Responses_to_Q&A.docx
DOCX document 12 KB Posted
- Attached to
- Fans Lighting Hanger 750 Federal contract opportunity
- Solicitation number
- FA2521-19-Q-B036
About this file
Responses to contractor questions
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Response_to_questions_pst_amndmnt.docx | DOCX document | |
| 750_136-7_E_6-7.pdf | ||
| 750_60-08-211_E_13-13.pdf | ||
| 750_60-08-211_E_11-13.pdf | ||
| 750_60-08-211_E_12-13.pdf | ||
| Combined_Synopsis_update_AMENDED.docx | DOCX document | |
| 750_207-5_E_1-1.pdf | ||
| 750_136-7_E_5-7.pdf | ||
| 750_84-4_E_1-1.pdf | ||
| Combined_Synopsis_update.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Responses to Q&A for Fans and Lighting in Hanger 750;
FA2521-19-Q-B036
1 Aug 19
Are the hanger doors open mostly throughout the day and during hanger use? Are there situations during use where they are closed?
Answer: Hanger doors are mostly open during the day, they are closed during adverse weather.
Are there drops in for the fans?
Answer: No drops for the fans that I know of
Is there hanging conduit to plug into?
Answer: I see conduit that the lights use so I assume they could tie into that
Can we have schematic for the hanger/where are the circuit panels located/wiring diagrams/drawings?
Schematics in amended attachment.
Netting is fabric or wire?
Answer: Fabric
Is there distance/clearance to be maintain by foam suppression system?
Schematics in amended attachment.
Hours allowed for contractor to work?\ Answer: we have people in the hanger from 0600-0100 Mon-Fri