORATED BY FULL TEXT
| H-810 |
| HURRICANE SEASON |
| JAN 2000 |
Hurricane season for the state of Florida is normally the period from 01 June through 30 November. During an actual hurricane, tropical storm or tropical depression condition, you may be contacted by the contracting office and requested to secure equipment, clean up your work area and properly protect stored materials. In accordance with the contract clause FAR 52.236-9, “Protection of Existing Vegetation, Structures, Equipment, Utilities and Improvements” and FAR 52.236-12 “Cleaning Up,” you should keep this in mind and maintain your work area free from debris and in a safe and secure condition at the completion of each work day. A duty is imposed on the Contractor to monitor local weather conditions, weather bulletins and base closure information in the local media. The Contractor must contact the Contract Administrator with a report of conditions adversely affecting the construction site.
| H-811 |
| CONSTRUCTION PERMITS |
| APR 2009 |
In accordance with (IAW) FAR 52.236-7, the Contractor shall obtain a construction permit for any construction work on Eglin Air Force Base. An AF Form 103 “Base Civil Engineering Work Clearance Request” must be submitted with all required signatures, to the Contract Inspector prior to beginning of performance on the job site. No work shall begin until approval of the AF Form 103 has been granted.
| H-817 |
| UTILITIES |
| JAN 2000 |
All reasonable required amounts of water and electric power will be made available to the Contractor by the Government without cost to the Contractor.
| H-818 |
| UTILITY OUTAGES |
| JAN 2000 |
Contractor shall notify the Contracting Officer’s Representative (COR) in writing two weeks prior to any utility outage anticipated during the performance of this contract.
| H-820 |
| SALVAGE MATERIALS |
| JAN 2000 |
(a) All items of Government property indicated on the drawings or in the specifications to be removed and disposed of by the contractor shall become the property of the contractor and shall be removed promptly from the Eglin AFB Reservation and legally disposed of EXCEPT _NONE________.
(b) Contractors are encouraged to recycle salvage materials when possible. Contact the Eglin Recycling Center, 850-882-7744 ext. 624, for assistance.
CLAUSES INCORPORATED BY FULL TEXT
| H-825 |
| ASBESTOS REMOVAL REQUIREMENTS |
| OCT 1992 |
The contractor shall comply with the applicable requirements of 29 CFR 1910.1001 and 40 CFR 61, Subparts A and M and with laws, ordinances, rules and regulations of federal, state, and local authorities regarding handling, transporting, and disposing of asbestos waste materials. Where the requirements of this specification and referenced documents vary, the most stringent requirements shall apply.
| H-829 |
| HAZARDOUS WASTE REMOVAL |
| JAN 2000 |
The Contractor shall dispose of all hazardous waste in accordance with all applicable local, federal and state environmental laws and regulations, including but not limited to 40 CFR 260-268, Hazardous Waste Management, and Rule 17-30 Florida Administrative Code. The Contractor shall assume the responsibility of determining what constitutes “hazardous waste” and complying with all environmental laws and regulations governing its removal.
| H-837 |
| DAILY REPORT TO INSPECTOR |
| JAN 2000 |
(a) The Contractor shall submit a Daily Report to 96 CEG/CEPDR inspector on AAC Form 3 or 4003. The report shall include weather conditions, work accomplished, test accomplished, test reports, delays and discrepancies.
(b) The report to the inspector shall be the original signed by the contractor or his superintendent and turned into 96 CEG/CEPDR inspector by 12:00 noon the following work day.
| H-841 |
| SUPERINTENDENT |
| APR 2010 |
Upon notification of award, the Prime Contractor shall identify a superintendent and alternate for this contract and job site. The full name, home address, SSN#, date of birth, state driver’s license #, days/hours of access required, and consent to a background check for security purposes of each such employee shall be required. The Prime Contractor’s superintendent and/or alternate shall be accountable for all individuals allowed onto the installation. The privilege of a potential employee being allowed access should be considered in all hiring and subcontracting decisions. The U.S. Air Force will not be responsible or liable for any costs or delays that a contractor incurs due to a contractor’s employee being denied access to Eglin AFB. The Superintendent and/or alternate shall be responsible for collecting badges/PVC cards from all employees upon completion of the project/contract or termination of service. Prior to final payment the Superintendent must provide proof to the contracting officer of collection/turn-in of all badges for employees granted base access in support of this project/job.
