SOW-Mobile_Recruiting_Office.docx

DOCX document 17 KB Posted

Attached to
Multi-wide Modular Office Federal contract opportunity
Solicitation number
F9L3CE5257A001
Issued by
Department of the Army Oklahoma Army National Guard

About this file

Statement of Work

View the file

Other files for this federal contract opportunity

Other files attached to Multi-wide Modular Office, newest first.
File Type Posted
Questions_and_answers_for_Multi-wide_Modular_Office_21_Sep_2015.pdf PDF
Questions_and_answers_for_Multi-wide_Modular_Office_19_Sep_2015.pdf PDF
SOW-Recruiting_Office_Amendment_1.pdf PDF
Office_Layout.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Mobile Office for Recruiting Personnel 13 Sept 2015

1. The contractor shall provide all labor, material, tools, equipment and transportation necessary to complete the work identified in the plans and this Statement of Work.

2. All debris is to be disposed of off Base.

3. The contractor shall apply all safety procedures required by local, state and federal regulations.

4. All work to be performed 7:00 AM to 5:30 PM Monday thru Thursday. If alternate work schedule is desired it must be requested in writing and approved by CE and Security 48 hours prior to the desired schedule.

5. The contractor will not be responsible for moving furniture or moveable partitions. The movement and replacement of furniture will be the responsibility of the OKANG and coordinated with the contractor.

6. The contractor shall coordinate all work with a representative of the CE office.

7. Refer to any and all sketches, plans, specifications and this SOW included with this Request for Proposal.

8. Mobile office trailer will be 36’x60’ and approximately 2,160 SF. It will consist of seven 12’x12’ office rooms with CAT6 network capability. It will consist of a break room/kitchen with running water and sink. It will consist of a common area/waiting area. It will consist of two storage closets, no less than 3’x5’. It will have central HVAC. Two separate bathrooms (male and female) that are ADA compliant. Flooring will be ceramic tile. Walls will be standard sheetrock/gypsum. It will consist of an ADA ramp and separate stairs for access to the trailer. Exterior doors will be 36”x80” and interior doors will be 32”x80”. Utilities will be all electric. Standard drip rail guttering will be installed around the trailer. Skirting will be installed around the bottom of the trailer.

9. Proposals will include all delivery and set-up charges.

10. Floor plan specification sheet is attached.