Atch_7_F17PS00722_1-4.pdf

PDF 101 KB Posted

Attached to
BOZEMAN WATER CLARIFIER Federal contract opportunity
Solicitation number
F17PS00722
Issued by
Department of the Interior Fish and Wildlife Service Region 9 Headquarters

About this file

Atch 7 Contract Form SF1442 Pgs 1-4

View the file

Other files for this federal contract opportunity

Other files attached to BOZEMAN WATER CLARIFIER, newest first.
File Type Posted
Sol_F17PS00722_Amd_0002.pdf PDF
F17PS00722-001.pdf PDF
Atch_4_Bozeman_FTC_Submittals.pdf PDF
Atch_6_Bozeman_FTC_Past_Perf_Quest.doc DOC document
Atch_1_Bozeman_FTC_Clarifier_Spec.pdf PDF
Atch_5_Bozeman_FTC_Wage_Det_MT34.pdf PDF
Sol_F17PS00722.pdf PDF
Atch_3_Bozeman_FTC_Drawing_Coversheet.pdf PDF
Atch_2_Bozeman_FTC_Clarifier_Drawings.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

0040335791

FWS, DIVISION OF CONTRACTING AND GE

LAKE PLAZA NORTH

134 UNION BOULEVARD

LAKEWOOD CO 80228-1807

F06

CONTRACTING AND GENERAL SERVICES

LAKE PLAZA NORTH

134 UNION BLVD

LAKEWOOD CO 80228

Timothy Officer 303 236-4320

1x 06/15/2017

F17PS00722

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

THIS SOLICITATION IS NOT A SEALED BID ACQUISITION; SEE PROPOSAL SUBMISSION

INSTRUCTIONS PAGES 30-34.

Contractor will furnish all material, labor, equipment and supervision to

Rehabilitate Bozeman Water Clarifier System. Repairing and upgrading the system will comprise of demolishing and removing the components of the existing lamella clarifier, surface preparation of sediment basin walls and floors to be resurfaced with a protective coating, new catwalks and handrails to be added to the top of the sedimentation basins, demolition of existing piping and electrical, providing new piping and electrical, and providing a new auger screen to filter effluent leaving the sedimentation basins. The CONTRACTOR shall bypass 500 to 800 gpm of flow from the facility directly to Bridger Creek to dewater the work area, by making temporary modifications to an existing concrete drainage structure. All work will be in accordance with the attached statement of work, specifications, drawings and industry standard practice for Montana.

GENERAL INFORMATION:

Continued ...

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 60 calendar days and complete it within ________________ ________________ calendar days after receiving

SEE FAR 52.211-10

07/14/2017

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

FWS, DIVISION OF CONTRACTING AND GE

LAKE PLAZA NORTH

134 UNION BOULEVARD

Lakewood CO 80228-1807

F06

Jon Morse

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

STANDARD FORM 1442 (REV. 4-85) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 35

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

F17PS00722

The magnitude of the project is $250,000.00 -

$500,000.00, with a budget toward the middle to higher range of the magnitude. The total performance period is 90 calendar days. The NAICS code is 237110, Water and Sewer Line and Related

Structures Construction and the size standard is

$36.5 million. All questions regarding subject requirement shall be submitted in writing to the

U.S. Fish and Wildlife, attention Mr. Tim

Officer, 134 Union Blvd., Lakewood CO 80228 or fax to (303) 236-4791. E-mail questions may be sent to tim_officer@fws.gov. Please include the solicitation number, your company name, address, telephone number, and contact name and fax number on any correspondence mailed or faxed to our office.

LOCATION AND INSPECTION OF THE SITE:

The Bozeman Fish Technology Center is located at

4050 Bridger Canyon Road, Bozeman, MT 59715.

Offerors are encouraged to visit the work area in order to examine the existing site conditions.

Contact the (BFTC) maintenance manager, Jason

Ilgen (406) 994-9946 jason_ilgen@fws.gov or the

Director, Bob Muth 406-994-9902, robert_muth@fws.gov to make arrangements to visit the site.

Your attention is invited to review Federal

Acquisition Regulation (FAR) provision 52.236-3, site investigation and conditions affecting the work (Apr. 1984). Failure of the contractor to ascertain the nature, location, and conditions which affect the work will not relieve the contractor from the responsibility for successfully performing the work, without additional expense to the government.

SEE Bond and Insurance requirements pages 9 and 18

SEE Site Visit information page 29

SEE Proposal Submission Instructions page 30-34 and Proposal Evaluation page 35

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

4 35

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

F17PS00722

Provide your proposal via email to tim_officer@fws.gov

Legacy Doc #: FWS

Delivery: 10/20/2017

Delivery Location Code: 0008350047

FWS BOZEMAN FISH TECHNOLOGY CENTER

4050 BRIDGER CANYON ROAD

BOZEMAN MT 59715-8433 US

FOB: Destination

Period of Performance: 07/17/2017 to 10/18/2017

00010 BOZEMAN WATER CLARIFIER: provide all materials, equipment, labor, and supervision for the rehabilitation of the existing effluent clarifier system. Repairing and upgrading the system will comprise of demolishing and removing the components of the existing lamella clarifier, surface preparation of sediment basin walls and floors to be resurfaced with a protective coating, new catwalks and handrails to be added to the top of the sedimentation basins, demolition of existing piping and electrical, providing new piping and electrical, and providing a new auger screen to filter effluent leaving the sedimentation basins. The CONTRACTOR shall bypass 500 to 800 gpm of flow from the facility directly to Bridger Creek to dewater the work area, by making temporary modifications to an existing concrete drainage structure.

Period of Performance: 07/19/2017 to 10/20/2017