| H-842 |
| WEATHER DELAYS |
| MAY 2003 |
The Anticipated Normal Weather Delay Schedule shown below is developed by month for this geographic location using National Oceanic and Atmospheric Administration (NOAA) and similar Weather Averaging System data for the project’s general location. The Government has included additional time in the allowed performance period using this data. (The basic performance period allows seven calendar days for every five-day working days assuming based on working Monday through Friday. The contractor’s progress schedule must take these anticipated adverse weather delays into account in all weather-dependent activities to ensure timely completion of the job.
MONTHLY ANITCIPATED ADVERSE WEATHER DELAY
WORK DAYS BASED ON A 5-DAY WORKWEEK
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
NOV
DEC
Upon acknowledgement of Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on his Daily Report (AAC Form 3), the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for fifty percent or more of the Contractor’s scheduled workday and must cause a delay in the work activities critical to contract completion. In order to obtain relief from contract schedule requirements, the Contractor will have to demonstrate not only that the anticipated amount of weather delay was exceeded by actual weather interruption, but also that reasonable efforts were made to compensate for such excess interruptions through changes in work hours, changes in the planned sequence of work, increased concurrent activities, or other available measures. Contemporaneous documentation of such efforts and prompt coordination thereof with government inspectors is encouraged (see below).
In the event that all reasonable effort to complete the required performance on schedule fail and it is determined that excessive inclement weather was the cause of that failure, the Contractor may request extension of the project performance period for any weather delays suffered because of adverse weather beyond the number day indicated on the chart. The number of workdays of delay added to the schedule shall be converted to calendar days by adding the appropriate number of weekend days associated with that number of workdays.
(1) Adverse weather days will not be granted for other than normal workdays that the Contractor requested to work solely for the Contractor’s convenience to meet the contract performance period.
(2) Any extensions to the contract because of change orders will have the normal adverse weather days figured into the extension period.
(3) If the contract dictates an alternate performance period other than a normal Monday through Friday five-day workweek, an extension will be considered based on the contract requirement for a workday.
Upon the request of the Contractor made within one workweek after the relevant events, the government inspector will review the Contractor’s documentation of weather delays and circumstances relevant to the availability of work-arounds and promptly confirm or dispute the Contractor’s conclusions in writing to the Contractor and the Contracting Officer. If the Contractor requests an adjustment to the contract schedule based on the government inspector’s review, the contractor shall notify the Contracting Officer in writing and provide relevant information and recommendations regarding the request. The Contracting Officer shall determine whether the request should be promptly granted, deferred pending determination of cumulative weather effects during the contract performance period, denied, or some combination thereof. The reason for any deferral or denial will be simultaneously communicated to the Contractor in writing.
The findings of the Contracting Officer shall be final and conclusive subject to appeal under the Disputes clause. Upon any extension, the Contractor shall immediately submit to the Contracting Officer a revised progress schedule to meet the revised performance period.
