Q A_-_30_Aug_2016.pdf
PDF 9 KB Posted
- Attached to
- Ventilation Upgrade Federal contract opportunity
- Solicitation number
- F3QCCM5338A001
About this file
Answers to questions - 30 Aug 2016
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SOW_-_2_Jun_2016.pdf | ||
| Q A_-_26_Aug_2016.pdf | ||
| Wage_Determination_2015-2139_Rev_4_Dated_8_Jul_2016.pdf | ||
| Appendix_C.pdf | ||
| CDRL_A004-Signed.pdf | ||
| CDRL_A003-Signed.pdf | ||
| CDRLs_A001-A002-Signed.pdf | ||
| RFQ.doc | DOC document | |
| dust_collector_layout.pdf | ||
| Images_Reference.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers - F3QCCM5338A001
30 Aug 2016
Q1: Looking through the SOW , I do not see where any T&B or controls is required . Please clarify?
A1: The supply fan controls are addressed in the last bullet of section 2.2 (1) of the SOW. The new fan controls need to utilize the existing control cabinet for the current fans. The dust collectors controls are addressed in the last couple bullets of section 2.2 (2) of the SOW. The dust collectors fans are to be controlled by an integrated control panel. These panels need to be tied into the existing control cabinet.
Q2: I am a supplier of the products required on this project. Is there a website I can view that lists the specifications for the project? All I have received is the RFQ document from several of the contractors.
A2: The SOW is now on FBO. Due to this error, the Government has extended the due date of responses to noon on Tuesday, 6 September 2016.