Section I - Contract Clauses
CLAUSES INCORPORATED BY REFERENCE
| 52.202-1 |
| Definitions |
| JUL 2004 |
| 52.203-3 |
| Gratuities |
| APR 1984 |
| 52.203-5 |
| Covenant Against Contingent Fees |
| APR 1984 |
| 52.203-7 |
| Anti-Kickback Procedures |
| OCT 2010 |
| 52.203-8 |
| Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity |
| JAN 1997 |
| 52.203-10 |
| Price Or Fee Adjustment For Illegal Or Improper Activity |
| JAN 1997 |
| 52.203-12 |
| Limitation On Payments To Influence Certain Federal Transactions |
| OCT 2010 |
| 52.204-4 |
| Printed or Copied Double-Sided on Postconsumer Fiber Content Paper |
| MAY 2011 |
| 52.204-7 |
| Central Contractor Registration |
| APR 2008 |
| 52.204-9 |
| Personal Identity Verification of Contractor Personnel |
| JAN 2011 |
| 52.209-6 |
| Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment |
| DEC 2010 |
| 52.215-21 |
| Requirements for Certified Cost or Pricing Data or Information Other Than Certified Cost or Pricing Data--Modifications |
| OCT 2010 |
| 52.219-8 |
| Utilization of Small Business Concerns |
| JAN 2011 |
| 52.219-9 |
| Small Business Subcontracting Plan |
| JAN 2011 |
| 52.222-3 |
| Convict Labor |
| JUN 2003 |
| 52.222-4 |
| Contract Work Hours and Safety Standards Act - Overtime Compensation |
| JUL 2005 |
| 52.222-6 |
| Davis Bacon Act |
| JUL 2005 |
| 52.222-7 |
| Withholding of Funds |
| FEB 1988 |
| 52.222-8 |
| Payrolls and Basic Records |
| JUN 2010 |
| 52.222-9 |
| Apprentices and Trainees |
| JUL 2005 |
| 52.222-10 |
| Compliance with Copeland Act Requirements |
| FEB 1988 |
| 52.222-11 |
| Subcontracts (Labor Standards) |
| JUL 2005 |
| 52.222-12 |
| Contract Termination-Debarment |
| FEB 1988 |
| 52.222-13 |
| Compliance with Davis-Bacon and Related Act Regulations. |
| FEB 1988 |
| 52.222-14 |
| Disputes Concerning Labor Standards |
| FEB 1988 |
| 52.222-15 |
| Certification of Eligibility |
| FEB 1988 |
| 52.222-21 |
| Prohibition Of Segregated Facilities |
| FEB 1999 |
| 52.222-26 |
| Equal Opportunity |
| MAR 2007 |
| 52.222-27 |
| Affirmative Action Compliance Requirements for Construction |
| FEB 1999 |
| 52.222-35 |
| Equal Opportunity for Veterans |
| SEP 2010 |
| 52.222-36 |
| Affirmative Action For Workers With Disabilities |
| OCT 2010 |
| 52.222-37 |
| Employment Reports on Veterans |
| SEP 2010 |
| 52.222-50 |
| Combating Trafficking in Persons |
| FEB 2009 |
| 52.222-54 |
| Employment Eligibility Verification |
| JAN 2009 |
| 52.223-3 |
| Hazardous Material Identification And Material Safety Data |
| JAN 1997 |
| 52.223-5 |
| Pollution Prevention and Right-to-Know Information |
| MAY 2011 |
| 52.223-6 |
| Drug-Free Workplace |
| MAY 2001 |
| 52.223-18 |
| Contractor Policy to Ban Text Messaging While Driving |
| SEP 2010 |
| 52.225-13 |
| Restrictions on Certain Foreign Purchases |
| JUN 2008 |
| 52.227-1 |
| Authorization and Consent |
| DEC 2007 |
| 52.227-2 |
| Notice And Assistance Regarding Patent And Copyright Infringement |
| DEC 2007 |
| 52.227-4 |
| Patent Indemnity-Construction Contracts |
| DEC 2007 |
| 52.228-1 |
| Bid Guarantee |
| SEP 1996 |
| 52.228-2 |
| Additional Bond Security |
| OCT 1997 |
| 52.228-5 |
| Insurance - Work On A Government Installation |
| JAN 1997 |
| 52.228-11 |
| Pledges Of Assets |
| SEP 2009 |
| 52.228-12 |
| Prospective Subcontractor Requests for Bonds |
| OCT 1995 |
| 52.228-14 |
| Irrevocable Letter of Credit |
| DEC 1999 |
| 52.228-15 |
| Performance and Payment Bonds--Construction |
| OCT 2010 |
| 52.229-3 |
| Federal, State And Local Taxes |
| APR 2003 |
| 52.232-5 |
| Payments under Fixed-Price Construction Contracts |
| SEP 2002 |
| 52.232-23 |
| Assignment Of Claims |
| JAN 1986 |
| 52.232-27 |
| Prompt Payment for Construction Contracts |
| OCT 2008 |
| 52.232-33 |
| Payment by Electronic Funds Transfer--Central Contractor Registration |
| OCT 2003 |
| 52.233-1 |
| Disputes |
| JUL 2002 |
| 52.233-3 |
| Protest After Award |
| AUG 1996 |
| 52.236-2 |
| Differing Site Conditions |
| APR 1984 |
| 52.236-3 |
| Site Investigation and Conditions Affecting the Work |
| APR 1984 |
| 52.236-5 |
| Material and Workmanship |
| APR 1984 |
| 52.236-6 |
| Superintendence by the Contractor |
| APR 1984 |
| 52.236-7 |
| Permits and Responsibilities |
| NOV 1991 |
| 52.236-8 |
| Other Contracts |
| APR 1984 |
| 52.236-9 |
| Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements |
| APR 1984 |
| 52.236-10 |
| Operations and Storage Areas |
| APR 1984 |
| 52.236-11 |
| Use and Possession Prior to Completion |
| APR 1984 |
| 52.236-12 |
| Cleaning Up |
| APR 1984 |
| 52.236-13 |
| Accident Prevention |
| NOV 1991 |
| 52.236-14 |
| Availability and Use of Utility Services |
| APR 1984 |
| 52.236-15 |
| Schedules for Construction Contracts |
| APR 1984 |
| 52.236-17 |
| Layout of Work |
| APR 1984 |
| 52.236-26 |
| Preconstruction Conference |
| FEB 1995 |
| 52.236-27 Alt I |
| Site Visit (Construction) (Feb 1995) - Alternate I |
| FEB 1995 |
| 52.242-13 |
| Bankruptcy |
| JUL 1995 |
| 52.242-14 |
| Suspension of Work |
| APR 1984 |
| 52.243-4 |
| Changes |
| JUN 2007 |
| 52.244-5 |
| Competition In Subcontracting |
| DEC 1996 |
| 52.244-6 |
| Subcontracts for Commercial Items |
| DEC 2010 |
| 52.246-21 |
| Warranty of Construction |
| MAR 1994 |
| 52.248-1 |
| Value Engineering |
| OCT 2010 |
| 52.248-3 |
| Value Engineering-Construction |
| OCT 2010 |
| 52.249-2 |
| Termination For Convenience Of The Government (Fixed-Price) |
| MAY 2004 |
| 52.249-2 Alt I |
| Termination for Convenience of the Government (Fixed-Price) (May 2004) - Alternate I |
| SEP 1996 |
| 52.249-10 |
| Default (Fixed-Price Construction) |
| APR 1984 |
| 52.253-1 |
| Computer Generated Forms |
| JAN 1991 |
| 252.201-7000 |
| Contracting Officer's Representative |
| DEC 1991 |
| 252.203-7000 |
| Requirements Relating to Compensation of Former DoD Officials |
| JAN 2009 |
| 252.203-7001 |
| Prohibition On Persons Convicted of Fraud or Other Defense-Contract-Related Felonies |
| DEC 2008 |
| 252.203-7002 |
| Requirement to Inform Employees of Whistleblower Rights |
| JAN 2009 |
| 252.204-7003 |
| Control Of Government Personnel Work Product |
| APR 1992 |
| 252.204-7004 Alt A |
| Central Contractor Registration (52.204-7) Alternate A |
| SEP 2007 |
| 252.205-7000 |
| Provision Of Information To Cooperative Agreement Holders |
| DEC 1991 |
| 252.209-7004 |
| Subcontracting With Firms That Are Owned or Controlled By The Government of a Terrorist Country |
| DEC 2006 |
| 252.223-7006 |
| Prohibition On Storage And Disposal Of Toxic And Hazardous Materials |
| APR 1993 |
| 252.225-7012 |
| Preference For Certain Domestic Commodities |
| JUN 2010 |
| 252.227-7033 |
| Rights in Shop Drawings |
| APR 1966 |
| 252.232-7003 |
| Electronic Submission of Payment Requests and Receiving Reports |
| MAR 2008 |
| 252.232-7010 |
| Levies on Contract Payments |
| DEC 2006 |
| 252.236-7000 |
| Modification Proposals-Price Breakdown |
| DEC 1991 |
| 252.236-7006 |
| Cost Limitation |
| JAN 1997 |
| 252.239-7001 |
| Information Assurance Contractor Training and Certification |
| JAN 2008 |
| 252.243-7001 |
| Pricing Of Contract Modifications |
| DEC 1991 |
| 252.243-7002 |
| Requests for Equitable Adjustment |
| MAR 1998 |
| 252.244-7000 |
| Subcontracts for Commercial Items and Commercial Components (DoD Contracts) |
| NOV 2010 |
| 252.247-7023 |
| Transportation of Supplies by Sea |
| MAY 2002 |
| 252.247-7024 |
| Notification Of Transportation Of Supplies By Sea |
| MAR 2000 |
52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (APR 2009)
(a) Definitions. As used in this clause--
Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.
Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is ``not dominant in its field of operation'' when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.
(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:
(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.
(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.
(3) For long-term contracts--
(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and
(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.
(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/services/contractingopportunities/sizestandardstopics/.
(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.
(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the rerepresentation required by paragraph (b) of this clause by validating or updating all its representations in the Online Representations and Certifications Application and its data in the Central Contractor Registration, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.
(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.
(g) If the Contractor does not have representations and certifications in ORCA, or does not have a representation in ORCA for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:
The Contractor represents that it ( ) is, ( ) is not a small business concern under NAICS Code238220 assigned to contract number .
(Contractor to sign and date and insert authorized signer's name and title).
(End of clause)
CLAUSES INCORPORATED BY FULL TEXT
52.223-3 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA (JAN 1997)
(a) "Hazardous material", as used in this clause, includes any material defined as hazardous under the latest version of Federal Standard No. 313 (including revisions adopted during the term of the contract).
(b) The offeror must list any hazardous material, as defined in paragraph (a) of this clause, to be delivered under this contract. The hazardous material shall be properly identified and include any applicable identification number, such as National Stock Number or Special Item Number. This information shall also be included on the Material Safety Data Sheet submitted under this contract.
Material
Identification No.
(If none, insert "None")
(c) This list must be updated during performance of the contract whenever the Contractor determines that any other material to be delivered under this contract is hazardous.
(d) The apparently successful offeror agrees to submit, for each item as required prior to award, a Material Safety Data Sheet, meeting the requirements of 29 CFR 1910.1200(g) and the latest version of Federal Standard No. 313, for all hazardous material identified in paragraph (b) of this clause. Data shall be submitted in accordance with Federal Standard No. 313, whether or not the apparently successful offeror is the actual manufacturer of these items. Failure to submit the Material Safety Data Sheet prior to award may result in the apparently successful offeror being considered nonresponsible and ineligible for award.
(e) If, after award, there is a change in the composition of the item(s) or a revision to Federal Standard No. 313, which renders incomplete or inaccurate the data submitted under paragraph (d) of this clause, the Contractor shall promptly notify the Contracting Officer and resubmit the data.
(f) Neither the requirements of this clause nor any act or failure to act by the Government shall relieve the Contractor of any responsibility or liability for the safety of Government, Contractor, or subcontractor personnel or property.
(g) Nothing contained in this clause shall relieve the Contractor from complying with applicable Federal, State, and local laws, codes, ordinances, and regulations (including the obtaining of licenses and permits) in connection with hazardous material.
(h) The Government's rights in data furnished under this contract with respect to hazardous material are as follows:
(1) To use, duplicate and disclose any data to which this clause is applicable. The purposes of this right are to--
(i) Apprise personnel of the hazards to which they may be exposed in using, handling, packaging, transporting, or disposing of hazardous materials;
(ii) Obtain medical treatment for those affected by the material; and
(iii) Have others use, duplicate, and disclose the data for the Government for these purposes.
(2) To use, duplicate, and disclose data furnished under this clause, in accordance with subparagraph (h)(1) of this clause, in precedence over any other clause of this contract providing for rights in data.
(3) The Government is not precluded from using similar or identical data acquired from other sources.
(End of clause)
CLAUSES INCORPORATED BY FULL TEXT
52.223-4 RECOVERED MATERIAL CERTIFICATION (MAY 2008)
As required by the Resource Conservation and Recovery Act of 1976 (42 U.S.C. 6962(c)(3)(A)(i)), the offeror certifies, by signing this offer, that the percentage of recovered materials content for EPA-designated items to be delivered or used in the performance of the contract will be at least the amount required by the applicable contract specifications or other contractual requirements.
(End of provision)
CLAUSES INCORPORATED BY FULL TEXT
52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPA-DESIGNATED ITEMS (MAY 2008)
(a) Definitions. As used in this clause--
Postconsumer material means a material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item. Postconsumer material is a part of the broader category of “recovered material.”
Recovered material means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.
(b) The Contractor, on completion of this contract, shall--
(1) Estimate the percentage of the total recovered material content for EPA-designated item(s) delivered and/or used in contract performance, including, if applicable, the percentage of post-consumer material content; and
(2) Submit this estimate to Contracting Officer.
(End of clause)
CLAUSES INCORPORATED BY FULL TEXT
52.223-17 AFFIRMATIVE PROCUREMENT OF EPA-DESIGNATED ITEMS IN SERVICE AND CONSTRUCTION CONTRACTS (MAY 2008)
(a) In the performance of this contract, the Contractor shall make maximum use of products containing recovered materials that are EPA-designated items unless the product cannot be acquired—
(1) Competitively within a timeframe providing for compliance with the contract performance schedule;
(2) Meeting contract performance requirements; or
(3) At a reasonable price.
(b) Information about this requirement is available at EPA's Comprehensive Procurement Guidelines web site, http://www.epa.gov/cpg/. The list of EPA-designated items is available at http://www.epa.gov/cpg/products.htm.
(End of clause)
CLAUSES INCORPORATED BY FULL TEXT
52.225-9 BUY AMERICAN ACT—CONSTRUCTION MATERIALS (SEP 2010)
(a) Definitions. As used in this clause--
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is--
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in section 3 of the Shipping Act of 1984 (46 U.S.C. App. 1702), such as agricultural products and petroleum products.
Component means an article, material, or supply incorporated directly into a construction material.
Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means--
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means--
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if--
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
Foreign construction material means a construction material other than a domestic construction material.
United States means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements the Buy American Act (41 U.S.C. 10a-10d) by providing a preference for domestic construction material. In accordance with 41 U.S.C. 431, the component test of the Buy American Act is waived for construction material that is a COTS item (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American Act. (1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including--
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American Act applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American Act applies, use of foreign construction material is noncompliant with the Buy American Act.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction material description Unit of measure Quantity Price (dollars) \1\
Item 1
Foreign construction material
Domestic construction material
Item 2
Foreign construction material
Domestic construction material
Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).
List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.
Include other applicable supporting information.
(End of clause)
52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004)
United States law will apply to resolve any claim of breach of this contract.
(End of clause)
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
http://www.farsite.hill.af.mil http://www.farsite.hill.af.mil/VFDFARA.HTM http://www.farsite.hill.af.mil/VFAFARa.HTM (End of clause)
52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (APR 1984)
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.
(b) The use in this solicitation or contract of any Defense Federal Acquisition Regulation (48 CFR Chapter 2) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
(End of clause)
252.204-7006 BILLING INSTRUCTIONS (OCT 2005)
When submitting a request for payment, the Contractor shall--
(a) Identify the contract line item(s) on the payment request that reasonably reflect contract work performance; and
(b) Separately identify a payment amount for each contract line item included in the payment request.
(End of clause)
252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)
(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.
(b) The Contractor shall--
(1) Check all drawings furnished immediately upon receipt;
(2) Compare all drawings and verify the figures before laying out the work;
(3) Promptly notify the Contracting Officer of any discrepancies;
(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and
(5) Reproduce and print contract drawings and specifications as needed.
(c) In general--
(1) Large-scale drawings shall govern small-scale drawings; and
(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.
(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:
Title
File
Pages
Replace HVAC Navy Dorms Specifications dated 11 June 2011
Replace HVAC Navy Dorms Drawings dated 11 June 2011
(End of clause)
5352.201-9101 OMBUDSMAN (APR 2010)
(a) An ombudsman has been appointed to hear and facilitate the resolution of concerns from offerors, potential offerors, and others for this acquisition. When requested, the ombudsman will maintain strict confidentiality as to the source of the concern. The existence of the ombudsman does not affect the authority of the program manager, contracting officer, or source selection official. Further, the ombudsman does not participate in the evaluation of proposals, the source selection process, or the adjudication of protests or formal contract disputes. The ombudsman may refer the party to another official who can resolve the concern.
(b) Before consulting with an ombudsman, interested parties must first address their concerns, issues, disagreements, and/or recommendations to the contracting officer for resolution. Consulting an ombudsman does not alter or postpone the timelines for any other processes (e.g., agency level bid protests, GAO bid protests, requests for debriefings, employee-employer actions, contests of OMB Circular A-76 competition performance decisions).
(c) If resolution cannot be made by the contracting officer, concerned parties may contact the Center/MAJCOM or AFISRA ombudsmen, Brig Gen David A. Harris, AAC/CS, 101 West D Avenue, Suite 116, Eglin AFB, FL 32542-5495, Commercial: (850) 882-5422, DSN: 872-5422. Concerns, issues, disagreements, and recommendations that cannot be resolved at the MAJCOM/DRU or ARISRA level, may be brought by the concerned party for further consideration to the Air Force ombudsman, Associate Deputy Assistant Secretary (ADAS) (Contracting), SAF/AQC, 1060 Air Force Pentagon, Washington DC 20330-1060, phone number (703) 588-7004, facsimile number (703) 588-1067.
(d) The ombudsman has no authority to render a decision that binds the agency.
(e) Do not contact the ombudsman to request copies of the solicitation, verify offer due date, or clarify technical requirements. Such inquiries shall be directed to the Contracting Officer.
5352.223-9001 HEALTH AND SAFETY ON GOVERNMENT INSTALLATIONS (JUN 1997)
(a) In performing work under this contract on a Government installation, the contractor shall:
(1) Comply with the specific health and safety requirements established by this contract;
(2) Comply with the health and safety rules of the Government installation that concern related activities not directly addressed in this contract;
(3) Take all reasonable steps and precautions to prevent accidents and preserve the health and safety of contractor and Government personnel performing or in any way coming in contact with the performance of this contract; and
(4) Take such additional immediate precautions as the contracting officer may reasonably require for health and safety purposes.
(c) The contracting officer may, by written order, direct Air Force Occupational Safety and Health Standards (AFOSH) and/or health/safety standards as may be required in the performance of this contract and any adjustments resulting from such direction will be in accordance with the Changes clause of this contract.
(d) Any violation of these health and safety rules and requirements, unless promptly corrected as directed by the contracting officer, shall be grounds for termination of this contract in accordance with the Default clause of this contract.
| 5352.242-9000 |
| Contractor Access to Air Force InstallationS |
| (AUGUST 2007) |
(a) The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.
(b) The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter is required regardless of the length of visit and will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the contract specialist for processing into the Security Forces data base. Contractors requiring base access for meetings or site visits must complete the Eglin CAB (Contractor Access Badge) Affidavit. Contractors requiring access to work on base will need to complete the Eglin CAB Affidavit and a Form I-9 (Employment Eligibility Verification). These documents must be delivered to the Eglin AFB East Gate Pass and ID Office in a sealed envelope with a point of contact (POC) and phone number on the front of the envelope. You may also mail or FEDX the documents to:
96 Security Forces Squadron, Bldg 272
302 West D Ave
Eglin AFB FL 32542
Attn Pass & Registration
Anticipate a three-day lead time for Security Forces to process the documents and conduct the required background check. Once the background check is complete, a copy will be returned to the POC listed on the envelope. The prime contractor can provide paperwork for their subcontractor(s) and submit as many documents per envelope as necessary.
(c) When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver’s license, current vehicle registration, valid vehicle insurance certificate and social security card to obtain a vehicle pass. All deliveries to contractor work sites on Eglin AFB main base must go through the North Gate, located off SR-85 South. Trucks trying to enter the East, West or the ACC gate will be turned around and told to use the North Gate. Contractors’ work trucks carrying equipment and tools are also required to use the North Gate.
(d) During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.
(e) When work under this contract requires unescorted entry to controlled or restricted areas, the contractor shall comply with AFI 31-101, Volume 1, The Air Force Installation Security Program, and AFI 31-501, Personnel Security Program Management citing the appropriate paragraphs as applicable.
(f) Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.
(g) Failure to comply with these requirements may result in withholding of final payment.
(End of clause) Section J - List of Documents, Exhibits and Other Attachments
CLAUSES INCORPORATED BY FULL TEXT
PART III- LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
SECTION J
LIST OF ATTACHMENTS
(All listed attachments are at the end of this document)
| TITLE |
| DATE |
| NUMBER OF PAGES |
Wide Area Workflow Instructions
Wage Rate/General Decision No. FL100128
| Undated 01/21/2011 |
| 1 |
| Specification No. FTFA 09-1120 (Attachment 1) |
| 11 June 2011 |
| 490 |
| Drawing No. 09-1120 (Attachment 2) |
| 11 June 2011 |
| 124 |
WIDE AREA WORK FLOW DODAAC AND EMAIL DISTRIBUTION TABLE
SF 1442
THE FOLLOWING CODES WILL BE REQUIRED TO ROUTE YOUR INVOICES AND ADDITIONAL EMAILS CORRECTLY THROUGH WAWF:
Invoice Type: CONSTRUCTION PAYMENT INVOICE *Contract Number: See Block #4 of the award
*Issue Date: See Block #3 of the award
Issue By DODAAC: See Block #7 of the award
*Admin DODAAC: See Block #26 of the award
*Inspected By DODAAC / BPN: F1T2BR
*Contracting Officer Code: Same as Issued By DoDAAC (see Block #7)
Pay DODAAC: See Block #27 of the award
*Federal Supply Classification Code: Z163
ADDITIONAL EMAIL NOTIFICATIONS:
1. mary.harriott@eglin.af.mil Mary Harriott, Contract Specialist (AAC/PKOA)
2. kimberly.welch@eglin.af.mil Kinberly Welch, Contracting Officer (AAC/PKOA)
3. pablo.cruz@eglin.af.mil Pablo Cruz, Engineer (96 CEG/CEPDR)
4. mark.nelson@eglin.af.mil Mark Nelson, Inspector (96 CEG/CEPDR)
Payments may be expedited electronically via the Internet through the Wide Area Work Flow (WAWF) system.
WAWF may be accessed at https://wawf.eb.mil WAWF Training may be accessed online at http://www.wawftraining.com Payment information may be accessed using the DFAS website at http://www.dod.mil/dfas/ (may also be accessed through WAWF website. Log on and click on “Pay Status” shown in left-hand column)
In order to inquire on the status of your payment, DFAS will need your contract number or invoice number. You may access WAWF to check the status of your in. Log in, click on My Pay Status (in the left column of the page), scroll to bottom portion of page, see Commercial Pay and click on Vendor Pay Inquiry. Input your invoice data to access status.
If DFAS has processed your payment, it should be deposited into your bank account approximately 31 days after THEIR process date.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .